UDRP/PWD/06/69/RD/066a Agreement signed
Project: UDRP-RB Package No.: 77 Package Name: UDRP/PWD/06/69/RD/066a Sanction Cost: 87.49  lakhs
District: Pauri Block: Kot Constituency: Pauri Circle:
DEA: DEA Pauri DSC: Egis International DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  2274   RamkundGhat to GIC Devprayag Link MR (0.600 KM.) (completed)
Procurement:
Package No.: 77        Package Name: UDRP/PWD/06/69/RD/066a        Tender Date: 28-01-2015        Current Status: Agreement signed        Achieved on Date: 31-07-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/06/69/RD/066a        Contractor Name: Bharat Singh Rawat       
Start Date: 07-08-2015        Intended Completion Date: 31-01-2017        Original End Date:  06-11-2016
Total Bond Cost: 7790651.52 (77.91 lakhs)        Variation Cost: -532531.61 (-5.33 lakhs)     Hence Total Bond Cost is   7258119.91 (72.58 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 225910 for 58 days        LD Analysis for Milestone2: calculated LD is Rs 233700 for 60 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence0.38 KM1.330.38 KM0.38 KM1.841.33
2.R/Wall, B/ Wall Type Protection works448.00 m45.23448.00 m448.00 m62.4845.23
3.GSB/RBI/G-10.65 KM0.780.65 KM0.65 KM1.080.78
4.G-20.68 KM0.710.68 KM0.68 KM0.980.71
5.G-30.68 KM1.020.68 KM0.68 KM1.411.02
6.BM i/c Prime Coat, Tack Coat0.68 KM6.880.68 KM0.68 KM9.56.88
7.Culverts/Scupper 1.00 No3.101.00 No1.00 No4.283.10
8.longitudinal Drain675.00 m7.54675.00 m675.00 m10.427.54
9.Crash Barrier0.00 m0.000.00 m0.00 m00.00
10.Parapet80.00 No2.2980.00 No80.00 No3.162.29
11.Road Furniture6.00 No0.356.00 No6.00 No0.480.35
12.Other Allied Works & Finishing Work 1.00 Job3.161.00 Job1.00 Job4.373.16
Total Amount: 72.39 100   72.39
Remarks: No Remarks       Work Program Made On: 10-05-2016       Updation of work program on: 26-09-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.27-February-201612.44  lakhs
2.14-March-20167.76  lakhs
3.08-April-20165.15  lakhs
4.13-May-20162.28  lakhs
5.14-July-20167.41  lakhs
6.30-September-201613.02  lakhs
7.25-January-201716.27  lakhs
8.30-June-20178.07  lakhs
Total 72.4  lakhs
% Payment 99.75 %
Advance Amount:  17.68  lakhs        Recovered Amount:  17.68  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 43     No. of Test Done : 47      No. of Test Passed : 43      No. of Test Failed : 4   Test report of this package
Number of Pics Available on Web Repository: 19
Number of Notice(s) issued: 97

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.28-11-20170+250Discussion... During Site visit by world bank team....Noshad QureshiSite SupervisorDSC2 R&B WB Pauri See Pic
2.28-11-20170+200Discussion... during Site visit by world bank team....Noshad QureshiSite SupervisorDSC2 R&B WB Pauri See Pic
3.24-12-20160+000 to 0+050Providing concreat M15 in KC drainAmit KumarJEUDRP R&B Pauri See Pic
4.20-11-20160+080Progress of HP Filling in R/WAmit KumarJEUDRP R&B Pauri See Pic
5.28-09-20160/7Construction of R/WDeepak GoelREDSC2 R&B WB Pauri See Pic
6.21-09-20160+445 to 0+475Providing M10 concreat for KC drain.Amit KumarJEUDRP R&B Pauri See Pic
7.21-09-20160+440Progress of excavation & slope stablation & compacting for KC drain.Amit KumarJEUDRP R&B Pauri See Pic
8.20-09-20160/7construction of R/W with 9 layer of plum wallNoshad QureshiSite SupervisorDSC2 R&B WB Pauri See Pic
9.20-09-20160/20construction of kc drain in progressNoshad QureshiSite SupervisorDSC2 R&B WB Pauri See Pic
10.10-09-20160+065 to 0+120Progress of R/WAmit KumarJEUDRP R&B Pauri See Pic
11.24-05-20160+110Progress of wire cratesAmit KumarJEUDRP R&B Pauri See Pic
12.16-03-20160+080Progress of plum in B/WAmit KumarJEUDRP R&B Pauri See Pic
13.07-03-20160+070Progress off Plum in R/WAmit KumarJEUDRP R&B Pauri See Pic
14.04-03-20160+065Progress of Plum in B/WAmit KumarJEUDRP R&B Pauri See Pic
15.01-03-20160+178Progress of scuperAmit KumarJEUDRP R&B Pauri See Pic
16.29-02-20160/3Construction of plum concreteNoshad QureshiSite SupervisorDSC2 R&B WB Pauri See Pic
17.02-02-20160+350Collie wallAmit KumarJEUDRP R&B Pauri See Pic
18.12-01-20160+415Breast wallNoshad QureshiSite SupervisorDSC2 R&B WB Pauri See Pic
19.09-01-20160+410Hill cuttingAmit KumarJEUDRP R&B Pauri See Pic