UDRP/PWD/06/69/RD/066a
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
77 |
Package Name: |
UDRP/PWD/06/69/RD/066a |
Sanction Cost: |
87.49 lakhs |
District: |
Pauri |
Block: |
Kot |
Constituency: |
Pauri |
Circle: |
|
DEA: |
DEA Pauri |
DSC: |
Egis International |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 2274 RamkundGhat to GIC Devprayag Link MR (0.600 KM.) (completed) |
|
Procurement: |
Package No.: 77
Package Name: UDRP/PWD/06/69/RD/066a
Tender Date: 28-01-2015
Current Status: Agreement signed
Achieved on Date: 31-07-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/06/69/RD/066a
Contractor Name: Bharat Singh Rawat
|
Start Date: 07-08-2015
Intended Completion Date: 31-01-2017
Original End Date: 06-11-2016
|
Total Bond Cost: 7790651.52 (77.91 lakhs)
Variation Cost: -532531.61 (-5.33 lakhs) Hence Total Bond Cost is 7258119.91 (72.58 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 225910 for 58 days
LD Analysis for Milestone2: calculated LD is Rs 233700 for 60 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 0.38 KM | 1.33 | 0.38 KM | 0.38 KM | 1.84 | 1.33 | 2. | R/Wall, B/ Wall Type Protection works | 448.00 m | 45.23 | 448.00 m | 448.00 m | 62.48 | 45.23 | 3. | GSB/RBI/G-1 | 0.65 KM | 0.78 | 0.65 KM | 0.65 KM | 1.08 | 0.78 | 4. | G-2 | 0.68 KM | 0.71 | 0.68 KM | 0.68 KM | 0.98 | 0.71 | 5. | G-3 | 0.68 KM | 1.02 | 0.68 KM | 0.68 KM | 1.41 | 1.02 | 6. | BM i/c Prime Coat, Tack Coat | 0.68 KM | 6.88 | 0.68 KM | 0.68 KM | 9.5 | 6.88 | 7. | Culverts/Scupper | 1.00 No | 3.10 | 1.00 No | 1.00 No | 4.28 | 3.10 | 8. | longitudinal Drain | 675.00 m | 7.54 | 675.00 m | 675.00 m | 10.42 | 7.54 | 9. | Crash Barrier | 0.00 m | 0.00 | 0.00 m | 0.00 m | 0 | 0.00 | 10. | Parapet | 80.00 No | 2.29 | 80.00 No | 80.00 No | 3.16 | 2.29 | 11. | Road Furniture | 6.00 No | 0.35 | 6.00 No | 6.00 No | 0.48 | 0.35 | 12. | Other Allied Works & Finishing Work | 1.00 Job | 3.16 | 1.00 Job | 1.00 Job | 4.37 | 3.16 |
Total Amount: |
72.39 |
|
100 |
72.39 |
|
Remarks:
No Remarks
Work Program Made On:
10-05-2016
Updation of work program on:
26-09-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 27-February-2016 | 12.44 lakhs |
2. | 14-March-2016 | 7.76 lakhs |
3. | 08-April-2016 | 5.15 lakhs |
4. | 13-May-2016 | 2.28 lakhs |
5. | 14-July-2016 | 7.41 lakhs |
6. | 30-September-2016 | 13.02 lakhs |
7. | 25-January-2017 | 16.27 lakhs |
8. | 30-June-2017 | 8.07 lakhs |
Total |
72.4 lakhs |
% Payment |
99.75 % |
|
Advance Amount: 17.68 lakhs
Recovered Amount: 17.68 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 19 |
Number of Notice(s) issued: 97 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 28-11-2017 | 0+250 | Discussion...
During Site visit by world bank team.... | Noshad Qureshi | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
2. | 28-11-2017 | 0+200 | Discussion...
during Site visit by world bank team.... | Noshad Qureshi | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
3. | 24-12-2016 | 0+000 to 0+050 | Providing concreat M15 in KC drain | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
4. | 20-11-2016 | 0+080 | Progress of HP Filling in R/W | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
5. | 28-09-2016 | 0/7 | Construction of R/W | Deepak Goel | RE | DSC2 R&B WB Pauri | See Pic |
6. | 21-09-2016 | 0+445 to 0+475 | Providing M10 concreat for KC drain. | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
7. | 21-09-2016 | 0+440 | Progress of excavation & slope stablation & compacting for KC drain. | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
8. | 20-09-2016 | 0/7 | construction of R/W with 9 layer of plum wall | Noshad Qureshi | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
9. | 20-09-2016 | 0/20 | construction of kc drain in progress | Noshad Qureshi | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
10. | 10-09-2016 | 0+065 to 0+120 | Progress of R/W | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
11. | 24-05-2016 | 0+110 | Progress of wire crates | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
12. | 16-03-2016 | 0+080 | Progress of plum in B/W | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
13. | 07-03-2016 | 0+070 | Progress off Plum in R/W | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
14. | 04-03-2016 | 0+065 | Progress of Plum in B/W | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
15. | 01-03-2016 | 0+178 | Progress of scuper | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
16. | 29-02-2016 | 0/3 | Construction of plum concrete | Noshad Qureshi | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
17. | 02-02-2016 | 0+350 | Collie wall | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
18. | 12-01-2016 | 0+415 | Breast wall | Noshad Qureshi | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
19. | 09-01-2016 | 0+410 | Hill cutting | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
|
|