UDRP/PWD/06/69/RD/066
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
76 |
Package Name: |
UDRP/PWD/06/69/RD/066 |
Sanction Cost: |
736.44 lakhs |
District: |
Pauri |
Block: |
Kot |
Constituency: |
Pauri |
Circle: |
Tehri WB Circle |
DEA: |
DEA Pauri |
DSC: |
Egis International |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 2121 Arkani-Khandukhal-Muchyali Dewal Charakot MR (17.500 KM.) (completed) |
|
Procurement: |
Package No.: 76
Package Name: UDRP/PWD/06/69/RD/066
Tender Date: 28-01-2015
Current Status: Agreement signed
Achieved on Date: 16-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/06/69/RD/066
Contractor Name: Rajendra Singh Kuldeep Singh
|
Start Date: 22-06-2015
Intended Completion Date: 30-06-2017
Original End Date: 21-09-2016
|
Total Bond Cost: 69461928.82 (694.62 lakhs)
Variation Cost: -13747413.53 (-137.47 lakhs) Hence Total Bond Cost is 55714515.29 (557.15 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 3334176 for 96 days
LD Analysis for Milestone2: calculated LD is Rs 7501896 for 216 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 1.94 KM | 7.02 | 1.94 KM | 1.94 KM | 1.26 | 7.02 | 2. | R/Wall, B/ Wall Type Protection works | 2862.00 m | 245.42 | 2862.00 m | 2862.00 m | 44.05 | 245.42 | 3. | GSB/RBI/G-1 | 0.73 KM | 0.53 | 0.73 KM | 0.73 KM | 0.1 | 0.53 | 4. | G-2 | 0.73 KM | 0.55 | 0.73 KM | 0.73 KM | 0.1 | 0.55 | 5. | G-3 | 4.79 KM | 13.10 | 4.79 KM | 4.79 KM | 2.35 | 13.10 | 6. | PC/CC i/c Prime Coat, Tack Coat | 14.50 KM | 158.44 | 14.50 KM | 14.50 KM | 28.44 | 158.44 | 7. | Cause Way | 0.00 No | 0.00 | 0.00 No | 0.00 No | 0 | 0.00 | 8. | Culverts/Scupper | 36.00 No | 56.75 | 36.00 No | 36.00 No | 10.19 | 56.75 | 9. | longitudinal Drain | 13830.00 m | 18.14 | 13830.00 m | 13830.00 m | 3.26 | 18.14 | 10. | Crash Barrier | 995.00 m | 22.41 | 995.00 m | 995.00 m | 4.02 | 22.41 | 11. | Parapet | 520.00 No | 13.91 | 520.00 No | 520.00 No | 2.5 | 13.91 | 12. | Road Furniture | 256.00 No | 4.78 | 256.00 No | 256.00 No | 0.86 | 4.78 | 13. | Other Allied Works & Finishing Work | 1.00 Job | 16.09 | 1.00 Job | 1.00 Job | 2.89 | 16.09 |
Total Amount: |
557.14 |
|
100 |
557.14 |
|
Remarks:
No Remarks
Work Program Made On:
01-10-2015
Updation of work program on:
16-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-November-2015 | 40.56 lakhs |
2. | 26-April-2016 | 167.70 lakhs |
3. | 02-September-2016 | 118.26 lakhs |
4. | 31-January-2017 | 60.45 lakhs |
5. | 30-March-2017 | 31.06 lakhs |
6. | 10-April-2017 | 22.66 lakhs |
7. | 30-June-2017 | 30.00 lakhs |
8. | 17-August-2017 | 17.59 lakhs |
9. | 30-December-2017 | 68.87 lakhs |
Total |
557.15 lakhs |
% Payment |
100 % |
|
Advance Amount: 119.52 lakhs
Recovered Amount: 119.52 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 46 |
Number of Notice(s) issued: 94 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 30-05-2017 | Ch -9/7-8, | Seal coat rolling work. | Pradeep Kumar Prabhakar | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
2. | 30-05-2017 | Ch -9/4-5, | Seal coat rolling work. | Pradeep Kumar Prabhakar | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
3. | 17-05-2017 | Ch -9/3-4, | PC laying work. | Pradeep Kumar Prabhakar | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
4. | 12-05-2017 | Ch 10/37-38. | Rolling of seal coat. | Pradeep Kumar Prabhakar | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
5. | 12-05-2017 | Ch -10/38-39 | Rolling of PC. | Pradeep Kumar Prabhakar | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
6. | 08-05-2017 | Ch 10/21-22 | Seal coat laying. | Pradeep Kumar Prabhakar | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
7. | 08-05-2017 | Ch -10/30-31 | PC laying work | Pradeep Kumar Prabhakar | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
8. | 04-05-2017 | Ch-11/26-27 | Seal coat rolling. | Pradeep Kumar Prabhakar | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
9. | 04-05-2017 | Ch -11/17-18. | P C laying work. | Pradeep Kumar Prabhakar | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
10. | 03-05-2017 | Km -12, | Seal coat laying. | Pradeep Kumar Prabhakar | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
11. | 03-05-2017 | 11/38 | Surface Rolling. | Pradeep Kumar Prabhakar | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
12. | 03-05-2017 | 4.250 | Training of environment | Pradeep Kumar Prabhakar | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
13. | 03-05-2017 | Ch -11/30 | Seal coat rolling | Pradeep Kumar Prabhakar | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
14. | 02-05-2017 | Ch-11/30-32. | Seal coat rolling. | Pradeep Kumar Prabhakar | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
15. | 02-05-2017 | Ch -11/33. | P c rolling work. | Pradeep Kumar Prabhakar | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
16. | 26-04-2017 | Ch -11/34-35 | Excavation for kachcha drain. | Pradeep Kumar Prabhakar | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
17. | 24-04-2017 | Ch -11/0-5, | G3compacted and sprinkling | Pradeep Kumar Prabhakar | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
18. | 20-04-2017 | Ch -11/38-39. | G3 compaction and sprinkling. | Pradeep Kumar Prabhakar | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
19. | 20-04-2017 | Ch-10/27 | G3 compaction and sprinkling. | Pradeep Kumar Prabhakar | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
20. | 15-04-2017 | Ch-10/27-28 | G3compact and sprinkling. | Pradeep Kumar Prabhakar | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
|
|