Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/06/69/RD/066 Agreement signed
Project: UDRP-RB Package No.: 76 Package Name: UDRP/PWD/06/69/RD/066 Sanction Cost: 736.44  lakhs
District: Pauri Block: Kot Constituency: Pauri Circle: Tehri WB Circle
DEA: DEA Pauri DSC: Egis International DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  2121   Arkani-Khandukhal-Muchyali Dewal Charakot MR (17.500 KM.) (completed)
Procurement:
Package No.: 76        Package Name: UDRP/PWD/06/69/RD/066        Tender Date: 28-01-2015        Current Status: Agreement signed        Achieved on Date: 16-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/06/69/RD/066        Contractor Name: Rajendra Singh Kuldeep Singh       
Start Date: 22-06-2015        Intended Completion Date: 30-06-2017        Original End Date:  21-09-2016
Total Bond Cost: 69461928.82 (694.62 lakhs)        Variation Cost: -13747413.53 (-137.47 lakhs)     Hence Total Bond Cost is   55714515.29 (557.15 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 3334176 for 96 days        LD Analysis for Milestone2: calculated LD is Rs 7501896 for 216 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence1.94 KM7.021.94 KM1.94 KM1.267.02
2.R/Wall, B/ Wall Type Protection works2862.00 m245.422862.00 m2862.00 m44.05245.42
3.GSB/RBI/G-10.73 KM0.530.73 KM0.73 KM0.10.53
4.G-20.73 KM0.550.73 KM0.73 KM0.10.55
5.G-34.79 KM13.104.79 KM4.79 KM2.3513.10
6.PC/CC i/c Prime Coat, Tack Coat14.50 KM158.4414.50 KM14.50 KM28.44158.44
7.Cause Way0.00 No0.000.00 No0.00 No00.00
8.Culverts/Scupper 36.00 No56.7536.00 No36.00 No10.1956.75
9.longitudinal Drain13830.00 m18.1413830.00 m13830.00 m3.2618.14
10.Crash Barrier995.00 m22.41995.00 m995.00 m4.0222.41
11.Parapet520.00 No13.91520.00 No520.00 No2.513.91
12.Road Furniture256.00 No4.78256.00 No256.00 No0.864.78
13.Other Allied Works & Finishing Work 1.00 Job16.091.00 Job1.00 Job2.8916.09
Total Amount: 557.14 100   557.14
Remarks: No Remarks       Work Program Made On: 01-10-2015       Updation of work program on: 16-11-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-November-201540.56  lakhs
2.26-April-2016167.70  lakhs
3.02-September-2016118.26  lakhs
4.31-January-201760.45  lakhs
5.30-March-201731.06  lakhs
6.10-April-201722.66  lakhs
7.30-June-201730.00  lakhs
8.17-August-201717.59  lakhs
9.30-December-201768.87  lakhs
Total 557.15  lakhs
% Payment 100 %
Advance Amount:  119.52  lakhs        Recovered Amount:  119.52  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 296     No. of Test Done : 324      No. of Test Passed : 296      No. of Test Failed : 28   Test report of this package
Number of Pics Available on Web Repository: 46
Number of Notice(s) issued: 94

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.30-05-2017Ch -9/7-8,Seal coat rolling work.Pradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
2.30-05-2017Ch -9/4-5,Seal coat rolling work.Pradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
3.17-05-2017Ch -9/3-4,PC laying work.Pradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
4.12-05-2017Ch 10/37-38.Rolling of seal coat.Pradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
5.12-05-2017Ch -10/38-39Rolling of PC.Pradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
6.08-05-2017Ch 10/21-22Seal coat laying.Pradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
7.08-05-2017Ch -10/30-31PC laying workPradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
8.04-05-2017Ch-11/26-27Seal coat rolling.Pradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
9.04-05-2017Ch -11/17-18.P C laying work.Pradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
10.03-05-2017Km -12,Seal coat laying.Pradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
11.03-05-201711/38Surface Rolling.Pradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
12.03-05-20174.250Training of environmentPradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
13.03-05-2017Ch -11/30Seal coat rollingPradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
14.02-05-2017Ch-11/30-32.Seal coat rolling.Pradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
15.02-05-2017Ch -11/33.P c rolling work.Pradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
16.26-04-2017Ch -11/34-35Excavation for kachcha drain.Pradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
17.24-04-2017Ch -11/0-5,G3compacted and sprinklingPradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
18.20-04-2017Ch -11/38-39.G3 compaction and sprinkling.Pradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
19.20-04-2017Ch-10/27G3 compaction and sprinkling.Pradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
20.15-04-2017Ch-10/27-28G3compact and sprinkling.Pradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic