Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/06/69/RD/065 Agreement signed
Project: UDRP-RB Package No.: 75 Package Name: UDRP/PWD/06/69/RD/065 Sanction Cost: 625.35  lakhs
District: Pauri Block: Kot Constituency: Pauri Circle: Tehri WB Circle
DEA: DEA Pauri DSC: Egis International DSC Scope: Design and Supervision No.of Sub project : 2
Subproject in this package
1  2120   Arkani-Janasu-Khandukhal MR (5.200 KM.) (completed)
2  2270   Uffalda-Dhelchauri MR (7.500 KM.) (completed)
Procurement:
Package No.: 75        Package Name: UDRP/PWD/06/69/RD/065        Tender Date: 20-11-2014        Current Status: Agreement signed        Achieved on Date: 16-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/06/69/RD/065        Contractor Name: Divya Jyoti Construction       
Start Date: 22-06-2015        Intended Completion Date: 15-03-2017        Original End Date:  21-09-2016
Total Bond Cost: 57567580.74 (575.68 lakhs)        Variation Cost: 1551277.99 (15.51 lakhs)     Hence Total Bond Cost is   59118858.73 (591.19 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 374192 for 13 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence2.89 KM9.802.89 KM2.89 KM1.669.80
2.R/Wall, B/ Wall Type Protection works1744.00 m176.601744.00 m1744.00 m30176.60
3.GSB/RBI/G-10.38 KM3.930.38 KM0.38 KM0.63.93
4.G-20.55 KM3.050.55 KM0.55 KM0.463.05
5.G-32.69 KM15.342.69 KM2.69 KM2.6715.34
6.PC/CC i/c Prime Coat, Tack Coat12.70 KM222.1712.70 KM12.70 KM38.5222.17
7.Cause Way6.00 No20.596.00 No6.00 No3.2720.59
8.Culverts/Scupper 34.00 No72.1234.00 No34.00 No12.9372.12
9.longitudinal Drain12052.00 m25.9712052.00 m12052.00 m4.5625.97
10.Crash Barrier0.00 m0.000.00 m0.00 m00.00
11.Parapet372.00 No8.98372.00 No372.00 No1.618.98
12.Road Furniture142.00 No10.24142.00 No142.00 No1.6310.24
13.Other Allied Works & Finishing Work 2.00 Job12.112.00 Job2.00 Job2.1112.11
Total Amount: 580.9 100   580.9
Remarks: No Remarks       Work Program Made On: 03-10-2015       Updation of work program on: 29-03-2019      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-November-2015126.32  lakhs
2.08-April-2016115.17  lakhs
3.13-May-201660.58  lakhs
4.04-August-2016168.09  lakhs
5.01-September-201886.56  lakhs
6.28-February-201925.87  lakhs
Total 582.59  lakhs
% Payment 98.54 %
Advance Amount:  198.11  lakhs        Recovered Amount:  198.11  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 207     No. of Test Done : 217      No. of Test Passed : 207      No. of Test Failed : 10   Test report of this package
Number of Pics Available on Web Repository: 28
Number of Notice(s) issued: 118

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.07-04-2017Ch-0/3-5,.ParapetPradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
2.07-04-2017Ch-0/0-3,Breast wall.Pradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
3.14-03-2017Billkedar townEMP implementation training by Environmental Expert of EgisDeepak GoelREDSC2 R&B WB Pauri See Pic
4.11-02-2017km-01;ch-5.175.pc work.Pradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
5.09-02-2017km-5;ch-4/20-21R/wall.Pradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
6.09-02-2017km-5;ch-4.500.R/wall.Pradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
7.09-02-20177.250iB/wall.Pradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
8.09-02-20177.250bB/wallPradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
9.06-02-2017Ufalda dehalchauri MR km-9 ch-9.400R/wall dryHema MallJEUDRP R&B Pauri See Pic
10.06-02-2017Ufalda dehalchauri MR km-9 ch-9.400B/wallHema MallJEUDRP R&B Pauri See Pic
11.06-02-2017Ufalda dehalchauri MR km-11 ch-10.625Pc workHema MallJEUDRP R&B Pauri See Pic
12.06-02-2017Ufalda dehalchauri MR km-9 ch-8.850Banded R/wallHema MallJEUDRP R&B Pauri See Pic
13.06-02-2017Ufalda dehalchauri MR km-6 ch-5.125ParapetHema MallJEUDRP R&B Pauri See Pic
14.06-02-2017Ufalda dehalchauri MR km-6 ch-5.025Pc workHema MallJEUDRP R&B Pauri See Pic
15.06-02-2017Km-5 ch-4.025Pc workHema MallJEUDRP R&B Pauri See Pic
16.06-02-2017Km-5, ch-4.525Banded r/wallHema MallJEUDRP R&B Pauri See Pic
17.06-02-2017Km-5 ch-4.475Banded r/wallHema MallJEUDRP R&B Pauri See Pic
18.06-02-2017Km-3 ch -2.300Banded R/wallHema MallJEUDRP R&B Pauri See Pic
19.06-02-2017Km-1, ch-1.750Pc workHema MallJEUDRP R&B Pauri See Pic
20.06-02-2017Arkani janashu khanukhal m/r,km-1, ch-0/6Pc work & b/wallHema MallJEUDRP R&B Pauri See Pic