Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/04/44/RD/064 Agreement signed
Project: UDRP-RB Package No.: 74 Package Name: UDRP/PWD/04/44/RD/064 Sanction Cost: 417.14  lakhs
District: Tehri Block: Narendra Nagar Constituency: Narendra Nagar Circle: Tehri WB Circle
DEA: DEA Tehri DSC: Egis International DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  2652   Chaka-Pendarsh Motor raod (8.850 KM.) (completed)
Procurement:
Package No.: 74        Package Name: UDRP/PWD/04/44/RD/064        Tender Date: 15-12-2015        Current Status: Agreement signed        Achieved on Date: 06-04-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/04/44/RD/064        Contractor Name: O. P. Builders       
Start Date: 13-04-2016        Intended Completion Date: 31-12-2017        Original End Date:  12-07-2017
Total Bond Cost: 41156128.5 (411.56 lakhs)        Variation Cost: 3803382.19 (38.03 lakhs)     Hence Total Bond Cost is   44959510.69 (449.6 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 61734 for 3 days        LD Analysis for Milestone2: calculated LD is Rs 2345892 for 114 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.R/Wall, B/ Wall Type Protection works1313.00 m30.271090.00 m1090.00 m7.9930.27
2.GSB/RBI/G-10.00 KM0.000.00 KM0.00 KM00.00
3.G-22.85 KM19.092.49 KM2.49 KM5.0419.09
4.G-32.85 KM19.222.93 KM2.93 KM5.0719.22
5.PC/CC i/c Prime Coat, Tack Coat8.85 KM8.628.85 KM8.85 KM2.288.62
6.BM i/c Prime Coat, Tack Coat8.85 KM161.198.79 KM8.79 KM42.53161.19
7.SDBC i/c Tackcoat8.85 KM100.258.79 KM8.79 KM26.45100.25
8.Cause Way3.00 No3.052.00 No2.00 No0.813.05
9.Culverts/Scupper 13.00 No26.4714.00 No14.00 No6.9926.47
10.longitudinal Drain584.00 m10.158550.00 m8550.00 m2.6810.15
11.Crash Barrier0.00 m0.000.00 m0.00 m00.00
12.Road Furniture36.00 No0.6736.00 No36.00 No0.180.67
Total Amount: 378.98 100   378.98
Remarks: No Remarks       Work Program Made On: 03-07-2016       Updation of work program on: 15-11-2018      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-July-201635.02  lakhs
2.08-September-201631.50  lakhs
3.30-September-201648.56  lakhs
4.26-December-201610.25  lakhs
5.29-May-201731.91  lakhs
6.30-June-2017264.05  lakhs
7.12-October-20174.45  lakhs
8.28-November-201710.46  lakhs
9.30-May-201812.63  lakhs
10.30-November-20182.91  lakhs
Total 451.74  lakhs
% Payment 100.48 %
Advance Amount:  222.41  lakhs        Recovered Amount:  222.41  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 1110     No. of Test Done : 1151      No. of Test Passed : 1110      No. of Test Failed : 41   Test report of this package
Number of Pics Available on Web Repository: 194
Number of Notice(s) issued: 69

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.08-03-2018Ch 8.000JointKuldeep Kumar KaranwalJEUDRP R&B Tehri See Pic
2.24-01-20181.800Site inspection by EE Mam WB PWD TehriSudhir Kumar AEAEUDRP R&B Tehri See Pic
3.06-12-2017Ch 0.400Parapets with white wasKuldeep Kumar KaranwalJEUDRP R&B Tehri See Pic
4.29-06-20170.200Core cuttingSudhir Kumar AEAEUDRP R&B Tehri See Pic
5.08-06-20178.700SDBC work in progressSudhir Kumar AEAEUDRP R&B Tehri See Pic
6.08-06-20177.435Site inspection by SE Sir TehriSudhir Kumar AEAEUDRP R&B Tehri See Pic
7.06-06-20177.887Bm rollingKuldeep Kumar KaranwalJEUDRP R&B Tehri See Pic
8.06-06-20177.900Laying of BMSudhir Kumar AEAEUDRP R&B Tehri See Pic
9.02-06-20177+875BM laying in Progress.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
10.01-06-2017Ch 8.200Bm rollingKuldeep Kumar KaranwalJEUDRP R&B Tehri See Pic
11.31-05-20178.700Rolling of BMSudhir Kumar AEAEUDRP R&B Tehri See Pic
12.31-05-20171.250Checking thickness of BM / SDBC by QC DSC 2 Tehri . AE.JE WB Tehri .n Contractor,s Engineer . It found 75 mm (BM +SDBC)Sudhir Kumar AEAEUDRP R&B Tehri See Pic
13.16-05-20176.250Sieve test for G3Sudhir Kumar AEAEUDRP R&B Tehri See Pic
14.16-05-2017Laying of G35.400Sudhir Kumar AEAEUDRP R&B Tehri See Pic
15.16-05-20178.500G3 testingSudhir Kumar AEAEUDRP R&B Tehri See Pic
16.09-05-2017Ch7.300Parti filling under constructionKuldeep Kumar KaranwalJEUDRP R&B Tehri See Pic
17.27-04-20177+840Site visit by Team Leader.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
18.24-04-20177+450Gradation test for WBM G3.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
19.13-04-20173.975Meeting/ Discuss about problems with Jakholi villagers by AE WB TehriSudhir Kumar AEAEUDRP R&B Tehri See Pic
20.11-04-2017Ch. 3.980Site visit AE sir for villagers village pathKuldeep Kumar KaranwalJEUDRP R&B Tehri See Pic