UDRP/PWD/04/44/RD/064
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
74 |
Package Name: |
UDRP/PWD/04/44/RD/064 |
Sanction Cost: |
417.14 lakhs |
District: |
Tehri |
Block: |
Narendra Nagar |
Constituency: |
Narendra Nagar |
Circle: |
Tehri WB Circle |
DEA: |
DEA Tehri |
DSC: |
Egis International |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 2652 Chaka-Pendarsh Motor raod (8.850 KM.) (completed) |
|
Procurement: |
Package No.: 74
Package Name: UDRP/PWD/04/44/RD/064
Tender Date: 15-12-2015
Current Status: Agreement signed
Achieved on Date: 06-04-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/04/44/RD/064
Contractor Name: O. P. Builders
|
Start Date: 13-04-2016
Intended Completion Date: 31-12-2017
Original End Date: 12-07-2017
|
Total Bond Cost: 41156128.5 (411.56 lakhs)
Variation Cost: 3803382.19 (38.03 lakhs) Hence Total Bond Cost is 44959510.69 (449.6 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 61734 for 3 days
LD Analysis for Milestone2: calculated LD is Rs 2345892 for 114 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | R/Wall, B/ Wall Type Protection works | 1313.00 m | 30.27 | 1090.00 m | 1090.00 m | 7.99 | 30.27 | 2. | GSB/RBI/G-1 | 0.00 KM | 0.00 | 0.00 KM | 0.00 KM | 0 | 0.00 | 3. | G-2 | 2.85 KM | 19.09 | 2.49 KM | 2.49 KM | 5.04 | 19.09 | 4. | G-3 | 2.85 KM | 19.22 | 2.93 KM | 2.93 KM | 5.07 | 19.22 | 5. | PC/CC i/c Prime Coat, Tack Coat | 8.85 KM | 8.62 | 8.85 KM | 8.85 KM | 2.28 | 8.62 | 6. | BM i/c Prime Coat, Tack Coat | 8.85 KM | 161.19 | 8.79 KM | 8.79 KM | 42.53 | 161.19 | 7. | SDBC i/c Tackcoat | 8.85 KM | 100.25 | 8.79 KM | 8.79 KM | 26.45 | 100.25 | 8. | Cause Way | 3.00 No | 3.05 | 2.00 No | 2.00 No | 0.81 | 3.05 | 9. | Culverts/Scupper | 13.00 No | 26.47 | 14.00 No | 14.00 No | 6.99 | 26.47 | 10. | longitudinal Drain | 584.00 m | 10.15 | 8550.00 m | 8550.00 m | 2.68 | 10.15 | 11. | Crash Barrier | 0.00 m | 0.00 | 0.00 m | 0.00 m | 0 | 0.00 | 12. | Road Furniture | 36.00 No | 0.67 | 36.00 No | 36.00 No | 0.18 | 0.67 |
Total Amount: |
378.98 |
|
100 |
378.98 |
|
Remarks:
No Remarks
Work Program Made On:
03-07-2016
Updation of work program on:
15-11-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-July-2016 | 35.02 lakhs |
2. | 08-September-2016 | 31.50 lakhs |
3. | 30-September-2016 | 48.56 lakhs |
4. | 26-December-2016 | 10.25 lakhs |
5. | 29-May-2017 | 31.91 lakhs |
6. | 30-June-2017 | 264.05 lakhs |
7. | 12-October-2017 | 4.45 lakhs |
8. | 28-November-2017 | 10.46 lakhs |
9. | 30-May-2018 | 12.63 lakhs |
10. | 30-November-2018 | 2.91 lakhs |
Total |
451.74 lakhs |
% Payment |
100.48 % |
|
Advance Amount: 222.41 lakhs
Recovered Amount: 222.41 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 194 |
Number of Notice(s) issued: 69 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 08-03-2018 | Ch 8.000 | Joint | Kuldeep Kumar Karanwal | JE | UDRP R&B Tehri | See Pic |
2. | 24-01-2018 | 1.800 | Site inspection by EE Mam WB PWD Tehri | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
3. | 06-12-2017 | Ch 0.400 | Parapets with white was | Kuldeep Kumar Karanwal | JE | UDRP R&B Tehri | See Pic |
4. | 29-06-2017 | 0.200 | Core cutting | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
5. | 08-06-2017 | 8.700 | SDBC work in progress | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
6. | 08-06-2017 | 7.435 | Site inspection by SE Sir Tehri | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
7. | 06-06-2017 | 7.887 | Bm rolling | Kuldeep Kumar Karanwal | JE | UDRP R&B Tehri | See Pic |
8. | 06-06-2017 | 7.900 | Laying of BM | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
9. | 02-06-2017 | 7+875 | BM laying in Progress. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
10. | 01-06-2017 | Ch 8.200 | Bm rolling | Kuldeep Kumar Karanwal | JE | UDRP R&B Tehri | See Pic |
11. | 31-05-2017 | 8.700 | Rolling of BM | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
12. | 31-05-2017 | 1.250 | Checking thickness of BM / SDBC by QC DSC 2 Tehri . AE.JE WB Tehri .n Contractor,s Engineer . It found 75 mm (BM +SDBC) | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
13. | 16-05-2017 | 6.250 | Sieve test for G3 | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
14. | 16-05-2017 | Laying of G3 | 5.400 | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
15. | 16-05-2017 | 8.500 | G3 testing | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
16. | 09-05-2017 | Ch7.300 | Parti filling under construction | Kuldeep Kumar Karanwal | JE | UDRP R&B Tehri | See Pic |
17. | 27-04-2017 | 7+840 | Site visit by Team Leader. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
18. | 24-04-2017 | 7+450 | Gradation test for WBM G3. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
19. | 13-04-2017 | 3.975 | Meeting/ Discuss about problems with Jakholi villagers by AE WB Tehri | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
20. | 11-04-2017 | Ch. 3.980 | Site visit AE sir for villagers village path | Kuldeep Kumar Karanwal | JE | UDRP R&B Tehri | See Pic |
|
|