UDRP/PWD/05/56/RD/062
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
72 |
Package Name: |
UDRP/PWD/05/56/RD/062 |
Sanction Cost: |
605.05 lakhs |
District: |
Dehradun |
Block: |
Chakrata |
Constituency: |
Chakrata |
Circle: |
Tehri WB Circle |
DEA: |
DEA Chakrata |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 1514 Koruba Kwarana Mangrauli MR (7.000 KM.) (completed) |
|
Procurement: |
Package No.: 72
Package Name: UDRP/PWD/05/56/RD/062
Tender Date: 20-11-2014
Current Status: Agreement signed
Achieved on Date: 05-08-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/05/56/RD/062
Contractor Name: Amit Joshi
|
Start Date: 12-08-2015
Intended Completion Date: 04-05-2017
Original End Date: 11-11-2016
|
Total Bond Cost: 43489374.46 (434.89 lakhs)
Variation Cost: 9977920.85 (99.78 lakhs) Hence Total Bond Cost is 53467295.31 (534.67 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 43490 for 2 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 7.00 KM | 85.64 | 7.00 KM | 7.00 KM | 16.73 | 85.64 | 2. | R/Wall, B/ Wall Type Protection works | 1036.00 m | 105.88 | 1036.00 m | 1036.00 m | 20.68 | 105.88 | 3. | GSB/RBI/G-1 | 7.00 KM | 46.78 | 7.00 KM | 7.00 KM | 9.14 | 46.78 | 4. | G-2 | 7.00 KM | 36.27 | 7.00 KM | 7.00 KM | 7.08 | 36.27 | 5. | G-3 | 7.00 KM | 38.44 | 7.00 KM | 7.00 KM | 7.51 | 38.44 | 6. | PC/CC i/c Prime Coat, Tack Coat | 7.00 KM | 82.58 | 7.00 KM | 7.00 KM | 16.13 | 82.58 | 7. | Cause Way | 5.00 No | 5.98 | 5.00 No | 5.00 No | 1.17 | 5.98 | 8. | Culverts/Scupper | 15.00 No | 29.85 | 15.00 No | 15.00 No | 5.83 | 29.85 | 9. | longitudinal Drain | 7000.00 m | 58.51 | 7000.00 m | 7000.00 m | 11.43 | 58.51 | 10. | Crash Barrier | 345.00 m | 19.53 | 345.00 m | 345.00 m | 3.81 | 19.53 | 11. | Road Furniture | 35.00 No | 2.58 | 35.00 No | 35.00 No | 0.5 | 2.58 |
Total Amount: |
512.04 |
|
100 |
512.04 |
|
Remarks:
No Remarks
Work Program Made On:
11-09-2015
Updation of work program on:
22-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 07-November-2015 | 49.53 lakhs |
2. | 19-December-2015 | 46.93 lakhs |
3. | 29-January-2016 | 35.01 lakhs |
4. | 08-March-2016 | 17.33 lakhs |
5. | 12-April-2016 | 39.45 lakhs |
6. | 24-May-2016 | 19.19 lakhs |
7. | 12-August-2016 | 38.13 lakhs |
8. | 30-September-2016 | 12.87 lakhs |
9. | 28-October-2016 | 46.36 lakhs |
10. | 07-January-2017 | 30.14 lakhs |
11. | 28-February-2017 | 32.50 lakhs |
12. | 24-March-2017 | 61.49 lakhs |
13. | 08-June-2017 | 57.35 lakhs |
14. | 31-July-2017 | 40.55 lakhs |
Total |
526.83 lakhs |
% Payment |
98.53 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 91 |
Number of Notice(s) issued: 59 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 27-04-2017 | Ch 5/12-5/13 | Laying temperature of premix carpet
Remark- acceptable | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
2. | 01-04-2017 | 3/29 | Pc work under progress | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
3. | 06-03-2017 | Ch 3/1-3/2 | Discuss with SE sir after Checking of kutcha drain and causeway. | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
4. | 25-02-2017 | Ch 4/1-4/2 | Laying of WBM G-3 | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
5. | 20-02-2017 | 0/13 | Checking of measurements and quality of plum, found ok | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
6. | 11-02-2017 | Ch 0/15-0/16 | Banded R/W complete and satisfactory | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
7. | 24-10-2016 | Km1 | Public meeting | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
8. | 05-10-2016 | Ch 0/15-0/16 | Checking of crust thickness and found ok | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
9. | 29-09-2016 | Km 1 | Pc work under progress | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
10. | 28-09-2016 | Ch 1/14-1/15 | Banded R/W is ok | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
11. | 28-09-2016 | Ch 0/2-0/3 | Laing of PC is satisfactory | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
12. | 28-09-2016 | Ch 0/2-0/3 | Laying of prime coat is ok | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
13. | 28-09-2016 | Cube testing of M-30 strength at ch 0/4 | Strength of cube is found ok | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
14. | 28-09-2016 | Ch 6/11 | WBM G-3 work have completed at ch 6/11 to 6/21and
found satisfactory | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
15. | 27-09-2016 | At Laboratory | PC aggregate gradation checking | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
16. | 27-09-2016 | At ch 0/2 - 0/3 | Seal coat work in progress | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
17. | 27-09-2016 | At ch 0/2 | PC work is in progress | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
18. | 29-08-2016 | Ch 3/23-3/24 | R/w under progress and quality of work is satisfactory | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
19. | 01-07-2016 | Ch 0/6-0/7 | WBM G-3 completed | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
20. | 29-06-2016 | Km 3 | Slip clearance under progress. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
|
|