Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/05/56/RD/062 Agreement signed
Project: UDRP-RB Package No.: 72 Package Name: UDRP/PWD/05/56/RD/062 Sanction Cost: 605.05  lakhs
District: Dehradun Block: Chakrata Constituency: Chakrata Circle: Tehri WB Circle
DEA: DEA Chakrata DSC: Egis International DSC Scope: only Supervision No.of Sub project : 1
Subproject in this package
1  1514   Koruba Kwarana Mangrauli MR (7.000 KM.) (completed)
Procurement:
Package No.: 72        Package Name: UDRP/PWD/05/56/RD/062        Tender Date: 20-11-2014        Current Status: Agreement signed        Achieved on Date: 05-08-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/05/56/RD/062        Contractor Name: Amit Joshi       
Start Date: 12-08-2015        Intended Completion Date: 04-05-2017        Original End Date:  11-11-2016
Total Bond Cost: 43489374.46 (434.89 lakhs)        Variation Cost: 9977920.85 (99.78 lakhs)     Hence Total Bond Cost is   53467295.31 (534.67 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 43490 for 2 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence7.00 KM85.647.00 KM7.00 KM16.7385.64
2.R/Wall, B/ Wall Type Protection works1036.00 m105.881036.00 m1036.00 m20.68105.88
3.GSB/RBI/G-17.00 KM46.787.00 KM7.00 KM9.1446.78
4.G-27.00 KM36.277.00 KM7.00 KM7.0836.27
5.G-37.00 KM38.447.00 KM7.00 KM7.5138.44
6.PC/CC i/c Prime Coat, Tack Coat7.00 KM82.587.00 KM7.00 KM16.1382.58
7.Cause Way5.00 No5.985.00 No5.00 No1.175.98
8.Culverts/Scupper 15.00 No29.8515.00 No15.00 No5.8329.85
9.longitudinal Drain7000.00 m58.517000.00 m7000.00 m11.4358.51
10.Crash Barrier345.00 m19.53345.00 m345.00 m3.8119.53
11.Road Furniture35.00 No2.5835.00 No35.00 No0.52.58
Total Amount: 512.04 100   512.04
Remarks: No Remarks       Work Program Made On: 11-09-2015       Updation of work program on: 22-05-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.07-November-201549.53  lakhs
2.19-December-201546.93  lakhs
3.29-January-201635.01  lakhs
4.08-March-201617.33  lakhs
5.12-April-201639.45  lakhs
6.24-May-201619.19  lakhs
7.12-August-201638.13  lakhs
8.30-September-201612.87  lakhs
9.28-October-201646.36  lakhs
10.07-January-201730.14  lakhs
11.28-February-201732.50  lakhs
12.24-March-201761.49  lakhs
13.08-June-201757.35  lakhs
14.31-July-201740.55  lakhs
Total 526.83  lakhs
% Payment 98.53 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 311     No. of Test Done : 326      No. of Test Passed : 311      No. of Test Failed : 15   Test report of this package
Number of Pics Available on Web Repository: 91
Number of Notice(s) issued: 59

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.27-04-2017Ch 5/12-5/13Laying temperature of premix carpet Remark- acceptableDhwajvir SinghJEUDRP R&B Karnprayag See Pic
2.01-04-20173/29Pc work under progressLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
3.06-03-2017Ch 3/1-3/2Discuss with SE sir after Checking of kutcha drain and causeway.Dhwajvir SinghJEUDRP R&B Chakrata See Pic
4.25-02-2017Ch 4/1-4/2Laying of WBM G-3Dhwajvir SinghJEUDRP R&B Chakrata See Pic
5.20-02-20170/13Checking of measurements and quality of plum, found okLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
6.11-02-2017Ch 0/15-0/16Banded R/W complete and satisfactoryDhwajvir SinghJEUDRP R&B Chakrata See Pic
7.24-10-2016Km1Public meetingLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
8.05-10-2016Ch 0/15-0/16Checking of crust thickness and found okDhwajvir SinghJEUDRP R&B Chakrata See Pic
9.29-09-2016Km 1Pc work under progressLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
10.28-09-2016Ch 1/14-1/15Banded R/W is okDhwajvir SinghJEUDRP R&B Chakrata See Pic
11.28-09-2016Ch 0/2-0/3Laing of PC is satisfactoryDhwajvir SinghJEUDRP R&B Chakrata See Pic
12.28-09-2016Ch 0/2-0/3Laying of prime coat is okDhwajvir SinghJEUDRP R&B Chakrata See Pic
13.28-09-2016Cube testing of M-30 strength at ch 0/4Strength of cube is found okDhwajvir SinghJEUDRP R&B Chakrata See Pic
14.28-09-2016Ch 6/11WBM G-3 work have completed at ch 6/11 to 6/21and found satisfactoryDhwajvir SinghJEUDRP R&B Chakrata See Pic
15.27-09-2016At LaboratoryPC aggregate gradation checkingRajan NautiyalJEUDRP R&B Chakrata See Pic
16.27-09-2016At ch 0/2 - 0/3Seal coat work in progressRajan NautiyalJEUDRP R&B Chakrata See Pic
17.27-09-2016At ch 0/2PC work is in progressRajan NautiyalJEUDRP R&B Chakrata See Pic
18.29-08-2016Ch 3/23-3/24R/w under progress and quality of work is satisfactoryDhwajvir SinghJEUDRP R&B Chakrata See Pic
19.01-07-2016Ch 0/6-0/7WBM G-3 completedDhwajvir SinghJEUDRP R&B Chakrata See Pic
20.29-06-2016Km 3Slip clearance under progress.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic