UDRP/AF/SL/12
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
709 |
Package Name: |
UDRP/AF/SL/12 |
Sanction Cost: |
612.54 lakhs |
District: |
Tehri |
Block: |
Narendra Nagar |
Constituency: |
Narendra Nagar |
Circle: |
|
DEA: |
DEA Tehri |
DSC: |
CCEE Group India Pvt. Ltd in Association with JSV |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4051 Tachla Naur Slope Motor Road KM-1 (150.000 KM.) (completed) |
|
Procurement: |
Package No.: 709
Package Name: UDRP/AF/SL/12
Tender Date: 11-11-2019
Current Status: Agreement signed
Achieved on Date: 02-06-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/SL/12
Contractor Name: Global Construction
|
Start Date: 09-07-2020
Intended Completion Date: 06-09-2021
Original End Date: 08-07-2021
|
Total Bond Cost: 54390157.29 (543.9 lakhs)
Variation Cost: 181827.89 (1.82 lakhs) Hence Total Bond Cost is 54571985.18 (545.72 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 7152285 for 263 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | R/Wall, B/ Wall Type Protection works | 221.00 m | 38.20 | 221.00 m | 221.00 m | 7.95 | 38.20 | 2. | Stressing & Grouting | 1.00 Job | 226.87 | 1.00 Job | 1.00 Job | 47.19 | 226.87 | 3. | Env. Man & Moni Plan | 1.00 Job | 4.73 | 1.00 Job | 1.00 Job | 0.98 | 4.73 | 4. | Other Allied Works & Finishing Work | 1.00 Job | 18.09 | 1.00 Job | 1.00 Job | 3.76 | 18.09 | 5. | Approach Ramp /path | 150.00 m | 22.41 | 150.00 m | 150.00 m | 4.66 | 22.41 | 6. | Anchors | 8739.00 m | 36.67 | 8739.00 m | 8739.00 m | 7.63 | 36.67 | 7. | Hydroseeding,3-D Net, High tensile Rolled Cable Net | 8250.00 sqm | 122.43 | 8250.00 sqm | 8250.00 sqm | 25.47 | 122.43 | 8. | Gabion work | 150.00 m | 11.36 | 150.00 m | 150.00 m | 2.36 | 11.36 |
Total Amount: |
480.76 |
|
100 |
480.76 |
|
Remarks:
No Remarks
Work Program Made On:
21-10-2020
Updation of work program on:
21-09-2021
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 11-November-2020 | 71.52 lakhs |
2. | 18-December-2020 | 137.01 lakhs |
3. | 04-February-2021 | 36.12 lakhs |
4. | 27-February-2021 | 39.14 lakhs |
5. | 31-May-2021 | 33.93 lakhs |
6. | 06-July-2021 | 64.23 lakhs |
7. | 31-August-2021 | 68.64 lakhs |
8. | 30-September-2021 | 46.85 lakhs |
9. | 22-February-2022 | 48.08 lakhs |
Total |
545.52 lakhs |
% Payment |
99.96 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 348 |
Number of Notice(s) issued: 5 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 06-04-2022 | Tachhla Naur km 1 | World Bank Team visit | Sudhir Kumar | ` | ` | See Pic |
2. | 06-04-2022 | Tachhla Naur km 1 | World Bank Team visit | Sudhir Kumar | ` | ` | See Pic |
3. | 06-04-2022 | Tachhla Naur km 1 | World Bank Team visit | Sudhir Kumar | ` | ` | See Pic |
4. | 28-01-2022 | 0+85 | R/wall at sub project. | Sohan Negi | ` | ` | See Pic |
5. | 27-01-2022 | 0+095 to 0+130 | White washing for parapet & B/wall | Sohan negi | ` | ` | See Pic |
6. | 27-01-2022 | 0+070 | Soil Erosion control Coir mat. | Sohan Negi | ` | ` | See Pic |
7. | 27-01-2022 | 0+025 | Installation of PVC pipe for drainage out of seepage area water. | Sohan Negi | ` | ` | See Pic |
8. | 27-01-2022 | 0+110 | Breast wall protection at sub project | Sohan Negi | ` | ` | See Pic |
9. | 27-01-2022 | 0+055 | Breast wall protection at sub project | Sohan Negi | ` | ` | See Pic |
10. | 27-01-2022 | 0+000 | Rigid pavement CC road | Sohan Negi | ` | ` | See Pic |
11. | 27-01-2022 | 0+040 | Parapet protection | Sohan Negi | ` | ` | See Pic |
12. | 27-01-2022 | 0+00 | Road and wire mesh protection | Rajveer Tomar | ` | ` | See Pic |
13. | 27-01-2022 | 00+00 | Wire mesh protection | Rajveer Tomar | ` | ` | See Pic |
14. | 27-01-2022 | 00+00 | Wire mesh protection | Rajveer Tomar | ` | ` | See Pic |
15. | 27-01-2022 | 0+085to0+110 | Retaining wall in progress | Rajveer Tomar | ` | ` | See Pic |
16. | 27-01-2022 | 0+000 | Slope protection work with high tensile wire mesh, Anchoring and anchor plates | Sohan Negi | ` | ` | See Pic |
17. | 27-01-2022 | 0+00 to 0+80 | High tensile wire mesh work in progress | Rajveer Tomar | ` | ` | See Pic |
18. | 27-01-2022 | 0+080To0+110 | Retaining wall in progress | Rajveer Tomar | ` | ` | See Pic |
19. | 27-01-2022 | 0+090to0+110 | Retaining wall in progress | Rajveer Tomar | ` | ` | See Pic |
20. | 12-11-2021 | Tachhla Naur km 1 Tehri | Joint inspection with AE PWD Narendra Nagar | Sudhir Kumar | ` | ` | See Pic |
|
|