Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/SL/10 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 707 Package Name: UDRP/AF/SL/10 Sanction Cost: 262.28  lakhs
District: Tehri Block: Barakot Constituency: Narendra Nagar Circle:
DEA: DEA Tehri DSC: CCEE Group India Pvt. Ltd in Association with JSV DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4044   Road protection WORK of jajalgaja mr KM-4 (115.000 KM.) (completed)
Procurement:
Package No.: 707        Package Name: UDRP/AF/SL/10        Tender Date: 07-11-2019        Current Status: Agreement signed        Achieved on Date: 07-02-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/SL/10        Contractor Name: M/S JaiKedar construction company       
Start Date: 15-02-2020        Intended Completion Date: 18-06-2021        Original End Date:  14-02-2021
Total Bond Cost: 22590174.69 (225.9 lakhs)        Variation Cost: 1111618.52 (11.12 lakhs)     Hence Total Bond Cost is   23701793.21 (237.02 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 4269510 for 378 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.R/Wall, B/ Wall Type Protection works131.60 m15.39131.60 m131.60 m7.1415.39
2.Stressing & Grouting1.00 Job78.181.00 Job1.00 Job36.2578.18
3.Env. Man & Moni Plan1.00 Job8.391.00 Job1.00 Job3.898.39
4.Other Allied Works & Finishing Work 1.00 Job9.731.00 Job1.00 Job4.519.73
5.Approach Ramp /path 90.00 m13.85130.00 m130.00 m6.4213.85
6.Anchors3100.00 m15.753100.00 m3100.00 m7.315.75
7.Hydroseeding,3-D Net, High tensile Rolled Cable Net7730.16 sqm68.117730.16 sqm7730.16 sqm31.5868.11
8.Gabion work24.00 m3.1224.00 m24.00 m1.453.12
9.PCC in Foundation50.80 cum2.6050.80 cum50.80 cum1.212.60
10.Excavation in soil864.00 cum0.42864.00 cum864.00 cum0.20.42
11.Retrofitting1.00 job0.141.00 job1.00 job0.070.14
Total Amount: 215.68 100   215.68
Remarks: No Remarks       Work Program Made On: 19-01-2021       Updation of work program on: 24-06-2021      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.11-November-202014.14  lakhs
2.19-December-202049.38  lakhs
3.04-February-202123.50  lakhs
4.27-February-202141.05  lakhs
5.30-March-202153.09  lakhs
6.31-May-202125.39  lakhs
7.21-September-202130.47  lakhs
Total 237.02  lakhs
% Payment 100 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 127     No. of Test Done : 127      No. of Test Passed : 127      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 224
Number of Notice(s) issued: 10

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.06-04-2022Jajal Gaja km 4World Bank team visitSudhir Kumar ` ` See Pic
2.05-04-2022Jajal Gaja km 4World Bank Team visitSudhir Kumar ` ` See Pic
3.28-01-20220+000Protection work at sub project.Sohan Negi ` ` See Pic
4.28-01-20220+000 to 0+090Wire mesh protection with B/Wall at sub project.Sohan Negi ` ` See Pic
5.28-01-20220+025Wire mesh protection with Anchor and plates.Sohan Negi ` ` See Pic
6.28-01-20220+000 to 0+090Breast wall protection with white wash .Sohan Negi ` ` See Pic
7.28-01-20220+055MBCB protection at sub project.Sohan Negi ` ` See Pic
8.28-01-20220+050R/Wall Protection at sub project.Sohan Negi ` ` See Pic
9.28-01-20220+020Wire mesh protection with Anchoring at sub project.Sohan Negi ` ` See Pic
10.28-01-20220+070Parapet for road protection at sub projectSohan Negi ` ` See Pic
11.28-01-20220+70B/wall at sub projectSohan Negi ` ` See Pic
12.28-01-20220+090Wire mesh protection at sub project.Sohan Negi ` ` See Pic
13.24-07-20210+090Noise monitoring testVikash Baboounknownunknown See Pic
14.24-07-20210+090Air monitoring testVikash Baboounknownunknown See Pic
15.07-07-2021At site laboratorySite lab material testingSohan Negi ` ` See Pic
16.07-07-2021At site officeDustbinSohan Negi ` ` See Pic
17.07-07-2021At site office mettingLabour's in PPE kitSohan Negi ` ` See Pic
18.07-07-2021Chainge 0+450Dumping zoneSohan Negi ` ` See Pic
19.07-07-2021Chainge 0+050DG Set at siteSohan Negi ` ` See Pic
20.07-07-2021Chainage 3+300Soak pitSohan Negi ` ` See Pic