UDRP/AF/SL/10
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
707 |
Package Name: |
UDRP/AF/SL/10 |
Sanction Cost: |
262.28 lakhs |
District: |
Tehri |
Block: |
Barakot |
Constituency: |
Narendra Nagar |
Circle: |
|
DEA: |
DEA Tehri |
DSC: |
CCEE Group India Pvt. Ltd in Association with JSV |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4044 Road protection WORK of jajalgaja mr KM-4 (115.000 KM.) (completed) |
|
Procurement: |
Package No.: 707
Package Name: UDRP/AF/SL/10
Tender Date: 07-11-2019
Current Status: Agreement signed
Achieved on Date: 07-02-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/SL/10
Contractor Name: M/S JaiKedar construction company
|
Start Date: 15-02-2020
Intended Completion Date: 18-06-2021
Original End Date: 14-02-2021
|
Total Bond Cost: 22590174.69 (225.9 lakhs)
Variation Cost: 1111618.52 (11.12 lakhs) Hence Total Bond Cost is 23701793.21 (237.02 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 4269510 for 378 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | R/Wall, B/ Wall Type Protection works | 131.60 m | 15.39 | 131.60 m | 131.60 m | 7.14 | 15.39 | 2. | Stressing & Grouting | 1.00 Job | 78.18 | 1.00 Job | 1.00 Job | 36.25 | 78.18 | 3. | Env. Man & Moni Plan | 1.00 Job | 8.39 | 1.00 Job | 1.00 Job | 3.89 | 8.39 | 4. | Other Allied Works & Finishing Work | 1.00 Job | 9.73 | 1.00 Job | 1.00 Job | 4.51 | 9.73 | 5. | Approach Ramp /path | 90.00 m | 13.85 | 130.00 m | 130.00 m | 6.42 | 13.85 | 6. | Anchors | 3100.00 m | 15.75 | 3100.00 m | 3100.00 m | 7.3 | 15.75 | 7. | Hydroseeding,3-D Net, High tensile Rolled Cable Net | 7730.16 sqm | 68.11 | 7730.16 sqm | 7730.16 sqm | 31.58 | 68.11 | 8. | Gabion work | 24.00 m | 3.12 | 24.00 m | 24.00 m | 1.45 | 3.12 | 9. | PCC in Foundation | 50.80 cum | 2.60 | 50.80 cum | 50.80 cum | 1.21 | 2.60 | 10. | Excavation in soil | 864.00 cum | 0.42 | 864.00 cum | 864.00 cum | 0.2 | 0.42 | 11. | Retrofitting | 1.00 job | 0.14 | 1.00 job | 1.00 job | 0.07 | 0.14 |
Total Amount: |
215.68 |
|
100 |
215.68 |
|
Remarks:
No Remarks
Work Program Made On:
19-01-2021
Updation of work program on:
24-06-2021
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 11-November-2020 | 14.14 lakhs |
2. | 19-December-2020 | 49.38 lakhs |
3. | 04-February-2021 | 23.50 lakhs |
4. | 27-February-2021 | 41.05 lakhs |
5. | 30-March-2021 | 53.09 lakhs |
6. | 31-May-2021 | 25.39 lakhs |
7. | 21-September-2021 | 30.47 lakhs |
Total |
237.02 lakhs |
% Payment |
100 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 224 |
Number of Notice(s) issued: 10 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 06-04-2022 | Jajal Gaja km 4 | World Bank team visit | Sudhir Kumar | ` | ` | See Pic |
2. | 05-04-2022 | Jajal Gaja km 4 | World Bank Team visit | Sudhir Kumar | ` | ` | See Pic |
3. | 28-01-2022 | 0+000 | Protection work at sub project. | Sohan Negi | ` | ` | See Pic |
4. | 28-01-2022 | 0+000 to 0+090 | Wire mesh protection with B/Wall at sub project. | Sohan Negi | ` | ` | See Pic |
5. | 28-01-2022 | 0+025 | Wire mesh protection with Anchor and plates. | Sohan Negi | ` | ` | See Pic |
6. | 28-01-2022 | 0+000 to 0+090 | Breast wall protection with white wash . | Sohan Negi | ` | ` | See Pic |
7. | 28-01-2022 | 0+055 | MBCB protection at sub project. | Sohan Negi | ` | ` | See Pic |
8. | 28-01-2022 | 0+050 | R/Wall Protection at sub project. | Sohan Negi | ` | ` | See Pic |
9. | 28-01-2022 | 0+020 | Wire mesh protection with Anchoring at sub project. | Sohan Negi | ` | ` | See Pic |
10. | 28-01-2022 | 0+070 | Parapet for road protection at sub project | Sohan Negi | ` | ` | See Pic |
11. | 28-01-2022 | 0+70 | B/wall at sub project | Sohan Negi | ` | ` | See Pic |
12. | 28-01-2022 | 0+090 | Wire mesh protection at sub project. | Sohan Negi | ` | ` | See Pic |
13. | 24-07-2021 | 0+090 | Noise monitoring test | Vikash Baboo | unknown | unknown | See Pic |
14. | 24-07-2021 | 0+090 | Air monitoring test | Vikash Baboo | unknown | unknown | See Pic |
15. | 07-07-2021 | At site laboratory | Site lab material testing | Sohan Negi | ` | ` | See Pic |
16. | 07-07-2021 | At site office | Dustbin | Sohan Negi | ` | ` | See Pic |
17. | 07-07-2021 | At site office metting | Labour's in PPE kit | Sohan Negi | ` | ` | See Pic |
18. | 07-07-2021 | Chainge 0+450 | Dumping zone | Sohan Negi | ` | ` | See Pic |
19. | 07-07-2021 | Chainge 0+050 | DG Set at site | Sohan Negi | ` | ` | See Pic |
20. | 07-07-2021 | Chainage 3+300 | Soak pit | Sohan Negi | ` | ` | See Pic |
|
|