UDRP/AF/SL/08
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
705 |
Package Name: |
UDRP/AF/SL/08 |
Sanction Cost: |
529.10 lakhs |
District: |
Tehri |
Block: |
Kouldhar |
Constituency: |
Pratapnagar |
Circle: |
|
DEA: |
DEA Tehri |
DSC: |
CCEE Group India Pvt. Ltd in Association with JSV |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4046 Dobra Bhliyana Slope Motor Road KM-3 (125.000 KM.) (completed) |
|
Procurement: |
Package No.: 705
Package Name: UDRP/AF/SL/08
Tender Date: 07-11-2019
Current Status: Agreement signed
Achieved on Date: 07-02-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/SL/08
Contractor Name: M/S Garware Technical fibers Ltd.
|
Start Date: 15-02-2020
Intended Completion Date: 10-06-2021
Original End Date: 14-02-2021
|
Total Bond Cost: 47858029.21 (478.58 lakhs)
Variation Cost: -7015415.58 (-70.15 lakhs) Hence Total Bond Cost is 40842613.63 (408.43 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 9739103 for 407 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | R/Wall, B/ Wall Type Protection works | 90.00 m | 28.05 | 90.00 m | 90.00 m | 6.64 | 28.05 | 2. | Stressing & Grouting | 1.00 Job | 154.16 | 1.00 Job | 1.00 Job | 36.5 | 154.16 | 3. | Env. Man & Moni Plan | 1.00 Job | 5.32 | 1.00 Job | 1.00 Job | 1.26 | 5.32 | 4. | Other Allied Works & Finishing Work | 1.00 Job | 23.47 | 1.00 Job | 1.00 Job | 5.56 | 23.47 | 5. | Approach Ramp /path | 125.00 m | 42.80 | 125.00 m | 125.00 m | 10.13 | 42.80 | 6. | Anchors | 6240.00 m | 68.25 | 6240.00 m | 6240.00 m | 16.16 | 68.25 | 7. | Hydroseeding,3-D Net, High tensile Rolled Cable Net | 4343.02 sqm | 85.73 | 4343.02 sqm | 4343.02 sqm | 20.3 | 85.73 | 8. | Gabion work | 675.00 m | 14.63 | 675.00 m | 675.00 m | 3.46 | 14.63 |
Total Amount: |
422.41 |
|
100 |
422.41 |
|
Remarks:
No Remarks
Work Program Made On:
21-10-2020
Updation of work program on:
24-06-2021
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 29-October-2020 | 55.25 lakhs |
2. | 11-November-2020 | 27.08 lakhs |
3. | 09-March-2021 | 139.27 lakhs |
4. | 31-March-2021 | 35.66 lakhs |
5. | 31-May-2021 | 104.74 lakhs |
6. | 30-November-2021 | 46.43 lakhs |
Total |
408.43 lakhs |
% Payment |
100 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 254 |
Number of Notice(s) issued: 16 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 28-01-2022 | 0+90 | SD Anchor protection with Anchor Plates work at sub project | Sohan Negi | ` | ` | See Pic |
2. | 28-01-2022 | 0+060 | B/wall,CC drain, parapet protection work at sub project | Sohan Negi | ` | ` | See Pic |
3. | 28-01-2022 | 0+90 | Primary and secondary wire mesh protection work | Sohan Negi | ` | ` | See Pic |
4. | 28-01-2022 | 0+100 | CC pavement work at sub project. | Sohan Negi | ` | ` | See Pic |
5. | 28-01-2022 | 0+70 | B/wall protection work at sub project. | Sohan Negi | ` | ` | See Pic |
6. | 28-01-2022 | 0+40 | Wire mesh protection work with Anchor and plates. | Sohan Negi | ` | ` | See Pic |
7. | 28-01-2022 | 0+30 | Gabion Protection work at sub project | Sohan Negi | ` | ` | See Pic |
8. | 28-01-2022 | 0+000 to 0+ 130 | Slope protection work with High tensile wire mesh | Sohan Negi | ` | ` | See Pic |
9. | 28-01-2022 | 0+80 | Parapet Protection work with white wash | Sohan Negi | ` | ` | See Pic |
10. | 27-01-2022 | At site | CNG work in progress | Kishan singh rawat | ` | ` | See Pic |
11. | 07-07-2021 | 0+000 to 0+005 | First aid box for dobra bhaldiyana km-03 motar road | Deepak Shukla | ` | ` | See Pic |
12. | 07-07-2021 | 0+000 to 0+ 050 | PPB KIT with laber for dobra bhaldiyana km-03 motar road | Deepak Shukla | ` | ` | See Pic |
13. | 07-07-2021 | 2+000 to 3+000 | Laber camp for dobra bhaldiyana km-03 motar road | Deepak Shukla | ` | ` | See Pic |
14. | 07-07-2021 | 0+000 to 0+005 | Washroom for dobra bhaldiyana km-03 motar road | Deepak Shukla | ` | ` | See Pic |
15. | 07-07-2021 | 0+000 to 0+005 | Laboratory for dobra bhaldiyana km-03 motar road | Deepak Shukla | ` | ` | See Pic |
16. | 07-07-2021 | 0+000 to 0+005 | Dustbin for dobra bhaldiyana km-03 motar road | Deepak Shukla | ` | ` | See Pic |
17. | 07-07-2021 | 0+000 to 0+015 | Soak pit for dobra bhaldiyana km-03 motar road | Deepak Shukla | ` | ` | See Pic |
18. | 07-07-2021 | 0+000 to 0+005 | Dumping zone for dobra bhaldiyana km-03 motar road | Deepak Shukla | ` | ` | See Pic |
19. | 07-07-2021 | 0+000 to 0+005 | DG set for dobra bhaldiyana km-03 | Deepak Shukla | ` | ` | See Pic |
20. | 07-07-2021 | 0+000 to 0+010 | Fire extinguisher for dobra bhaldiyana km-03 | Deepak Shukla | ` | ` | See Pic |
|
|