Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/SL/08 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 705 Package Name: UDRP/AF/SL/08 Sanction Cost: 529.10  lakhs
District: Tehri Block: Kouldhar Constituency: Pratapnagar Circle:
DEA: DEA Tehri DSC: CCEE Group India Pvt. Ltd in Association with JSV DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4046   Dobra Bhliyana Slope Motor Road KM-3 (125.000 KM.) (completed)
Procurement:
Package No.: 705        Package Name: UDRP/AF/SL/08        Tender Date: 07-11-2019        Current Status: Agreement signed        Achieved on Date: 07-02-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/SL/08        Contractor Name: M/S Garware Technical fibers Ltd.       
Start Date: 15-02-2020        Intended Completion Date: 10-06-2021        Original End Date:  14-02-2021
Total Bond Cost: 47858029.21 (478.58 lakhs)        Variation Cost: -7015415.58 (-70.15 lakhs)     Hence Total Bond Cost is   40842613.63 (408.43 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 9739103 for 407 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.R/Wall, B/ Wall Type Protection works90.00 m28.0590.00 m90.00 m6.6428.05
2.Stressing & Grouting1.00 Job154.161.00 Job1.00 Job36.5154.16
3.Env. Man & Moni Plan1.00 Job5.321.00 Job1.00 Job1.265.32
4.Other Allied Works & Finishing Work 1.00 Job23.471.00 Job1.00 Job5.5623.47
5.Approach Ramp /path 125.00 m42.80125.00 m125.00 m10.1342.80
6.Anchors6240.00 m68.256240.00 m6240.00 m16.1668.25
7.Hydroseeding,3-D Net, High tensile Rolled Cable Net4343.02 sqm85.734343.02 sqm4343.02 sqm20.385.73
8.Gabion work675.00 m14.63675.00 m675.00 m3.4614.63
Total Amount: 422.41 100   422.41
Remarks: No Remarks       Work Program Made On: 21-10-2020       Updation of work program on: 24-06-2021      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.29-October-202055.25  lakhs
2.11-November-202027.08  lakhs
3.09-March-2021139.27  lakhs
4.31-March-202135.66  lakhs
5.31-May-2021104.74  lakhs
6.30-November-202146.43  lakhs
Total 408.43  lakhs
% Payment 100 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 251     No. of Test Done : 251      No. of Test Passed : 251      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 254
Number of Notice(s) issued: 16

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.28-01-20220+90SD Anchor protection with Anchor Plates work at sub projectSohan Negi ` ` See Pic
2.28-01-20220+060B/wall,CC drain, parapet protection work at sub projectSohan Negi ` ` See Pic
3.28-01-20220+90Primary and secondary wire mesh protection workSohan Negi ` ` See Pic
4.28-01-20220+100CC pavement work at sub project.Sohan Negi ` ` See Pic
5.28-01-20220+70B/wall protection work at sub project.Sohan Negi ` ` See Pic
6.28-01-20220+40Wire mesh protection work with Anchor and plates.Sohan Negi ` ` See Pic
7.28-01-20220+30Gabion Protection work at sub projectSohan Negi ` ` See Pic
8.28-01-20220+000 to 0+ 130Slope protection work with High tensile wire meshSohan Negi ` ` See Pic
9.28-01-20220+80Parapet Protection work with white washSohan Negi ` ` See Pic
10.27-01-2022At siteCNG work in progressKishan singh rawat ` ` See Pic
11.07-07-20210+000 to 0+005First aid box for dobra bhaldiyana km-03 motar roadDeepak Shukla ` ` See Pic
12.07-07-20210+000 to 0+ 050PPB KIT with laber for dobra bhaldiyana km-03 motar roadDeepak Shukla ` ` See Pic
13.07-07-20212+000 to 3+000Laber camp for dobra bhaldiyana km-03 motar roadDeepak Shukla ` ` See Pic
14.07-07-20210+000 to 0+005Washroom for dobra bhaldiyana km-03 motar roadDeepak Shukla ` ` See Pic
15.07-07-20210+000 to 0+005Laboratory for dobra bhaldiyana km-03 motar roadDeepak Shukla ` ` See Pic
16.07-07-20210+000 to 0+005Dustbin for dobra bhaldiyana km-03 motar roadDeepak Shukla ` ` See Pic
17.07-07-20210+000 to 0+015Soak pit for dobra bhaldiyana km-03 motar roadDeepak Shukla ` ` See Pic
18.07-07-20210+000 to 0+005Dumping zone for dobra bhaldiyana km-03 motar roadDeepak Shukla ` ` See Pic
19.07-07-20210+000 to 0+005DG set for dobra bhaldiyana km-03Deepak Shukla ` ` See Pic
20.07-07-20210+000 to 0+010Fire extinguisher for dobra bhaldiyana km-03Deepak Shukla ` ` See Pic