Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/SL/07 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 704 Package Name: UDRP/AF/SL/07 Sanction Cost: 578.73  lakhs
District: Champawat Block: Barakot Constituency: Champawat Circle:
DEA: DEA Nainital DSC: CCEE Group India Pvt. Ltd in Association with JSV DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4042   Shri Purnagiri Temple Area in Tanakpur Slope MR (0.100 KM.) (in prorgress)
Procurement:
Package No.: 704        Package Name: UDRP/AF/SL/07        Tender Date: 31-07-2021        Current Status: Agreement signed        Achieved on Date: 28-10-2021

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/SL/07        Contractor Name: M/s Stonefield Construction       
Start Date: 25-11-2021        Intended Completion Date: 14-12-2022        Original End Date:  31-03-2022
Total Bond Cost: 41863272.62 (418.63 lakhs)        Variation Cost: -76191.35 (-0.76 lakhs)     Hence Total Bond Cost is   41787081.27 (417.87 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 5944688 for 284 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Env. Man & Moni Plan26.00 Job2.3626.00 Job8.00 Job0.190.73
2.Other Allied Works & Finishing Work 4.00 Job7.473.00 Job1.00 Job0.672.49
3.Steel Railing/crush barrier860.00 m19.07860.00 m0.00 m00.00
4.Protection Work10.00 Job47.8210.00 Job2.00 Job2.579.56
5.Errection Work100.00 Job0.91100.00 Job0.00 Job00.00
6.Anchors3172.00 m217.883172.00 m1920.00 m35.37131.89
7.Hydroseeding,3-D Net, High tensile Rolled Cable Net1980.00 sqm25.781980.00 sqm0.00 sqm00.00
8.PCC in Foundation395.00 cum25.05395.00 cum0.00 cum00.00
9.Excavation in soil124.00 cum0.46124.00 cum0.00 cum00.00
10.Reinforcement work210.00 mt13.34210.00 mt0.00 mt00.00
11.Sand Filling168.20 Cum2.82168.20 Cum0.00 Cum00.00
12.Wearing Coat142.50 Cum9.91142.50 Cum0.00 Cum00.00
Total Amount: 372.87 38.8   144.67
Remarks: No Remarks       Work Program Made On: 28-01-2022       Updation of work program on: 06-05-2022      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.30-March-2022112.41  lakhs
2.04-June-202241.60  lakhs
3.30-August-202274.14  lakhs
4.29-November-202292.81  lakhs
5.22-December-20225.62  lakhs
6.29-December-202222.25  lakhs
7.31-March-202382.56  lakhs
Total 431.39  lakhs
% Payment 103.24 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles
Environment & Social Compliances(Sub Project level):
Shri Purnagiri Temple Area in Tanakpur Slope MR(4042)EMP, project information board
Detailed report of this Package
Quality
No. of Test Required : 233     No. of Test Done : 233      No. of Test Passed : 233      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 72
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.08-06-2022Ch 0+25 Grouting approx El 870Grouting of 32 dia Anchor in progressChhatrapati Pant ` ` See Pic
2.21-05-20220+010Drilling & installation of Anchor work in progressSohan Negi ` ` See Pic
3.21-05-20220+015Drilling & installation of solid anchor for protection workSohan Negi ` ` See Pic
4.04-04-2022At siteGrouting cube castingKishan singh rawat ` ` See Pic
5.04-04-2022At siteGrouting work in progressKishan singh rawat ` ` See Pic
6.04-04-2022At siteNoise testKishan singh rawat ` ` See Pic
7.04-04-2022At sitePull testKishan singh rawat ` ` See Pic
8.04-04-2022At siteGrouting work in progressKishan singh rawat ` ` See Pic
9.04-04-2022At siteGrout work in progressKishan singh rawat ` ` See Pic
10.24-03-2022At siteDrilling work in progressKishan singh rawat ` ` See Pic
11.24-03-2022At siteDrilling work in progressKishan singh rawat ` ` See Pic
12.24-03-2022At siteSite visit with designer- Ashish Gharpure , Geologist - GVRG Acharyaulu , Geotech- B Venkateswar and Slope stabilization Dr - Manish semwalKishan singh rawat ` ` See Pic
13.24-03-2022At siteR/W for top platform work in progressKishan singh rawat ` ` See Pic
14.24-03-2022At siteGrouting work in progressKishan singh rawat ` ` See Pic
15.24-03-2022At siteGrouting work in progressKishan singh rawat ` ` See Pic
16.24-03-2022At sitePublic consultation meeting at siteKishan singh rawat ` ` See Pic
17.24-03-2022At siteAt siteKishan singh rawat ` ` See Pic
18.24-03-2022At siteLabour laws & labour safety meeting at siteKishan singh rawat ` ` See Pic
19.04-03-2022At siteDrilling work in progressKishan singh rawat ` ` See Pic
20.04-03-20220+040Drilling work in progressKishan singh rawat ` ` See Pic