UDRP/AF/SL/07
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
704 |
Package Name: |
UDRP/AF/SL/07 |
Sanction Cost: |
578.73 lakhs |
District: |
Champawat |
Block: |
Barakot |
Constituency: |
Champawat |
Circle: |
|
DEA: |
DEA Nainital |
DSC: |
CCEE Group India Pvt. Ltd in Association with JSV |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4042 Shri Purnagiri Temple Area in Tanakpur Slope MR (0.100 KM.) (in prorgress) |
|
Procurement: |
Package No.: 704
Package Name: UDRP/AF/SL/07
Tender Date: 31-07-2021
Current Status: Agreement signed
Achieved on Date: 28-10-2021 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/SL/07
Contractor Name: M/s Stonefield Construction
|
Start Date: 25-11-2021
Intended Completion Date: 14-12-2022
Original End Date: 31-03-2022
|
Total Bond Cost: 41863272.62 (418.63 lakhs)
Variation Cost: -76191.35 (-0.76 lakhs) Hence Total Bond Cost is 41787081.27 (417.87 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 5944688 for 284 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Env. Man & Moni Plan | 26.00 Job | 2.36 | 26.00 Job | 8.00 Job | 0.19 | 0.73 | 2. | Other Allied Works & Finishing Work | 4.00 Job | 7.47 | 3.00 Job | 1.00 Job | 0.67 | 2.49 | 3. | Steel Railing/crush barrier | 860.00 m | 19.07 | 860.00 m | 0.00 m | 0 | 0.00 | 4. | Protection Work | 10.00 Job | 47.82 | 10.00 Job | 2.00 Job | 2.57 | 9.56 | 5. | Errection Work | 100.00 Job | 0.91 | 100.00 Job | 0.00 Job | 0 | 0.00 | 6. | Anchors | 3172.00 m | 217.88 | 3172.00 m | 1920.00 m | 35.37 | 131.89 | 7. | Hydroseeding,3-D Net, High tensile Rolled Cable Net | 1980.00 sqm | 25.78 | 1980.00 sqm | 0.00 sqm | 0 | 0.00 | 8. | PCC in Foundation | 395.00 cum | 25.05 | 395.00 cum | 0.00 cum | 0 | 0.00 | 9. | Excavation in soil | 124.00 cum | 0.46 | 124.00 cum | 0.00 cum | 0 | 0.00 | 10. | Reinforcement work | 210.00 mt | 13.34 | 210.00 mt | 0.00 mt | 0 | 0.00 | 11. | Sand Filling | 168.20 Cum | 2.82 | 168.20 Cum | 0.00 Cum | 0 | 0.00 | 12. | Wearing Coat | 142.50 Cum | 9.91 | 142.50 Cum | 0.00 Cum | 0 | 0.00 |
Total Amount: |
372.87 |
|
38.8 |
144.67 |
|
Remarks:
No Remarks
Work Program Made On:
28-01-2022
Updation of work program on:
06-05-2022
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-March-2022 | 112.41 lakhs |
2. | 04-June-2022 | 41.60 lakhs |
3. | 30-August-2022 | 74.14 lakhs |
4. | 29-November-2022 | 92.81 lakhs |
5. | 22-December-2022 | 5.62 lakhs |
6. | 29-December-2022 | 22.25 lakhs |
7. | 31-March-2023 | 82.56 lakhs |
Total |
431.39 lakhs |
% Payment |
103.24 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | PUC vehicles | Environment & Social Compliances(Sub Project level): | Shri Purnagiri Temple Area in Tanakpur Slope MR(4042) | EMP, project information board |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 72 |
No Notice issued. |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 08-06-2022 | Ch 0+25 Grouting approx El 870 | Grouting of 32 dia Anchor in progress | Chhatrapati Pant | ` | ` | See Pic |
2. | 21-05-2022 | 0+010 | Drilling & installation of Anchor work in progress | Sohan Negi | ` | ` | See Pic |
3. | 21-05-2022 | 0+015 | Drilling & installation of solid anchor for protection work | Sohan Negi | ` | ` | See Pic |
4. | 04-04-2022 | At site | Grouting cube casting | Kishan singh rawat | ` | ` | See Pic |
5. | 04-04-2022 | At site | Grouting work in progress | Kishan singh rawat | ` | ` | See Pic |
6. | 04-04-2022 | At site | Noise test | Kishan singh rawat | ` | ` | See Pic |
7. | 04-04-2022 | At site | Pull test | Kishan singh rawat | ` | ` | See Pic |
8. | 04-04-2022 | At site | Grouting work in progress | Kishan singh rawat | ` | ` | See Pic |
9. | 04-04-2022 | At site | Grout work in progress | Kishan singh rawat | ` | ` | See Pic |
10. | 24-03-2022 | At site | Drilling work in progress | Kishan singh rawat | ` | ` | See Pic |
11. | 24-03-2022 | At site | Drilling work in progress | Kishan singh rawat | ` | ` | See Pic |
12. | 24-03-2022 | At site | Site visit with designer- Ashish Gharpure , Geologist - GVRG Acharyaulu , Geotech- B Venkateswar and Slope stabilization Dr - Manish semwal | Kishan singh rawat | ` | ` | See Pic |
13. | 24-03-2022 | At site | R/W for top platform work in progress | Kishan singh rawat | ` | ` | See Pic |
14. | 24-03-2022 | At site | Grouting work in progress | Kishan singh rawat | ` | ` | See Pic |
15. | 24-03-2022 | At site | Grouting work in progress | Kishan singh rawat | ` | ` | See Pic |
16. | 24-03-2022 | At site | Public consultation meeting at site | Kishan singh rawat | ` | ` | See Pic |
17. | 24-03-2022 | At site | At site | Kishan singh rawat | ` | ` | See Pic |
18. | 24-03-2022 | At site | Labour laws & labour safety meeting at site | Kishan singh rawat | ` | ` | See Pic |
19. | 04-03-2022 | At site | Drilling work in progress | Kishan singh rawat | ` | ` | See Pic |
20. | 04-03-2022 | 0+040 | Drilling work in progress | Kishan singh rawat | ` | ` | See Pic |
|
|