Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/SL/06 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 702 Package Name: UDRP/AF/SL/06 Sanction Cost: 1526.43  lakhs
District: Rudraprayag Block: Ukhimath Constituency: Kedarnath Circle:
DEA: DEA Guptkashi DSC: CCEE Group India Pvt. Ltd in Association with JSV DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4041   Guptkashi Kalimath Slope Motor Road at KM-2 & KM-3 (0.812 KM.) (completed)
Procurement:
Package No.: 702        Package Name: UDRP/AF/SL/06        Tender Date: 24-01-2018        Current Status: Agreement signed        Achieved on Date: 23-07-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/SL/06        Contractor Name: Bharat Construction       
Start Date: 03-08-2018        Intended Completion Date: 02-02-2020       
Total Bond Cost: 138496385.36 (1384.96 lakhs)        Variation Cost: 22846749.05 (228.47 lakhs)     Hence Total Bond Cost is   161343134.41 (1613.43 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 19804928 for 286 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.GSB/RBI/G-10.75 KM9.240.75 KM0.75 KM0.659.24
2.PC/CC i/c Prime Coat, Tack Coat0.75 KM102.520.75 KM0.75 KM7.17102.52
3.Env. Man & Moni Plan1.00 Job3.091.00 Job1.00 Job0.223.09
4.Other Allied Works & Finishing Work 1.00 Job44.371.00 Job1.00 Job3.1144.37
5.Steel Railing/crush barrier0.20 m5.990.20 m0.20 m0.425.99
6.Gravity Bench Wall364.00 m42.56364.00 m364.00 m2.9842.56
7.Anchors4963.33 m411.134963.33 m4963.33 m28.77411.13
8.Gabion work7151.50 m244.297151.50 m7151.50 m17.1244.29
9.PCC in Foundation6611.13 cum509.626611.13 cum6611.13 cum35.66509.62
10.Excavation in soil9229.89 cum56.239229.89 cum9229.89 cum3.9456.23
Total Amount: 1429.04 100   1429.04
Remarks: No Remarks       Work Program Made On: 02-11-2018       Updation of work program on: 03-04-2021      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.08-January-2019125.63  lakhs
2.28-February-2019175.95  lakhs
3.08-March-2019183.99  lakhs
4.30-March-2019112.14  lakhs
5.21-May-2019135.96  lakhs
6.20-June-201937.07  lakhs
7.30-June-2019315.17  lakhs
8.28-August-201933.50  lakhs
9.23-October-201964.05  lakhs
10.31-December-201943.21  lakhs
11.17-February-202013.46  lakhs
12.19-May-2020210.59  lakhs
Total 1450.72  lakhs
% Payment 89.92 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 494     No. of Test Done : 495      No. of Test Passed : 494      No. of Test Failed : 1   Test report of this package
Number of Pics Available on Web Repository: 150
Number of Notice(s) issued: 35

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.27-11-2021A1 AbutmentExcavation in foundation of LHS AbutmentPrem Prakash AE ` ` See Pic
2.27-11-2020086HffthDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
3.04-02-20201+060Interlocking Paving TileManoj BhattREDSC WB SPW Rudraprayag See Pic
4.04-02-20200+430MBCB Fixing in ProgressManoj BhattREDSC WB SPW Rudraprayag See Pic
5.04-01-2020Chainage 1+150Cleaning of Gabion nala ....Shivam TiwariQCDSC WB SPW TEHRI See Pic
6.27-12-20190+400 to 0+450Interlocking paving tiles work in progress.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
7.20-12-20190+395Site visit by DSC Project Manager.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
8.16-12-2019Chainage 1+080Gabion wall work on progress at valley sideShivam TiwariQuality ControlDSC WB SPW Rudraprayag See Pic
9.02-12-20191+090Paving concrete interlocking tile work in progressManoj BhattREDSC WB SPW Rudraprayag See Pic
10.02-12-20190+410Gabion Wall edging in ProgressManoj BhattREDSC WB SPW Rudraprayag See Pic
11.20-11-2019Chainage 1+040Gabion wall work in progressShivam TiwariQuality ControlDSC WB SPW Rudraprayag See Pic
12.15-11-2019Chainage 0+020Interlocking tiles work on progress ....Shivam TiwariQuality ControlDSC WB SPW Rudraprayag See Pic
13.12-11-20190+100Site sample collection for Thickness and Gradation of WBM.Manoj BhattREDSC WB SPW Rudraprayag See Pic
14.12-11-2019Chainage 0+60Social expert visitShivam TiwariQuality ControlDSC WB SPW Rudraprayag See Pic
15.12-11-20190+100Site inspected by Social Expert of PIUManoj BhattREDSC WB SPW Rudraprayag See Pic
16.12-11-20190+100Site Visit of Social Expert from PIUManoj BhattREDSC WB SPW Rudraprayag See Pic
17.12-11-20190+060Site inspected by Design Expert and PM of DSCManoj BhattREDSC WB SPW Rudraprayag See Pic
18.11-11-20191+150Site inspected by Design expert,PM of DSC with EE.Manoj BhattREDSC WB SPW Rudraprayag See Pic
19.11-11-2019Chainage 1+150Site visit by Exn and DSC TeamShivam TiwariQuality ControlDSC WB SPW Rudraprayag See Pic
20.07-11-2019At site campWorld bank social Environment siteShivam TiwariQuality ControlDSC WB SPW Rudraprayag See Pic