Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/SL/05 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 701 Package Name: UDRP/AF/SL/05 Sanction Cost: 1958.04  lakhs
District: Rudraprayag Block: Ukhimath Constituency: Kedarnath Circle:
DEA: DEA Guptkashi DSC: CCEE Group India Pvt. Ltd in Association with JSV DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4040   Guptkashi Kalimath Slope Motor Road at KM-8 (0.400 KM.) (completed)
Procurement:
Package No.: 701        Package Name: UDRP/AF/SL/05        Tender Date: 24-01-2018        Current Status: Agreement signed        Achieved on Date: 23-07-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/SL/05        Contractor Name: Bharat Construction       
Start Date: 03-08-2018        Intended Completion Date: 02-02-2020       
Total Bond Cost: 176669009.44 (1766.69 lakhs)        Variation Cost: 78479504.05 (784.8 lakhs)     Hence Total Bond Cost is   255148513.49 (2551.49 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 25793820 for 292 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.GSB/RBI/G-10.40 KM6.130.40 KM0.40 KM0.276.13
2.PC/CC i/c Prime Coat, Tack Coat0.40 KM25.670.40 KM0.40 KM1.1325.67
3.Stressing & Grouting1.00 Job49.011.00 Job1.00 Job2.1549.01
4.Env. Man & Moni Plan1.00 Job2.941.00 Job1.00 Job0.132.94
5.Other Allied Works & Finishing Work 1.00 Job108.961.00 Job1.00 Job4.78108.96
6.Steel Railing/crush barrier40.00 m1.1540.00 m40.00 m0.051.15
7.Gravity Bench Wall1725.25 m39.681725.25 m1725.25 m1.7439.68
8.Anchors26695.58 m621.0326695.58 m26695.58 m27.26621.03
9.Hydroseeding,3-D Net, High tensile Rolled Cable Net47200.00 sqm707.4447200.00 sqm47200.00 sqm31.05707.44
10.Gabion work1837.00 m165.231837.00 m1837.00 m7.25165.23
11.PCC in Foundation6516.63 cum529.886516.63 cum6516.63 cum23.26529.88
12.Excavation in soil13177.26 cum20.9913177.26 cum13177.26 cum0.9220.99
Total Amount: 2278.11 100   2278.11
Remarks: No Remarks       Work Program Made On: 02-11-2018       Updation of work program on: 06-04-2021      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.08-January-2019208.45  lakhs
2.28-February-2019165.50  lakhs
3.08-March-201962.45  lakhs
4.30-March-2019308.26  lakhs
5.16-May-2019156.03  lakhs
6.20-June-2019143.09  lakhs
7.30-June-2019503.88  lakhs
8.28-August-2019121.72  lakhs
9.30-October-2019163.15  lakhs
10.05-December-201918.68  lakhs
11.17-February-2020235.29  lakhs
12.19-May-2020191.61  lakhs
Total 2278.11  lakhs
% Payment 89.29 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 573     No. of Test Done : 578      No. of Test Passed : 573      No. of Test Failed : 5   Test report of this package
Number of Pics Available on Web Repository: 224
Number of Notice(s) issued: 34

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.04-02-20200+258Concrete Steps at Downstream of CausewayManoj BhattREDSC WB SPW Rudraprayag See Pic
2.04-02-20200+287 to 0+375Concrete Spurs on River, to Protect Gravity Bench Wall-2Manoj BhattREDSC WB SPW Rudraprayag See Pic
3.27-01-20200+340 to 0+370GI chain linking Shotcrete mesh.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
4.04-01-20200+260CC steps work in progress.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
5.03-01-20200+300 to 0+380Concrete for spur in ProgressManoj BhattREDSC WB SPW Rudraprayag See Pic
6.03-01-2020Chainage 0+260Steps for causeway work in progressShivam TiwariQCDSC WB SPW TEHRI See Pic
7.30-12-20190+065 to 0+085Gabion wall work in progress.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
8.30-12-20190+370CC wall for high tensile area protection.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
9.27-12-20190+210Providing and laying of perforated pipes for subsurface drainage.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
10.27-12-20190+260CC Steps for causeway work in progress.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
11.26-12-20190+295CC spur waork in progress.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
12.20-12-20190+120 to 0+210Hydroseeding (1st Burm),Grass Growing up.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
13.20-12-20190+290Concreting for spur work in progress.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
14.20-12-20190+140Site visit by DSC Project Manager.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
15.18-12-2019Chainage 0+350Gabion toe wall work on progressShivam TiwariQuality ControlDSC WB SPW Rudraprayag See Pic
16.17-12-20190+250cube casting and slump test for concrete steps.Shivam TiwariQuality ControlDSC WB SPW Rudraprayag See Pic
17.17-12-2019Site laboratoryCube testing at site laboratoryShivam TiwariQuality ControlDSC WB SPW Rudraprayag See Pic
18.16-12-20190+300Excavation for spur at River edge work in progress.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
19.16-12-20190+290 to 0+340Gabion wall at river edge work in progress.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
20.16-12-2019Chainage 0+230Dressing for Side DrainShivam TiwariQuality ControlDSC WB SPW Rudraprayag See Pic