UDRP/PWD/05/52/RD/060
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
70 |
Package Name: |
UDRP/PWD/05/52/RD/060 |
Sanction Cost: |
389.77 lakhs |
District: |
Dehradun |
Block: |
Chakrata |
Constituency: |
Chakrata |
Circle: |
Tehri WB Circle |
DEA: |
DEA Chakrata |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 1429 Anu-Chilhar Upper-lower (5.750 KM.) (completed) |
|
Procurement: |
Package No.: 70
Package Name: UDRP/PWD/05/52/RD/060
Tender Date: 28-01-2015
Current Status: Agreement signed
Achieved on Date: 01-07-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/05/52/RD/060
Contractor Name: Raghava Nand Bijalwan
|
Start Date: 08-07-2015
Intended Completion Date: 30-03-2017
Original End Date: 07-10-2016
|
Total Bond Cost: 32755226.04 (327.55 lakhs)
Variation Cost: 6222085.34 (62.22 lakhs) Hence Total Bond Cost is 38977311.38 (389.77 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 5.75 KM | 45.72 | 5.75 KM | 5.75 KM | 11.89 | 45.72 | 2. | R/Wall, B/ Wall Type Protection works | 1182.77 m | 122.55 | 1182.77 m | 1182.77 m | 31.87 | 122.55 | 3. | GSB/RBI/G-1 | 5.62 KM | 42.27 | 5.62 KM | 5.62 KM | 10.99 | 42.27 | 4. | G-2 | 5.62 KM | 30.69 | 5.62 KM | 5.62 KM | 7.98 | 30.69 | 5. | G-3 | 5.62 KM | 40.92 | 5.62 KM | 5.62 KM | 10.64 | 40.92 | 6. | PC/CC i/c Prime Coat, Tack Coat | 5.62 KM | 67.15 | 5.62 KM | 5.62 KM | 17.46 | 67.15 | 7. | BM i/c Prime Coat, Tack Coat | 0.00 KM | 0.00 | 0.00 KM | 0.00 KM | 0 | 0.00 | 8. | Culverts/Scupper | 3.00 No | 5.28 | 3.00 No | 3.00 No | 1.37 | 5.28 | 9. | longitudinal Drain | 5750.00 m | 17.00 | 5750.00 m | 5750.00 m | 4.42 | 17.00 | 10. | Crash Barrier | 0.00 m | 0.00 | 0.00 m | 0.00 m | 0 | 0.00 | 11. | Parapet | 488.00 No | 12.29 | 488.00 No | 488.00 No | 3.2 | 12.29 | 12. | Road Furniture | 32.00 No | 0.73 | 32.00 No | 32.00 No | 0.19 | 0.73 |
Total Amount: |
384.6 |
|
100 |
384.6 |
|
Remarks:
No Remarks
Work Program Made On:
14-09-2015
Updation of work program on:
15-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 29-September-2015 | 42.71 lakhs |
2. | 06-November-2015 | 20.58 lakhs |
3. | 18-December-2015 | 19.20 lakhs |
4. | 22-January-2016 | 24.52 lakhs |
5. | 29-February-2016 | 15.27 lakhs |
6. | 30-March-2016 | 48.09 lakhs |
7. | 03-May-2016 | 10.05 lakhs |
8. | 07-June-2016 | 8.45 lakhs |
9. | 30-June-2016 | 18.95 lakhs |
10. | 15-September-2016 | 19.02 lakhs |
11. | 03-October-2016 | 16.72 lakhs |
12. | 15-October-2016 | 6.96 lakhs |
13. | 26-October-2016 | 21.66 lakhs |
14. | 15-November-2016 | 14.53 lakhs |
15. | 30-December-2016 | 25.47 lakhs |
16. | 15-March-2017 | 17.83 lakhs |
17. | 12-April-2017 | 29.55 lakhs |
18. | 30-June-2017 | 29.43 lakhs |
Total |
388.99 lakhs |
% Payment |
99.8 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 8.45 lakhs
Balance to be Recovered -8.45 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 305 |
Number of Notice(s) issued: 60 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 08-03-2017 | Ch 1.90 km | Inspection of 64 my steel bridge. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
2. | 07-03-2017 | At Ch 1/36-37 | SE Sir 8th Circle Tehri Visit at Anu chilhaar and Checking of existing Steel bridge | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
3. | 07-03-2017 | At ch 5/26 | P. C. Thickness checking by SE sir (8th circle Tehri) found satisfactory | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
4. | 07-03-2017 | At Ch 5/28 | SE sir (8th Circle Tehri) Visit regarding quality checking | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
5. | 11-02-2017 | At 1/36 (Existing Bridge) | Visit of SE sir regarding checking of work quality and Existing bridge checking | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
6. | 01-02-2017 | CH 2.200 | Removing loose earth material under pipe culvert is in progress | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
7. | 01-02-2017 | Ch 3/10 | Slip | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
8. | 01-02-2017 | CH 3/1 | Slip | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
9. | 31-01-2017 | 2.20 km | Location of pipe culvert at km 2.20 , removable earth has been cleared rest is huge as clearly shown on this pic. Pl refer blog of Mr ashish anthwal on pic id 26037. It is a sliding zone. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
10. | 18-01-2017 | Ch 1/24 | Casting of parapet with delenator | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
11. | 11-01-2017 | At Ch 0/0-0/2 | KC drain work | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
12. | 20-12-2016 | At ch 2/8 | Pipe culvert completed checking by AE and EE sir | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
13. | 19-12-2016 | Ch 2.200 km | Constitution of pipe culvert complete. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
14. | 28-11-2016 | Ch 2/8 | Checking slope of P.C.C of pipe culvert | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
15. | 28-11-2016 | Ch 2/8 | Cube filling for testing strength | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
16. | 28-11-2016 | Ch 2/8 | P.C.C M-10 at base for pipe Culvert | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
17. | 28-11-2016 | CH 2/8 | Excavation for pipe culvert | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
18. | 26-11-2016 | At ch 1/9 | PC work at balance patch at 1/9 | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
19. | 26-11-2016 | At ch 2/30 | PC work with Katcha drain | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
20. | 26-11-2016 | At ch 3/0 | WBM G1 Stone stock | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
|
|