Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/05/52/RD/060 Agreement signed
Project: UDRP-RB Package No.: 70 Package Name: UDRP/PWD/05/52/RD/060 Sanction Cost: 389.77  lakhs
District: Dehradun Block: Chakrata Constituency: Chakrata Circle: Tehri WB Circle
DEA: DEA Chakrata DSC: Egis International DSC Scope: only Supervision No.of Sub project : 1
Subproject in this package
1  1429   Anu-Chilhar Upper-lower (5.750 KM.) (completed)
Procurement:
Package No.: 70        Package Name: UDRP/PWD/05/52/RD/060        Tender Date: 28-01-2015        Current Status: Agreement signed        Achieved on Date: 01-07-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/05/52/RD/060        Contractor Name: Raghava Nand Bijalwan       
Start Date: 08-07-2015        Intended Completion Date: 30-03-2017        Original End Date:  07-10-2016
Total Bond Cost: 32755226.04 (327.55 lakhs)        Variation Cost: 6222085.34 (62.22 lakhs)     Hence Total Bond Cost is   38977311.38 (389.77 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence5.75 KM45.725.75 KM5.75 KM11.8945.72
2.R/Wall, B/ Wall Type Protection works1182.77 m122.551182.77 m1182.77 m31.87122.55
3.GSB/RBI/G-15.62 KM42.275.62 KM5.62 KM10.9942.27
4.G-25.62 KM30.695.62 KM5.62 KM7.9830.69
5.G-35.62 KM40.925.62 KM5.62 KM10.6440.92
6.PC/CC i/c Prime Coat, Tack Coat5.62 KM67.155.62 KM5.62 KM17.4667.15
7.BM i/c Prime Coat, Tack Coat0.00 KM0.000.00 KM0.00 KM00.00
8.Culverts/Scupper 3.00 No5.283.00 No3.00 No1.375.28
9.longitudinal Drain5750.00 m17.005750.00 m5750.00 m4.4217.00
10.Crash Barrier0.00 m0.000.00 m0.00 m00.00
11.Parapet488.00 No12.29488.00 No488.00 No3.212.29
12.Road Furniture32.00 No0.7332.00 No32.00 No0.190.73
Total Amount: 384.6 100   384.6
Remarks: No Remarks       Work Program Made On: 14-09-2015       Updation of work program on: 15-05-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.29-September-201542.71  lakhs
2.06-November-201520.58  lakhs
3.18-December-201519.20  lakhs
4.22-January-201624.52  lakhs
5.29-February-201615.27  lakhs
6.30-March-201648.09  lakhs
7.03-May-201610.05  lakhs
8.07-June-20168.45  lakhs
9.30-June-201618.95  lakhs
10.15-September-201619.02  lakhs
11.03-October-201616.72  lakhs
12.15-October-20166.96  lakhs
13.26-October-201621.66  lakhs
14.15-November-201614.53  lakhs
15.30-December-201625.47  lakhs
16.15-March-201717.83  lakhs
17.12-April-201729.55  lakhs
18.30-June-201729.43  lakhs
Total 388.99  lakhs
% Payment 99.8 %
Advance Amount:  0.00  lakhs        Recovered Amount:  8.45  lakhs        Balance to be Recovered  -8.45  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 371     No. of Test Done : 385      No. of Test Passed : 371      No. of Test Failed : 14   Test report of this package
Number of Pics Available on Web Repository: 305
Number of Notice(s) issued: 60

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.08-03-2017Ch 1.90 kmInspection of 64 my steel bridge.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
2.07-03-2017At Ch 1/36-37SE Sir 8th Circle Tehri Visit at Anu chilhaar and Checking of existing Steel bridgeRajan NautiyalJEUDRP R&B Chakrata See Pic
3.07-03-2017At ch 5/26P. C. Thickness checking by SE sir (8th circle Tehri) found satisfactoryRajan NautiyalJEUDRP R&B Chakrata See Pic
4.07-03-2017At Ch 5/28SE sir (8th Circle Tehri) Visit regarding quality checkingRajan NautiyalJEUDRP R&B Chakrata See Pic
5.11-02-2017At 1/36 (Existing Bridge)Visit of SE sir regarding checking of work quality and Existing bridge checkingRajan NautiyalJEUDRP R&B Chakrata See Pic
6.01-02-2017CH 2.200Removing loose earth material under pipe culvert is in progressAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
7.01-02-2017Ch 3/10SlipAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
8.01-02-2017CH 3/1SlipAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
9.31-01-20172.20 kmLocation of pipe culvert at km 2.20 , removable earth has been cleared rest is huge as clearly shown on this pic. Pl refer blog of Mr ashish anthwal on pic id 26037. It is a sliding zone.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
10.18-01-2017Ch 1/24Casting of parapet with delenatorAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
11.11-01-2017At Ch 0/0-0/2KC drain workRajan NautiyalJEUDRP R&B Chakrata See Pic
12.20-12-2016At ch 2/8Pipe culvert completed checking by AE and EE sirRajan NautiyalJEUDRP R&B Chakrata See Pic
13.19-12-2016Ch 2.200 kmConstitution of pipe culvert complete.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
14.28-11-2016Ch 2/8Checking slope of P.C.C of pipe culvertAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
15.28-11-2016Ch 2/8Cube filling for testing strengthAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
16.28-11-2016Ch 2/8P.C.C M-10 at base for pipe CulvertAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
17.28-11-2016CH 2/8Excavation for pipe culvertAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
18.26-11-2016At ch 1/9PC work at balance patch at 1/9Rajan NautiyalJEUDRP R&B Chakrata See Pic
19.26-11-2016At ch 2/30PC work with Katcha drainRajan NautiyalJEUDRP R&B Chakrata See Pic
20.26-11-2016At ch 3/0WBM G1 Stone stockRajan NautiyalJEUDRP R&B Chakrata See Pic