UDRP/PWD/03/29/RD/059
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
69 |
Package Name: |
UDRP/PWD/03/29/RD/059 |
Sanction Cost: |
250.13 lakhs |
District: |
Rudraprayag |
Block: |
Jakholi |
Constituency: |
Rudraprayag |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Guptkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 2542 Sirain-Chaura- Bhatwari Motor Road (3.000 KM.) (completed) |
|
Procurement: |
Package No.: 69
Package Name: UDRP/PWD/03/29/RD/059
Tender Date: 24-12-2014
Current Status: Agreement signed
Achieved on Date: 21-07-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/03/29/RD/059
Contractor Name: Tushar Builders
|
Start Date: 28-07-2015
Intended Completion Date: 27-12-2016
Original End Date: 27-10-2016
|
Total Bond Cost: 20737723.9 (207.38 lakhs)
Variation Cost: 4275136.46 (42.75 lakhs) Hence Total Bond Cost is 25012860.36 (250.13 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 207380 for 20 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 3.00 KM | 9.60 | 3.00 KM | 3.00 KM | 4.63 | 9.60 | 2. | R/Wall, B/ Wall Type Protection works | 830.00 m | 47.51 | 830.00 m | 830.00 m | 22.91 | 47.51 | 3. | G-2 | 6.60 KM | 33.45 | 6.60 KM | 6.60 KM | 16.13 | 33.45 | 4. | G-3 | 3.30 KM | 21.83 | 3.30 KM | 3.30 KM | 10.53 | 21.83 | 5. | PC/CC i/c Prime Coat, Tack Coat | 3.30 KM | 35.68 | 3.30 KM | 3.30 KM | 17.21 | 35.68 | 6. | Cause Way | 4.00 No | 2.79 | 4.00 No | 4.00 No | 1.35 | 2.79 | 7. | Culverts/Scupper | 11.00 No | 27.95 | 11.00 No | 11.00 No | 13.48 | 27.95 | 8. | Crash Barrier | 100.00 m | 2.20 | 100.00 m | 100.00 m | 1.06 | 2.20 | 9. | Parapet | 300.00 No | 8.98 | 300.00 No | 300.00 No | 4.33 | 8.98 | 10. | Road Furniture | 82.00 No | 0.52 | 82.00 No | 82.00 No | 0.25 | 0.52 | 11. | Other Allied Works & Finishing Work | 1.00 Job | 16.86 | 1.00 Job | 1.00 Job | 8.13 | 16.86 |
Total Amount: |
207.37 |
|
100 |
207.37 |
|
Remarks:
No Remarks
Work Program Made On:
29-09-2015
Updation of work program on:
19-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 24-September-2015 | 32.21 lakhs |
2. | 22-December-2015 | 13.04 lakhs |
3. | 29-February-2016 | 26.14 lakhs |
4. | 29-June-2016 | 35.76 lakhs |
5. | 23-August-2016 | 35.15 lakhs |
6. | 13-September-2016 | 27.96 lakhs |
7. | 26-October-2016 | 26.41 lakhs |
8. | 21-January-2017 | 20.61 lakhs |
9. | 30-June-2017 | 21.95 lakhs |
Total |
239.23 lakhs |
% Payment |
95.64 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 89 |
Number of Notice(s) issued: 62 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 21-01-2017 | 1+00 | Giving instructions about retaining wall by EE sir | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
2. | 21-12-2016 | 0+900 | Gradation of g2 materials checked by SE sir 7th circle | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
3. | 21-12-2016 | 0+900 | Wbm g1 ,g2,,g3 and PC thickness checking by SE sir 7th circle | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
4. | 21-12-2016 | 0/180 | Inspection of cause way by 7th circle S.E. sir & A.e. sir & checking thickness | Suresh Chandra Sharma | JE | UDRP R&B Guptkashi | See Pic |
5. | 04-12-2016 | 3/300 | Cooliwall in perogresh | Suresh Chandra Sharma | JE | UDRP R&B Guptkashi | See Pic |
6. | 22-10-2016 | Ch. 1500 | PC laying & rolling | Rahul Panwar | Survey Engineer | NH Srinagar | See Pic |
7. | 22-10-2016 | Ch. 1590 | PC Laying and Rolling | Rahul Panwar | Survey Engineer | NH Srinagar | See Pic |
8. | 20-10-2016 | Ch. 2200 | PC rolling | Rahul Panwar | Survey Engineer | NH Srinagar | See Pic |
9. | 19-10-2016 | Ch. 0+850 | Screening material laying over G3 | Rahul Panwar | Survey Engineer | NH Srinagar | See Pic |
10. | 18-10-2016 | Ch. 0.850 | Prime coat surface | Rahul Panwar | Survey Engineer | NH Srinagar | See Pic |
11. | 18-10-2016 | Ch. 2200 | Tack coat laying | Rahul Panwar | Survey Engineer | NH Srinagar | See Pic |
12. | 14-10-2016 | Ch. 2250 | Thickness checking | Amod Kumar Thakur | RE | DSC1 R&B WB Rudraprayag | See Pic |
13. | 14-10-2016 | CH. 2300 | PC + seal coat surface | Amod Kumar Thakur | RE | DSC1 R&B WB Rudraprayag | See Pic |
14. | 14-10-2016 | 2+300 | Seal coat Temperature checking at laying | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
15. | 14-10-2016 | 2+300 | Laying of seal coat | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
16. | 27-08-2016 | 1050 | demage road due to land slide | Jagat Chand Ramola | JE | UDRP R&B Guptkashi | See Pic |
17. | 17-08-2016 | 1180 | slip | Jagat Chand Ramola | JE | UDRP R&B Guptkashi | See Pic |
18. | 17-08-2016 | 1+00 | Settlement due to land slide | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
19. | 20-07-2016 | 980 | r/wall demage due to heavy slip | Jagat Chand Ramola | JE | UDRP R&B Guptkashi | See Pic |
20. | 20-07-2016 | 950 | slip clearance work on progress | Jagat Chand Ramola | JE | UDRP R&B Guptkashi | See Pic |
|
|