                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/52 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 667 Package Name: UDRP/AF/BR/52 Sanction Cost: 986.57  lakhs
District: Pithoragarh Block: Berinag Constituency: Gangolihat Circle:
DEA: DEA Munsyari DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4063   Bridge at Gangolihat Over Ramganga River at Berinag Vinayak Puranathal Bhuwani MR (90.000 M.) (in prorgress)
Procurement:
Package No.: 667        Package Name: UDRP/AF/BR/52        Tender Date: 17-06-2020        Current Status: Agreement signed        Achieved on Date: 29-01-2021

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/52        Contractor Name: M/s Hillways Construction Company Pvt. Ltd.       
Start Date: 13-02-2021        Intended Completion Date: 14-06-2023        Original End Date:  31-03-2022
Total Bond Cost: 101220221.76 (1012.2 lakhs)        Variation Cost: 15043958.64 (150.44 lakhs)     Hence Total Bond Cost is   116264180.4 (1162.64 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 16093980 for 318 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job30.251.00 Job1.00 Job2.9930.25
2.Foundation RHS1.00 Job35.031.00 Job1.00 Job3.4635.03
3.Foundation LHS1.00 Job35.031.00 Job1.00 Job3.4635.03
4.Abutment Superstructure RHS1.00 Job25.651.00 Job1.00 Job2.5425.65
5.Abutment Superstructure LHS1.00 Job25.651.00 Job1.00 Job2.5425.65
6.Fixing of chequered Plate/RCC Deck597.35 sqm43.74597.35 sqm597.35 sqm4.3243.74
7.Steel Railing/crush barrier183.80 m10.71183.80 m183.80 m1.0610.71
8.Approach Ramp /path 160.00 m39.50160.00 m160.00 m3.939.50
9.Protection Work1.00 Job4.841.00 Job1.00 Job0.484.84
10.Errection Work1.00 Job266.761.00 Job1.00 Job26.36266.76
11.Fabrication Work1.00 job495.021.00 job1.00 job48.91495.02
Total Amount: 1012.18 100   1012.18
Remarks: No Remarks       Work Program Made On: 17-03-2021       Updation of work program on: 27-02-2023      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-August-202139.62  lakhs
2.09-November-2021425.90  lakhs
3.30-November-202117.02  lakhs
4.31-December-202158.11  lakhs
5.11-January-2022151.01  lakhs
6.28-February-202235.89  lakhs
7.31-March-20225.46  lakhs
8.31-March-2023288.47  lakhs
9.22-June-202389.97  lakhs
Total 1111.45  lakhs
% Payment 95.6 %
Advance Amount:  274.34  lakhs        Recovered Amount:  274.34  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 360     No. of Test Done : 367      No. of Test Passed : 367      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 148
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.28-03-2022Abutment A2Gabion protection work completed.Anuj shekhar ` ` See Pic
2.28-03-2022Abutment A1Slump test for Abutment A1 Cap casting ,result found ok.Anuj shrkhar ` ` See Pic
3.28-03-2022Dumping yardProtection work by gabion, work in progress.Anuj shekhar ` ` See Pic
4.28-03-2022Dumping yard, abutment A1 sideProtection work by gabion,work in progress.Anuj shekhar ` ` See Pic
5.28-03-2022Abutment A1RCC M35 Pouring for abutment cap ,work in progress.Anuj shekhar ` ` See Pic
6.28-03-2022Abutment A1HP stone and backfilling upto 9th lift of abutment A1, work completed.Anuj shekhar ` ` See Pic
7.28-03-2022Abutment A1RCC M35 Pouring for Abutment Cap, work in progress.Anuj shekhar ` ` See Pic
8.28-03-2022RCC M35 Pouring for abutment A1 cap ,work in progress.Anuj Shekhar ` ` See Pic
9.28-02-2022Abutment A1 sideAbutment cap rcc work completeMukul Saxena ` ` See Pic
10.28-02-2022Abutment A1 sideProtection work in progressMukul saxena ` ` See Pic
11.28-02-2022Abutment A1Abutment cap rcc work in progressMukul saxena ` ` See Pic
12.27-02-2022Abutment A1RCC M35 Cube casting for 9th lift of abutment A1Anuj shekhar ` ` See Pic
13.27-02-2022Abutment A1Slump test for 9th lift of abutment A, result found ok.Anuj shekhar ` ` See Pic
14.27-02-2022Approach road ,Abutment A1 sideExcavation for approach road ,work in progress.Anuj shekhar ` ` See Pic
15.27-02-2022Abutment A1RCC M35 Pouring in 9th lift of abutment A1, work in progress.Anuj shekhar ` ` See Pic
16.27-02-2022Abutment A1RCC M35 Pouring in 9th lift of abutment A1, work in progress.Anuj shekhar ` ` See Pic
17.24-02-2022Abutment A1Reinforcement and shuttering work of Abutment Cap ,work in progress.Anuj shekhar ` ` See Pic
18.24-02-2022Abutment A1Site visit by CME and Environmental expert at Ramagnga River BR-52Anuj shekhar ` ` See Pic
19.19-02-2022BR 52 Ramganga River Purana thal Berinag PithoragarhAbutment A1 site 9th Lift ( final lift ) Casting And Cube cast...Virendra Singh Negi ` ` See Pic
20.19-02-2022BR 52 km 25 Puranathal Berinag pithoragarhAbutment A1 Site Shaft & Return Wall 9th lift casting And Slump check....Virendra Singh Negi (QC) ` ` See Pic