Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/52 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 667 Package Name: UDRP/AF/BR/52 Sanction Cost: 986.57  lakhs
District: Pithoragarh Block: Berinag Constituency: Gangolihat Circle:
DEA: DEA Munsyari DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4063   Bridge at Gangolihat Over Ramganga River at Berinag Vinayak Puranathal Bhuwani MR (90.000 M.) (in prorgress)
Procurement:
Package No.: 667        Package Name: UDRP/AF/BR/52        Tender Date: 17-06-2020        Current Status: Agreement signed        Achieved on Date: 29-01-2021

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/52        Contractor Name: M/s Hillways Construction Company Pvt. Ltd.       
Start Date: 13-02-2021        Intended Completion Date: 31-03-2022       
Total Bond Cost: 101220221.76 (1012.2 lakhs)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 15385440 for 304 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job30.251.00 Job0.15 Job0.454.54
2.Foundation RHS1.00 Job35.031.00 Job1.00 Job3.4635.03
3.Foundation LHS1.00 Job35.031.00 Job0.20 Job0.697.01
4.Abutment Superstructure RHS1.00 Job25.651.00 Job0.75 Job1.919.24
5.Abutment Superstructure LHS1.00 Job25.651.00 Job0.00 Job00.00
6.Fixing of chequered Plate/RCC Deck183.40 sqm43.74183.40 sqm0.00 sqm00.00
7.Steel Railing/crush barrier183.90 m10.71183.90 m0.00 m00.00
8.Approach Ramp /path 160.00 m39.50160.00 m20.00 m0.494.94
9.Protection Work1.00 Job4.841.00 Job0.00 Job00.00
10.Errection Work1.00 Job266.761.00 Job0.00 Job00.00
11.Fabrication Work1.00 job495.021.00 job1.00 job48.91495.02
Total Amount: 1012.18 55.9   565.78
Remarks: No Remarks       Work Program Made On: 17-03-2021       Updation of work program on: 21-09-2021      
Work Program Status:Work Programme workable.
Financial Progress
SNo. Date Payment
1.28-August-202139.62  lakhs
2.09-November-2021425.90  lakhs
Total 465.52  lakhs
% Payment 45.99 %
Advance Amount:  214.20  lakhs        Recovered Amount:  214.20  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 129     No. of Test Done : 136      No. of Test Passed : 136      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 64
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.22-11-2021Abutment A1Abutment A1 raft reinforcement work in progress.Anuj shekhar ` ` See Pic
2.22-11-2021BR -52Sample collection for water quality monitoring test,BR-52Anuj shekhar ` ` See Pic
3.22-11-2021Abutment LHSAir quality monitoring test,BR-52Anuj shekhar ` ` See Pic
4.22-11-2021Abutment A1Noise quality monitoring test, BR-52Anuj shekhar ` ` See Pic
5.18-11-2021Abutment RHSAir Quality MonitoringNeeraj Tewari ` ` See Pic
6.18-11-2021Abutment LHSAir Monitoring Test.Neeraj Tewari ` ` See Pic
7.18-11-2021Abutment LHSNoise level monitoring test.Neeraj Tewari ` ` See Pic
8.18-11-2021Abutment LHSDrilling work for anchoring.Neeraj Tewari ` ` See Pic
9.17-11-2021Abutment A1 BR-52Pull-out test for raft anchors in progress.Sanjeev Kumar ` ` See Pic
10.17-11-2021Abutment A1Pull-out test for rock anchors in progress at BR-52.Sanjeev Kumar ` ` See Pic
11.17-11-2021Abutment A1 EndPull-out test for raft anchors. BR-52Sanjeev Kumar ` ` See Pic
12.14-11-2021Abutment A1Abutment foundation layout checkingMukul saxena ` ` See Pic
13.12-11-2021BR 52 Puranathal km 25 Berinag (Pithoragarh)BR 52 Abutment A2 side Cap casting And Cube cast..Virendra singh negi ` ` See Pic
14.12-11-2021BR 52 Puranathal km 25 Berinag (Pithoragarh)BR 52 Abutment A2 side Cap casting And Slump Test.. Slump Value ..70 mmVirendra singh negi ` ` See Pic
15.11-11-2021Abutment A2RCC M35 IN ABUTMENT CAP ,WORK COMPLETED.Anuj shekhar ` ` See Pic
16.11-11-2021Abutment A2RCC M35 in abutment cap ,work completed.Anuj shekhar ` ` See Pic
17.11-11-2021abutment A2RCC M35 pouring for 5th lift ,work in progress.Anuj shekhar ` ` See Pic
18.11-11-2021Abutment A1Placing and fixing of anchoring road with epoxi for abutment A1Anuj shekhar ` ` See Pic
19.09-11-2021Abutment A1Drilling work for rock anchoring in abutment A1Anuj shekhar ` ` See Pic
20.09-11-2021Abutment A2Abutment cap rcc work in progressMukul Saxena ` ` See Pic