Package Profile Report

UDRP/AF/BR/85 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 666 Package Name: UDRP/AF/BR/85 Sanction Cost: 524.31  lakhs
District: Almora Block: Chaukhutiya Constituency: Dwarahat Circle:
DEA: DEA Bageshwar DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4126   Steel Truss Bridle Bridge on Palagwadi-Chalureseem Bridle Road on Ramganga River (70.000 M.) (in prorgress)
Procurement:
Package No.: 666        Package Name: UDRP/AF/BR/85        Tender Date: 05-09-2020        Current Status: Agreement signed        Achieved on Date: 19-01-2021

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/85        Contractor Name: M/s Manu Dev Contractor       
Start Date: 06-02-2021        Intended Completion Date: 22-09-2023        Original End Date:  31-03-2022
Total Bond Cost: 49143534.4 (491.44 lakhs)        Variation Cost: 6742412.91 (67.42 lakhs)     Hence Total Bond Cost is   55885947.31 (558.86 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 15996372 for 651 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Env. Man & Moni Plan1.00 Job4.481.00 Job0.30 Job0.271.35
2.Other Allied Works & Finishing Work 4.00 Job2.994.00 Job2.00 Job0.31.50
3.Foundation RHS1.00 Job21.821.00 Job0.00 Job00.00
4.Foundation LHS1.00 Job21.821.00 Job1.00 Job4.4421.82
5.Abutment Superstructure RHS1.00 Job1.361.00 Job0.00 Job00.00
6.Abutment Superstructure LHS1.00 Job1.361.00 Job0.00 Job00.00
7.Fixing of chequered Plate/RCC Deck1.00 sqm1.761.00 sqm0.00 sqm00.00
8.Steel Railing/crush barrier142.40 m2.15142.40 m0.00 m00.00
9.Approach Ramp /path 150.00 m50.92150.00 m0.00 m00.00
10.Protection Work1.00 Job28.111.00 Job0.00 Job00.00
11.Errection Work1.00 Job84.701.00 Job0.00 Job00.00
12.Fabrication Work1.00 job178.311.00 job0.50 job18.1489.15
13.Abutment Substructure RHS1.00 Job45.831.00 Job0.00 Job00.00
14.Abutment Substructure LHS1.00 Job45.831.00 Job0.00 Job00.00
Total Amount: 491.44 23.16   113.82
Remarks: No Remarks       Work Program Made On: 06-03-2021       Updation of work program on: 24-05-2022      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.15-June-202225.69  lakhs
2.03-August-20229.77  lakhs
3.21-October-202211.36  lakhs
4.21-December-202222.83  lakhs
5.20-January-202343.84  lakhs
6.28-January-202322.05  lakhs
Total 135.54  lakhs
% Payment 24.25 %
Advance Amount:  123.65  lakhs        Recovered Amount:  9.98  lakhs        Balance to be Recovered  113.67  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Environment & Social Compliances(Package level):No Pending Issue
Environment & Social Compliances(Sub Project level):
Steel Truss Bridle Bridge on Palagwadi-Chalureseem Bridle Road on Ramganga River(4126)EMP
Detailed report of this Package
Quality
No. of Test Required : 58     No. of Test Done : 58      No. of Test Passed : 58      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 36
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.20-06-2022BR-85, PalagwadiAbutment A1 side raft casted cubes.Lalit Kumar (SS) ` ` See Pic
2.20-06-2022BR-85, PalagwadiAbutment A1 side raft casting work in progress.Lalit Kumar (SS) ` ` See Pic
3.20-06-2022BR-85, PalagwadiAbutment A1 side raft casting work in progress.Lalit Kumar (SS) ` ` See Pic
4.20-06-2022BR-85, PalagwadiAbutment A1 side raft casting work in progress.Lalit Kumar (SS) ` ` See Pic
5.20-06-2022BR-85, PalagwadiAbutment A1 side raft casting work in progress.Lalit Kumar (SS) ` ` See Pic
6.20-06-2022BR-85, PalagwadiAbutment A1 side raft casting work in progress.Lalit Kumar (SS) ` ` See Pic
7.20-06-2022BR-85, PalagwadiAbutment A1 side raft slump test. And slump value is 75mm.Lalit Kumar (SS) ` ` See Pic
8.13-06-2022Paganwadiraft foundation A1 side abutment is completed at BR-85 paganwadiSumit Bisht (ss)unknownunknown See Pic
9.07-06-2022BR-85, PalagwadiAbutment A1 side raft return wall vertical reinforcement work in progress.Lalit Kumar (SS) ` ` See Pic
10.07-06-2022BR-85, PalagwadiAbutment A1 side raft return wall vertical reinforcement work in progress.Lalit Kumar (SS) ` ` See Pic
11.07-06-2022BR-85, PalagwadiAbutment A1 side raft return wall vertical reinforcement work in progress.Lalit Kumar (SS) ` ` See Pic
12.07-06-2022BR-85, PalagwadiAbutment A1 side raft return wall vertical reinforcement work in progress.Lalit Kumar (SS) ` ` See Pic
13.07-06-2022BR-85, PalagwadiAbutment A1 side raft return wall vertical reinforcement work in progress.Lalit Kumar (SS) ` ` See Pic
14.07-06-2022BR-85, PalagwadiAbutment A1 side return wall vertical reinforcement work in progress.Lalit Kumar (SS) ` ` See Pic
15.02-06-2022Bridge BR85Raft reinforcement binding in progress for LHS abutment.Rajesh sharma ` ` See Pic
16.01-06-2022BR-85, PalagwadiAbutment A1 side raft reinforcement work in progress.Lalit Kumar (SS) ` ` See Pic
17.01-06-2022BR-85, PalagwadiAbutment A1 side raft reinforcement work in progress.Lalit Kumar (SS) ` ` See Pic
18.01-06-2022BR-85, PalagwadiAbutment A1 side raft reinforcement work in progress.Lalit Kumar (SS) ` ` See Pic
19.31-05-2022Bridge BR85LHS raft steel reinforcement binding in progress.Rajesh sharma ` ` See Pic
20.06-05-2022BR 85 PalagwadiLabour is not presentSS Desh Deepakunknownunknown See Pic