UDRP/AF/BR/85
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
666 |
Package Name: |
UDRP/AF/BR/85 |
Sanction Cost: |
524.31 lakhs |
District: |
Almora |
Block: |
Chaukhutiya |
Constituency: |
Dwarahat |
Circle: |
|
DEA: |
DEA Bageshwar |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4126 Steel Truss Bridle Bridge on Palagwadi-Chalureseem Bridle Road on Ramganga River (70.000 M.) (in prorgress) |
|
Procurement: |
Package No.: 666
Package Name: UDRP/AF/BR/85
Tender Date: 05-09-2020
Current Status: Agreement signed
Achieved on Date: 19-01-2021 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/85
Contractor Name: M/s Manu Dev Contractor
|
Start Date: 06-02-2021
Intended Completion Date: 22-09-2023
Original End Date: 31-03-2022
|
Total Bond Cost: 49143534.4 (491.44 lakhs)
Variation Cost: 6742412.91 (67.42 lakhs) Hence Total Bond Cost is 55885947.31 (558.86 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 15996372 for 651 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Env. Man & Moni Plan | 1.00 Job | 4.48 | 1.00 Job | 0.30 Job | 0.27 | 1.35 | 2. | Other Allied Works & Finishing Work | 4.00 Job | 2.99 | 4.00 Job | 2.00 Job | 0.3 | 1.50 | 3. | Foundation RHS | 1.00 Job | 21.82 | 1.00 Job | 0.00 Job | 0 | 0.00 | 4. | Foundation LHS | 1.00 Job | 21.82 | 1.00 Job | 1.00 Job | 4.44 | 21.82 | 5. | Abutment Superstructure RHS | 1.00 Job | 1.36 | 1.00 Job | 0.00 Job | 0 | 0.00 | 6. | Abutment Superstructure LHS | 1.00 Job | 1.36 | 1.00 Job | 0.00 Job | 0 | 0.00 | 7. | Fixing of chequered Plate/RCC Deck | 1.00 sqm | 1.76 | 1.00 sqm | 0.00 sqm | 0 | 0.00 | 8. | Steel Railing/crush barrier | 142.40 m | 2.15 | 142.40 m | 0.00 m | 0 | 0.00 | 9. | Approach Ramp /path | 150.00 m | 50.92 | 150.00 m | 0.00 m | 0 | 0.00 | 10. | Protection Work | 1.00 Job | 28.11 | 1.00 Job | 0.00 Job | 0 | 0.00 | 11. | Errection Work | 1.00 Job | 84.70 | 1.00 Job | 0.00 Job | 0 | 0.00 | 12. | Fabrication Work | 1.00 job | 178.31 | 1.00 job | 0.50 job | 18.14 | 89.15 | 13. | Abutment Substructure RHS | 1.00 Job | 45.83 | 1.00 Job | 0.00 Job | 0 | 0.00 | 14. | Abutment Substructure LHS | 1.00 Job | 45.83 | 1.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
491.44 |
|
23.16 |
113.82 |
|
Remarks:
No Remarks
Work Program Made On:
06-03-2021
Updation of work program on:
24-05-2022
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 15-June-2022 | 25.69 lakhs |
2. | 03-August-2022 | 9.77 lakhs |
3. | 21-October-2022 | 11.36 lakhs |
4. | 21-December-2022 | 22.83 lakhs |
5. | 20-January-2023 | 43.84 lakhs |
6. | 28-January-2023 | 22.05 lakhs |
Total |
135.54 lakhs |
% Payment |
24.25 % |
|
Advance Amount: 123.65 lakhs
Recovered Amount: 9.98 lakhs
Balance to be Recovered 113.67 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | No Pending Issue | Environment & Social Compliances(Sub Project level): | Steel Truss Bridle Bridge on Palagwadi-Chalureseem Bridle Road on Ramganga River(4126) | EMP |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 36 |
No Notice issued. |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 20-06-2022 | BR-85, Palagwadi | Abutment A1 side raft casted cubes. | Lalit Kumar (SS) | ` | ` | See Pic |
2. | 20-06-2022 | BR-85, Palagwadi | Abutment A1 side raft casting work in progress. | Lalit Kumar (SS) | ` | ` | See Pic |
3. | 20-06-2022 | BR-85, Palagwadi | Abutment A1 side raft casting work in progress. | Lalit Kumar (SS) | ` | ` | See Pic |
4. | 20-06-2022 | BR-85, Palagwadi | Abutment A1 side raft casting work in progress. | Lalit Kumar (SS) | ` | ` | See Pic |
5. | 20-06-2022 | BR-85, Palagwadi | Abutment A1 side raft casting work in progress. | Lalit Kumar (SS) | ` | ` | See Pic |
6. | 20-06-2022 | BR-85, Palagwadi | Abutment A1 side raft casting work in progress. | Lalit Kumar (SS) | ` | ` | See Pic |
7. | 20-06-2022 | BR-85, Palagwadi | Abutment A1 side raft slump test.
And slump value is 75mm. | Lalit Kumar (SS) | ` | ` | See Pic |
8. | 13-06-2022 | Paganwadi | raft foundation A1 side abutment is completed at BR-85 paganwadi | Sumit Bisht (ss) | unknown | unknown | See Pic |
9. | 07-06-2022 | BR-85, Palagwadi | Abutment A1 side raft return wall vertical reinforcement work in progress. | Lalit Kumar (SS) | ` | ` | See Pic |
10. | 07-06-2022 | BR-85, Palagwadi | Abutment A1 side raft return wall vertical reinforcement work in progress. | Lalit Kumar (SS) | ` | ` | See Pic |
11. | 07-06-2022 | BR-85, Palagwadi | Abutment A1 side raft return wall vertical reinforcement work in progress. | Lalit Kumar (SS) | ` | ` | See Pic |
12. | 07-06-2022 | BR-85, Palagwadi | Abutment A1 side raft return wall vertical reinforcement work in progress. | Lalit Kumar (SS) | ` | ` | See Pic |
13. | 07-06-2022 | BR-85, Palagwadi | Abutment A1 side raft return wall vertical reinforcement work in progress. | Lalit Kumar (SS) | ` | ` | See Pic |
14. | 07-06-2022 | BR-85, Palagwadi | Abutment A1 side return wall vertical reinforcement work in progress. | Lalit Kumar (SS) | ` | ` | See Pic |
15. | 02-06-2022 | Bridge BR85 | Raft reinforcement binding in progress for LHS abutment. | Rajesh sharma | ` | ` | See Pic |
16. | 01-06-2022 | BR-85, Palagwadi | Abutment A1 side raft reinforcement work in progress. | Lalit Kumar (SS) | ` | ` | See Pic |
17. | 01-06-2022 | BR-85, Palagwadi | Abutment A1 side raft reinforcement work in progress. | Lalit Kumar (SS) | ` | ` | See Pic |
18. | 01-06-2022 | BR-85, Palagwadi | Abutment A1 side raft reinforcement work in progress. | Lalit Kumar (SS) | ` | ` | See Pic |
19. | 31-05-2022 | Bridge BR85 | LHS raft steel reinforcement binding in progress. | Rajesh sharma | ` | ` | See Pic |
20. | 06-05-2022 | BR 85 Palagwadi | Labour is not present | SS Desh Deepak | unknown | unknown | See Pic |
|
|