Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/100 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 664 Package Name: UDRP/AF/BR/100 Sanction Cost: 1074.38  lakhs
District: Nainital Block: Betalghat Constituency: Nainital Circle:
DEA: DEA Nainital DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4142   Construction of 210m span Arch Steel Truss Bridle Bridge Between Village Amel and Village Khairali Gaon over Kosi River ( M.) (in prorgress)
Procurement:
Package No.: 664        Package Name: UDRP/AF/BR/100        Tender Date: 11-06-2020        Current Status: Agreement signed        Achieved on Date: 11-11-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/100        Contractor Name: M/S.KGL Infrastructure       
Start Date: 28-11-2020        Intended Completion Date: 28-02-2023        Original End Date:  
Total Bond Cost: 109437900.32 (1094.38 lakhs)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job87.550.00 Job0.00 Job00.00
2.Group of Pile4.00 No90.834.00 No4.00 No8.390.83
3.Foundation RHS1.00 Job22.711.00 Job1.00 Job2.0822.71
4.Foundation LHS1.00 Job22.711.00 Job1.00 Job2.0822.71
5.Steel Railing/crush barrier420.00 m0.000.00 m0.00 m00.00
6.Approach Ramp /path 300.00 m98.49300.00 m225.00 m6.7573.87
7.Protection Work1.00 Job0.000.00 Job0.00 Job00.00
8.Errection Work5.00 Job270.680.00 Job0.00 Job00.00
9.Fabrication Work5.00 job392.405.00 job5.00 job0392.40
10.Abutment Substructure RHS1.00 Job18.171.00 Job1.00 Job1.6618.17
11.Abutment Substructure LHS1.00 Job18.171.00 Job1.00 Job1.6618.17
12.Well-Abutments/Pier/Shafts/Caps4.00 job72.674.00 job4.00 job6.6472.67
Total Amount: 1094.38 29.16   711.53
Remarks: No Remarks       Work Program Made On: 26-03-2021       Updation of work program on: 20-12-2022      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.27-January-20223.00  lakhs
2.06-April-202243.56  lakhs
3.30-May-202285.36  lakhs
4.31-May-2022235.44  lakhs
5.15-June-2022175.13  lakhs
6.27-July-202240.88  lakhs
7.31-August-202254.50  lakhs
8.22-September-202254.50  lakhs
9.22-December-20225.84  lakhs
10.27-January-202346.29  lakhs
11.13-February-2023110.25  lakhs
12.27-February-2023165.37  lakhs
13.17-April-2023104.00  lakhs
Total 1124.12  lakhs
% Payment 102.72 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 1337     No. of Test Done : 1337      No. of Test Passed : 1337      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 242
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.24-06-2022Amel-Khairali BetalghatCube casting work in progress for Pier-4 first lift at Amel Betalghat Haldwani District-NainitalMadhav Singh ` ` See Pic
2.24-06-20224142Slump test for Pier-4 first lift at BR-100 Amel-Khairali Betalghat Haldwani District-NainitalMadhav Singh ` ` See Pic
3.24-06-2022Amel-Khairali BetalghatPoring of M35 grade of concrete work is in progress for Pier-4 first lift at BR-100 Amel Betalghat Haldwani District-NainitalMadhav singh ` ` See Pic
4.24-06-2022BR/100Concrete work is in progress for pier-4 of Ist lift.Sanjeev Sharma ` ` See Pic
5.23-06-2022BR/100Cube casting for Pier-3 of Ist liftSanjeev Sharma ` ` See Pic
6.23-06-2022BR/100Slump test for pier-3 of Ist liftSanjeev Sharma ` ` See Pic
7.23-06-2022BR/100Concrete work started for Ist lift of pier-3Sanjeev Sharma ` ` See Pic
8.23-06-2022BR-100Pier no-03 1st lift concreting work is in progress...Jaspal rawat ` ` See Pic
9.22-06-2022BR 100At Ramnagar yard Ground ErectionSantosh Shukla ` ` See Pic
10.22-06-2022BR 100At Ramnagar yard inspection graund ErectionSantosh Shukla ` ` See Pic
11.22-06-2022BR 100At Ramnagar yard Inspection ground ErectionSantosh Shukla ` ` See Pic
12.21-06-2022BR/100Concrete work completed for pile cap of Pier-3Sanjeev Sharma ` ` See Pic
13.21-06-2022BR/100Cube casting for pile cap concrete of pier-3Sanjeev Sharma ` ` See Pic
14.21-06-2022BR/100Slump test for pile cap concrete of pier-3Sanjeev Sharma ` ` See Pic
15.21-06-2022BR-100Pier no-03 pile cap concreting work is in progress....Jaspal rawat ` ` See Pic
16.21-06-2022BR/100Pile cap concrete work started of pier-3Sanjeev Sharma ` ` See Pic
17.21-06-2022BR/100Pile cap reinforcement & Shuttering work is in progress of pier-3Sanjeev Sharma ` ` See Pic
18.20-06-2022BR/100Dewatering work is in progress for pile cap of Pier-3Sanjeev Sharma ` ` See Pic
19.19-06-2022BR/100Pile cap concreting work completed of pier-4Sanjeev Sharma ` ` See Pic
20.19-06-2022BR/100Cube casting for pile cap of Pier-4Sanjeev Sharma ` ` See Pic