UDRP/AF/BR/100
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
664 |
Package Name: |
UDRP/AF/BR/100 |
Sanction Cost: |
1074.38 lakhs |
District: |
Nainital |
Block: |
Betalghat |
Constituency: |
Nainital |
Circle: |
|
DEA: |
DEA Nainital |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4142 Construction of 210m span Arch Steel Truss Bridle Bridge Between Village Amel and Village Khairali Gaon over Kosi River ( M.) (in prorgress) |
|
Procurement: |
Package No.: 664
Package Name: UDRP/AF/BR/100
Tender Date: 11-06-2020
Current Status: Agreement signed
Achieved on Date: 11-11-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/100
Contractor Name: M/S.KGL Infrastructure
|
Start Date: 28-11-2020
Intended Completion Date: 28-02-2023
Original End Date:
|
Total Bond Cost: 109437900.32 (1094.38 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 87.55 | 0.00 Job | 0.00 Job | 0 | 0.00 | 2. | Group of Pile | 4.00 No | 90.83 | 4.00 No | 4.00 No | 8.3 | 90.83 | 3. | Foundation RHS | 1.00 Job | 22.71 | 1.00 Job | 1.00 Job | 2.08 | 22.71 | 4. | Foundation LHS | 1.00 Job | 22.71 | 1.00 Job | 1.00 Job | 2.08 | 22.71 | 5. | Steel Railing/crush barrier | 420.00 m | 0.00 | 0.00 m | 0.00 m | 0 | 0.00 | 6. | Approach Ramp /path | 300.00 m | 98.49 | 300.00 m | 225.00 m | 6.75 | 73.87 | 7. | Protection Work | 1.00 Job | 0.00 | 0.00 Job | 0.00 Job | 0 | 0.00 | 8. | Errection Work | 5.00 Job | 270.68 | 0.00 Job | 0.00 Job | 0 | 0.00 | 9. | Fabrication Work | 5.00 job | 392.40 | 5.00 job | 5.00 job | 0 | 392.40 | 10. | Abutment Substructure RHS | 1.00 Job | 18.17 | 1.00 Job | 1.00 Job | 1.66 | 18.17 | 11. | Abutment Substructure LHS | 1.00 Job | 18.17 | 1.00 Job | 1.00 Job | 1.66 | 18.17 | 12. | Well-Abutments/Pier/Shafts/Caps | 4.00 job | 72.67 | 4.00 job | 4.00 job | 6.64 | 72.67 |
Total Amount: |
1094.38 |
|
29.16 |
711.53 |
|
Remarks:
No Remarks
Work Program Made On:
26-03-2021
Updation of work program on:
20-12-2022
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 27-January-2022 | 3.00 lakhs |
2. | 06-April-2022 | 43.56 lakhs |
3. | 30-May-2022 | 85.36 lakhs |
4. | 31-May-2022 | 235.44 lakhs |
5. | 15-June-2022 | 175.13 lakhs |
6. | 27-July-2022 | 40.88 lakhs |
7. | 31-August-2022 | 54.50 lakhs |
8. | 22-September-2022 | 54.50 lakhs |
9. | 22-December-2022 | 5.84 lakhs |
10. | 27-January-2023 | 46.29 lakhs |
11. | 13-February-2023 | 110.25 lakhs |
12. | 27-February-2023 | 165.37 lakhs |
13. | 17-April-2023 | 104.00 lakhs |
Total |
1124.12 lakhs |
% Payment |
102.72 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. |
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 242 |
No Notice issued. |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 24-06-2022 | Amel-Khairali Betalghat | Cube casting work in progress for Pier-4 first lift at Amel Betalghat Haldwani District-Nainital | Madhav Singh | ` | ` | See Pic |
2. | 24-06-2022 | 4142 | Slump test for Pier-4 first lift at BR-100 Amel-Khairali Betalghat Haldwani District-Nainital | Madhav Singh | ` | ` | See Pic |
3. | 24-06-2022 | Amel-Khairali Betalghat | Poring of M35 grade of concrete work is in progress for Pier-4 first lift at BR-100 Amel Betalghat Haldwani District-Nainital | Madhav singh | ` | ` | See Pic |
4. | 24-06-2022 | BR/100 | Concrete work is in progress for pier-4 of Ist lift. | Sanjeev Sharma | ` | ` | See Pic |
5. | 23-06-2022 | BR/100 | Cube casting for Pier-3 of Ist lift | Sanjeev Sharma | ` | ` | See Pic |
6. | 23-06-2022 | BR/100 | Slump test for pier-3 of Ist lift | Sanjeev Sharma | ` | ` | See Pic |
7. | 23-06-2022 | BR/100 | Concrete work started for Ist lift of pier-3 | Sanjeev Sharma | ` | ` | See Pic |
8. | 23-06-2022 | BR-100 | Pier no-03 1st lift concreting work is in progress... | Jaspal rawat | ` | ` | See Pic |
9. | 22-06-2022 | BR 100 | At Ramnagar yard Ground Erection | Santosh Shukla | ` | ` | See Pic |
10. | 22-06-2022 | BR 100 | At Ramnagar yard inspection graund Erection | Santosh Shukla | ` | ` | See Pic |
11. | 22-06-2022 | BR 100 | At Ramnagar yard Inspection ground Erection | Santosh Shukla | ` | ` | See Pic |
12. | 21-06-2022 | BR/100 | Concrete work completed for pile cap of Pier-3 | Sanjeev Sharma | ` | ` | See Pic |
13. | 21-06-2022 | BR/100 | Cube casting for pile cap concrete of pier-3 | Sanjeev Sharma | ` | ` | See Pic |
14. | 21-06-2022 | BR/100 | Slump test for pile cap concrete of pier-3 | Sanjeev Sharma | ` | ` | See Pic |
15. | 21-06-2022 | BR-100 | Pier no-03 pile cap concreting work is in progress.... | Jaspal rawat | ` | ` | See Pic |
16. | 21-06-2022 | BR/100 | Pile cap concrete work started of pier-3 | Sanjeev Sharma | ` | ` | See Pic |
17. | 21-06-2022 | BR/100 | Pile cap reinforcement & Shuttering work is in progress of pier-3 | Sanjeev Sharma | ` | ` | See Pic |
18. | 20-06-2022 | BR/100 | Dewatering work is in progress for pile cap of Pier-3 | Sanjeev Sharma | ` | ` | See Pic |
19. | 19-06-2022 | BR/100 | Pile cap concreting work completed of pier-4 | Sanjeev Sharma | ` | ` | See Pic |
20. | 19-06-2022 | BR/100 | Cube casting for pile cap of Pier-4 | Sanjeev Sharma | ` | ` | See Pic |
|
|