Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/98 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 663 Package Name: UDRP/AF/BR/98 Sanction Cost: 676.46  lakhs
District: Nainital Block: Betalghat Constituency: Nainital Circle:
DEA: DEA Nainital DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4140   Construction of 90m span Bridle Arch Steel Truss Bridge Between Village Talli Sethi and Village Simtaya over Kosi River in District Nainital ( M.) (in prorgress)
Procurement:
Package No.: 663        Package Name: UDRP/AF/BR/98        Tender Date: 11-06-2020        Current Status: Agreement signed        Achieved on Date: 20-10-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/98        Contractor Name: HMR Construction Pvt. Ltd.       
Start Date: 09-12-2020        Intended Completion Date: 27-03-2023        Original End Date:  31-03-2022
Total Bond Cost: 62091336.54 (620.91 lakhs)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 14715804 for 474 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Env. Man & Moni Plan38.00 Job5.5038.00 Job38.00 Job0.995.50
2.Other Allied Works & Finishing Work 1.00 Job0.341.00 Job1.00 Job0.060.34
3.Foundation RHS1.00 Job32.001.00 Job1.00 Job5.7932.00
4.Foundation LHS1.00 Job21.331.00 Job1.00 Job3.8621.33
5.Steel Railing/crush barrier182.00 m3.73182.00 m182.00 m0.683.73
6.Approach Ramp /path 102.00 m40.34102.00 m102.00 m7.2940.34
7.Protection Work1.00 Job27.381.00 Job1.00 Job4.9527.38
8.Errection Work1.00 Job98.061.00 Job1.00 Job17.7398.06
9.Fabrication Work1.00 job269.771.00 job1.00 job48.77269.77
10.Abutment Substructure RHS1.00 Job32.841.00 Job1.00 Job5.9432.84
11.Abutment Substructure LHS1.00 Job21.901.00 Job1.00 Job3.9621.90
Total Amount: 553.19 100   553.19
Remarks: No Remarks       Work Program Made On: 25-02-2021       Updation of work program on: 19-08-2023      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-March-2022348.85  lakhs
2.15-June-202221.29  lakhs
3.31-August-202210.25  lakhs
4.22-December-20220.38  lakhs
5.29-December-202211.12  lakhs
6.07-February-202365.94  lakhs
7.23-March-202358.84  lakhs
8.16-May-202364.10  lakhs
Total 580.77  lakhs
% Payment 93.54 %
Advance Amount:  195.92  lakhs        Recovered Amount:  194.88  lakhs        Balance to be Recovered  1.04  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Environment & Social Compliances(Package level):No Pending Issue
Environment & Social Compliances(Sub Project level):
Construction of 90m span Bridle Arch Steel Truss Bridge Between Village Talli Sethi and Village Simtaya over Kosi River in District Nainital(4140) water sprinkling
Detailed report of this Package
Quality
No. of Test Required : 446     No. of Test Done : 446      No. of Test Passed : 446      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 249
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.21-06-2022BR 98A 1 Abutment Shuttering Work completeSantosh Shukla ` ` See Pic
2.21-06-2022BR 98Erection work in progressSantosh Shukla ` ` See Pic
3.07-06-2022Talli shethi Betalghat NainitalA1 Abutment Cap Reinforcement Fixing work is in progressSurendra Singh Bisht ` ` See Pic
4.07-06-2022Talli shethi Betalghat NainitalA1 Abutment Cap Reinforcement Fixing work is in progressSurendra Singh Bisht ` ` See Pic
5.05-06-2022BR -98Public meeting...Jaspal rawat ` ` See Pic
6.05-06-2022BR -98Social camps , labor low , health and safety , gender training.......Jaspal rawat ` ` See Pic
7.05-06-2022BR-98Health camp'sJaspal rawat ` ` See Pic
8.05-06-2022BR-98A1(LHS) abutment back fillings compaction work is in progress......Jaspal rawat ` ` See Pic
9.05-06-2022Talli shethi Betalghat NainitalA1 Abutment back filling leveling Compaction work is in progressSurendra Singh Bisht ` ` See Pic
10.05-06-2022Talli shethi Betalghat NainitalA1 Abutment back filling level compaction work is in progressSurendra Singh ` ` See Pic
11.05-06-2022Talli shethi Betalghat NainitalA1 Abutment back filling leveling work is in progressSurendra Singh Bisht ` ` See Pic
12.05-06-2022Talli shethi Betalghat NainitalA1 Abutment Cap Reinforcement Fixing work is in progressSurendra Singh Bisht ` ` See Pic
13.05-06-2022Talli shethi Betalghat NainitalA1 Abutment Cap Reinforcement Fixing work is in progressSurendra Singh Bisht ` ` See Pic
14.05-06-2022Talli shethi Betalghat NainitalA1 Abutment Cap Reinforcement Fixing work is in progressSurendra Singh Bisht ` ` See Pic
15.04-06-2022BR-98A1(LHS) abutment back fillings compaction work is in progress....Jaspal rawat ` ` See Pic
16.01-06-2022Talli shethi Betalghat NainitalA1 Abutment 8th Lift Curing work is in progressSurendra Singh Bisht ` ` See Pic
17.01-06-2022Talli shethi Betalghat NainitalA1 Abutment Shaft And Return wall 8th Lift Curing work is in progressSurendra Singh Bisht ` ` See Pic
18.26-05-2022Talli shethi Betalghat Nainital28 days Cube testing for A1 Abutment 7th Lift achieved compressive strength of the concrete cube = 37.77N/mm2.Surendra Singh Bisht ` ` See Pic
19.26-05-2022Talli shethi Betalghat NainitalCube casting for A1 Abutment Shaft And Return wall 8th Lift Concreting workSurendra Singh Bisht ` ` See Pic
20.26-05-2022Talli shethi Betalghat NainitalCube casting for A1 Abutment Shaft And Return wall 8th Lift Concreting workSurendra Singh ` ` See Pic