UDRP/AF/BR/98
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
663 |
Package Name: |
UDRP/AF/BR/98 |
Sanction Cost: |
676.46 lakhs |
District: |
Nainital |
Block: |
Betalghat |
Constituency: |
Nainital |
Circle: |
|
DEA: |
DEA Nainital |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4140 Construction of 90m span Bridle Arch Steel Truss Bridge Between Village Talli Sethi and Village Simtaya over Kosi River in District Nainital ( M.) (in prorgress) |
|
Procurement: |
Package No.: 663
Package Name: UDRP/AF/BR/98
Tender Date: 11-06-2020
Current Status: Agreement signed
Achieved on Date: 20-10-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/98
Contractor Name: HMR Construction Pvt. Ltd.
|
Start Date: 09-12-2020
Intended Completion Date: 27-03-2023
Original End Date: 31-03-2022
|
Total Bond Cost: 62091336.54 (620.91 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 14715804 for 474 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Env. Man & Moni Plan | 38.00 Job | 5.50 | 38.00 Job | 38.00 Job | 0.99 | 5.50 | 2. | Other Allied Works & Finishing Work | 1.00 Job | 0.34 | 1.00 Job | 1.00 Job | 0.06 | 0.34 | 3. | Foundation RHS | 1.00 Job | 32.00 | 1.00 Job | 1.00 Job | 5.79 | 32.00 | 4. | Foundation LHS | 1.00 Job | 21.33 | 1.00 Job | 1.00 Job | 3.86 | 21.33 | 5. | Steel Railing/crush barrier | 182.00 m | 3.73 | 182.00 m | 182.00 m | 0.68 | 3.73 | 6. | Approach Ramp /path | 102.00 m | 40.34 | 102.00 m | 102.00 m | 7.29 | 40.34 | 7. | Protection Work | 1.00 Job | 27.38 | 1.00 Job | 1.00 Job | 4.95 | 27.38 | 8. | Errection Work | 1.00 Job | 98.06 | 1.00 Job | 1.00 Job | 17.73 | 98.06 | 9. | Fabrication Work | 1.00 job | 269.77 | 1.00 job | 1.00 job | 48.77 | 269.77 | 10. | Abutment Substructure RHS | 1.00 Job | 32.84 | 1.00 Job | 1.00 Job | 5.94 | 32.84 | 11. | Abutment Substructure LHS | 1.00 Job | 21.90 | 1.00 Job | 1.00 Job | 3.96 | 21.90 |
Total Amount: |
553.19 |
|
100 |
553.19 |
|
Remarks:
No Remarks
Work Program Made On:
25-02-2021
Updation of work program on:
19-08-2023
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-March-2022 | 348.85 lakhs |
2. | 15-June-2022 | 21.29 lakhs |
3. | 31-August-2022 | 10.25 lakhs |
4. | 22-December-2022 | 0.38 lakhs |
5. | 29-December-2022 | 11.12 lakhs |
6. | 07-February-2023 | 65.94 lakhs |
7. | 23-March-2023 | 58.84 lakhs |
8. | 16-May-2023 | 64.10 lakhs |
Total |
580.77 lakhs |
% Payment |
93.54 % |
|
Advance Amount: 195.92 lakhs
Recovered Amount: 194.88 lakhs
Balance to be Recovered 1.04 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | No Pending Issue | Environment & Social Compliances(Sub Project level): | Construction of 90m span Bridle Arch Steel Truss Bridge Between Village Talli Sethi and Village Simtaya over Kosi River in District Nainital(4140) | water sprinkling |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 249 |
No Notice issued. |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 21-06-2022 | BR 98 | A 1 Abutment Shuttering Work complete | Santosh Shukla | ` | ` | See Pic |
2. | 21-06-2022 | BR 98 | Erection work in progress | Santosh Shukla | ` | ` | See Pic |
3. | 07-06-2022 | Talli shethi Betalghat Nainital | A1 Abutment Cap Reinforcement Fixing work is in progress | Surendra Singh Bisht | ` | ` | See Pic |
4. | 07-06-2022 | Talli shethi Betalghat Nainital | A1 Abutment Cap Reinforcement Fixing work is in progress | Surendra Singh Bisht | ` | ` | See Pic |
5. | 05-06-2022 | BR -98 | Public meeting... | Jaspal rawat | ` | ` | See Pic |
6. | 05-06-2022 | BR -98 | Social camps , labor low , health and safety , gender training....... | Jaspal rawat | ` | ` | See Pic |
7. | 05-06-2022 | BR-98 | Health camp's | Jaspal rawat | ` | ` | See Pic |
8. | 05-06-2022 | BR-98 | A1(LHS) abutment back fillings compaction work is in progress...... | Jaspal rawat | ` | ` | See Pic |
9. | 05-06-2022 | Talli shethi Betalghat Nainital | A1 Abutment back filling leveling Compaction work is in progress | Surendra Singh Bisht | ` | ` | See Pic |
10. | 05-06-2022 | Talli shethi Betalghat Nainital | A1 Abutment back filling level compaction work is in progress | Surendra Singh | ` | ` | See Pic |
11. | 05-06-2022 | Talli shethi Betalghat Nainital | A1 Abutment back filling leveling work is in progress | Surendra Singh Bisht | ` | ` | See Pic |
12. | 05-06-2022 | Talli shethi Betalghat Nainital | A1 Abutment Cap Reinforcement Fixing work is in progress | Surendra Singh Bisht | ` | ` | See Pic |
13. | 05-06-2022 | Talli shethi Betalghat Nainital | A1 Abutment Cap Reinforcement Fixing work is in progress | Surendra Singh Bisht | ` | ` | See Pic |
14. | 05-06-2022 | Talli shethi Betalghat Nainital | A1 Abutment Cap Reinforcement Fixing work is in progress | Surendra Singh Bisht | ` | ` | See Pic |
15. | 04-06-2022 | BR-98 | A1(LHS) abutment back fillings compaction work is in progress.... | Jaspal rawat | ` | ` | See Pic |
16. | 01-06-2022 | Talli shethi Betalghat Nainital | A1 Abutment 8th Lift Curing work is in progress | Surendra Singh Bisht | ` | ` | See Pic |
17. | 01-06-2022 | Talli shethi Betalghat Nainital | A1 Abutment Shaft And Return wall 8th Lift Curing work is in progress | Surendra Singh Bisht | ` | ` | See Pic |
18. | 26-05-2022 | Talli shethi Betalghat Nainital | 28 days Cube testing for A1 Abutment 7th Lift achieved compressive strength of the concrete cube = 37.77N/mm2. | Surendra Singh Bisht | ` | ` | See Pic |
19. | 26-05-2022 | Talli shethi Betalghat Nainital | Cube casting for A1 Abutment Shaft And Return wall 8th Lift Concreting work | Surendra Singh Bisht | ` | ` | See Pic |
20. | 26-05-2022 | Talli shethi Betalghat Nainital | Cube casting for A1 Abutment Shaft And Return wall 8th Lift Concreting work | Surendra Singh | ` | ` | See Pic |
|
|