Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/99 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 662 Package Name: UDRP/AF/BR/99 Sanction Cost: 750.88  lakhs
District: Nainital Block: Betalghat Constituency: Nainital Circle:
DEA: DEA Nainital DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4141   Construction of 125m span Bridle Arch Steel Truss Bridge Between Village Chapad and Village Ropa over Kosi ( M.) (in prorgress)
Procurement:
Package No.: 662        Package Name: UDRP/AF/BR/99        Tender Date: 11-06-2020        Current Status: Agreement signed        Achieved on Date: 26-10-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/99        Contractor Name: M/S.KGL Infrastructure       
Start Date: 14-11-2020        Intended Completion Date: 31-03-2022       
Total Bond Cost: 66754174.35 (667.54 lakhs)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 13317423 for 399 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Env. Man & Moni Plan33.00 Job4.5733.00 Job12.00 Job0.251.66
2.Other Allied Works & Finishing Work 1.00 Job1.351.00 Job0.00 Job00.00
3.Pile Cap1.00 No8.020.00 No0.00 No00.00
4.Group of Pile1.00 No40.430.00 No0.00 No00.00
5.Foundation RHS1.00 Job14.941.00 Job1.00 Job3.1914.94
6.Foundation LHS1.00 Job16.171.00 Job1.00 Job3.1916.17
7.Steel Railing/crush barrier452.40 m10.36452.40 m0.00 m00.00
8.Approach Ramp /path 100.00 m66.36100.00 m0.00 m00.00
9.Protection Work3.00 Job42.793.00 Job0.00 Job00.00
10.Errection Work1.00 Job130.491.00 Job0.00 Job00.00
11.PCC in Foundation30.17 cum2.1330.17 cum30.17 cum0.322.13
12.Excavation in soil914.21 cum2.01914.21 cum844.01 cum0.281.86
13.Fabrication Work1.00 job259.401.00 job0.44 job21.18114.13
14.Abutment Substructure RHS1.00 Job35.131.00 Job1.00 Job4.235.13
15.Abutment Substructure LHS1.00 Job35.131.00 Job0.50 Job2.117.57
16.Fixing Bearing/Slab Casting8.00 job4.388.00 job0.00 job00.00
17.Back Wall/ Approach slab1.00 job2.701.00 job0.00 job00.00
18.Well-Abutments/Pier/Shafts/Caps1.00 job11.500.00 job0.00 job00.00
19.Wearing Coat3.75 Cum0.553.75 Cum0.00 Cum00.00
Total Amount: 688.41 34.69   203.59
Remarks: No Remarks       Work Program Made On: 20-02-2021       Updation of work program on: 25-09-2021      
Work Program Status:Work Programme workable.
Financial Progress
SNo. Date Payment
1.31-May-202159.21  lakhs
2.16-September-202130.86  lakhs
Total 90.07  lakhs
% Payment 13.49 %
Advance Amount:  92.27  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  92.27  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles, labour licence
Environment & Social Compliances(Sub Project level):
Construction of 125m span Bridle Arch Steel Truss Bridge Between Village Chapad and Village Ropa over Kosi(4141)EMP Land Owner Consent, Boot, Glove, Signs, water sprinkling, debris disposal
Detailed report of this Package
Quality
No. of Test Required : 337     No. of Test Done : 351      No. of Test Passed : 341      No. of Test Failed : 10   Test report of this package
Number of Pics Available on Web Repository: 148
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.27-11-2021BR/99 Ropa Chapad Betalghat NainitalPile work is in progress for working pile No DSanjeev Kumar Sharma ` ` See Pic
2.27-11-2021BR 99Boring work is in progress for working Pile DAshutoshunknownunknown See Pic
3.27-11-2021BR 99 Ropa ChapadPile F depth checkingRakesh kumar Gautam QS ` ` See Pic
4.27-11-2021BR 99Pile bore depth checking for working Pile FAshutoshunknownunknown See Pic
5.27-11-2021BR/99 Ropa Chapad Betalghat NainitalDepth checking of working pile.Sanjeev Kumar Sharma ` ` See Pic
6.27-11-2021BR/100 Amel Khairali Betalghat Nainital.Health camp organised.Sanjeev Kumar Sharma ` ` See Pic
7.27-11-2021BR/99 Ropa chapad Betalghat NainitalHealth camp organised.Sanjeev Kumar Sharma ` ` See Pic
8.26-11-2021BR/99 Ropa Chapad Betalghat NainitalPile boring work is in progress for working pile.Sanjeev Kumar Sharma ` ` See Pic
9.26-11-2021BR/99 Ropa Chapad Betalghat NainitalGradation for SandSanjeev Kumar Sharma ` ` See Pic
10.26-11-2021BR/99 Ropa Chapad Betalghat NainitalGradation test for 10mmSanjeev Kumar Sharma ` ` See Pic
11.26-11-2021BR/99 Ropa Chapad Betalghat NainitalGradation test for 20mmSanjeev Kumar Sharma ` ` See Pic
12.26-11-2021BR/99Weight sample for 20MMSanjeev Kumar Sharma ` ` See Pic
13.25-11-2021BR/99 Ropa Chapad Betalghat NainitalPile boring work is in progress for working Pile D&FSanjeev Kumar Sharma ` ` See Pic
14.25-11-2021BR 99Pile boring work is in progress for working Pile No.D & Pile No.FAshutoshunknownunknown See Pic
15.25-11-2021BR 99Boring work is in progress for working Pile No DAshutoshunknownunknown See Pic
16.25-11-2021BR/99 Ropa Chapad Betalghat NainitalPile boring work is in progress for working Pile D&FSanjeev Kumar Sharma ` ` See Pic
17.25-11-2021BR 99Pile Boring work is in progress for working Pile No FAshutoshunknownunknown See Pic
18.24-11-2021BR/99 Ropa Chapad Betalghat NainitalPile boring work is in progress for working pile (D&F).Sanjeev Kumar Sharma ` ` See Pic
19.22-11-2021BR 99Boring work in progress for working Pile group D&FAshutoshunknownunknown See Pic
20.22-11-2021BR 99Boring work is in progress for working Pile foundationAshutoshunknownunknown See Pic