UDRP/AF/BR/99
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
662 |
Package Name: |
UDRP/AF/BR/99 |
Sanction Cost: |
750.88 lakhs |
District: |
Nainital |
Block: |
Betalghat |
Constituency: |
Nainital |
Circle: |
|
DEA: |
DEA Nainital |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4141 Construction of 125m span Bridle Arch Steel Truss Bridge Between Village Chapad and Village Ropa over Kosi ( M.) (in prorgress) |
|
Procurement: |
Package No.: 662
Package Name: UDRP/AF/BR/99
Tender Date: 11-06-2020
Current Status: Agreement signed
Achieved on Date: 26-10-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/99
Contractor Name: M/S.KGL Infrastructure
|
Start Date: 14-11-2020
Intended Completion Date: 27-11-2022
Original End Date: 31-03-2022
|
Total Bond Cost: 66754174.35 (667.54 lakhs)
Variation Cost: -683811.80 (-6.84 lakhs) Hence Total Bond Cost is 66070362.55 (660.7 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 15787321 for 473 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Env. Man & Moni Plan | 33.00 Job | 2.82 | 33.00 Job | 33.00 Job | 0.41 | 2.82 | 2. | Other Allied Works & Finishing Work | 1.00 Job | 1.35 | 1.00 Job | 0.00 Job | 0 | 0.00 | 3. | Pile Cap | 1.00 No | 8.02 | 1.00 No | 0.00 No | 0 | 0.00 | 4. | Group of Pile | 1.00 No | 40.43 | 1.00 No | 1.00 No | 5.89 | 40.43 | 5. | Foundation RHS | 1.00 Job | 14.94 | 1.00 Job | 1.00 Job | 2.18 | 14.94 | 6. | Foundation LHS | 1.00 Job | 16.17 | 1.00 Job | 1.00 Job | 2.36 | 16.17 | 7. | Steel Railing/crush barrier | 452.40 m | 10.36 | 452.40 m | 0.00 m | 0 | 0.00 | 8. | Approach Ramp /path | 100.00 m | 66.36 | 100.00 m | 0.00 m | 0 | 0.00 | 9. | Protection Work | 3.00 Job | 42.79 | 3.00 Job | 0.00 Job | 0 | 0.00 | 10. | Errection Work | 1.00 Job | 130.49 | 1.00 Job | 0.00 Job | 0 | 0.00 | 11. | PCC in Foundation | 30.17 cum | 2.13 | 30.17 cum | 30.17 cum | 0.31 | 2.13 | 12. | Excavation in soil | 914.21 cum | 2.01 | 914.21 cum | 900.00 cum | 0.29 | 1.98 | 13. | Fabrication Work | 1.00 job | 259.40 | 1.00 job | 1.00 job | 37.78 | 259.40 | 14. | Abutment Substructure RHS | 1.00 Job | 35.13 | 1.00 Job | 1.00 Job | 5.12 | 35.13 | 15. | Abutment Substructure LHS | 1.00 Job | 35.13 | 1.00 Job | 1.00 Job | 5.12 | 35.13 | 16. | Fixing Bearing/Slab Casting | 8.00 job | 4.38 | 8.00 job | 0.00 job | 0 | 0.00 | 17. | Back Wall/ Approach slab | 1.00 job | 2.70 | 1.00 job | 0.00 job | 0 | 0.00 | 18. | Well-Abutments/Pier/Shafts/Caps | 1.00 job | 11.50 | 1.00 job | 0.00 job | 0 | 0.00 | 19. | Wearing Coat | 3.75 Cum | 0.55 | 3.75 Cum | 0.00 Cum | 0 | 0.00 |
Total Amount: |
686.66 |
|
59.44 |
408.13 |
|
Remarks:
No Remarks
Work Program Made On:
20-02-2021
Updation of work program on:
20-12-2022
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-May-2021 | 59.21 lakhs |
2. | 16-September-2021 | 30.86 lakhs |
3. | 21-January-2022 | 128.91 lakhs |
4. | 22-February-2022 | 174.97 lakhs |
5. | 31-March-2022 | 0.75 lakhs |
6. | 31-May-2022 | 72.99 lakhs |
7. | 31-August-2022 | 78.81 lakhs |
8. | 29-November-2022 | 89.33 lakhs |
9. | 22-December-2022 | 8.50 lakhs |
10. | 23-March-2023 | 26.71 lakhs |
Total |
671.04 lakhs |
% Payment |
101.56 % |
|
Advance Amount: 92.27 lakhs
Recovered Amount: 92.27 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | No Pending Issue | Environment & Social Compliances(Sub Project level): | Construction of 125m span Bridle Arch Steel Truss Bridge Between Village Chapad and Village Ropa over Kosi(4141) | EMP, Boot, Glove, Signs, water sprinkling |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 291 |
No Notice issued. |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 24-06-2022 | BR/99 | Top chord erection work is in progress of first span | Sanjeev Sharma | ` | ` | See Pic |
2. | 23-06-2022 | BR/99 | Slump test for pier 2nd lift | Sanjeev Sharma | ` | ` | See Pic |
3. | 23-06-2022 | BR/99 | Concrete work is in progress of pier 2nd lift | Sanjeev Sharma | ` | ` | See Pic |
4. | 22-06-2022 | BR/99 | Bottom chord erection work is in progress for first spam | Sanjeev Sharma | ` | ` | See Pic |
5. | 20-06-2022 | BR/99 | Bottom chord erection work is in progress | Sanjeev Sharma | ` | ` | See Pic |
6. | 19-06-2022 | BR/99 | Bottom chord erection work is in progress | Sanjeev Sharma | ` | ` | See Pic |
7. | 18-06-2022 | BR/99 | Bottom chord erection work is in progress | Sanjeev Sharma | ` | ` | See Pic |
8. | 17-06-2022 | BR/99 | Erection work is in progress | Sanjeev Sharma | ` | ` | See Pic |
9. | 16-06-2022 | BR/99 | Erection work is in progress | Sanjeev Sharma | ` | ` | See Pic |
10. | 15-06-2022 | BR/99 | Curing work is in progress of pier | Sanjeev Sharma | ` | ` | See Pic |
11. | 15-06-2022 | BR/99 | Erection work is in progress | Sanjeev Sharma | ` | ` | See Pic |
12. | 14-06-2022 | BR/99 | Erection work started of RHS Abutment | Sanjeev Sharma | ` | ` | See Pic |
13. | 13-06-2022 | BR/99 | Curing work for Pier 1st lift | Sanjeev Sharma | ` | ` | See Pic |
14. | 09-06-2022 | Ropa Betalghat Nainital | Cube casting for Pier 1st Lift Concreting work | Surendra Singh Bisht | ` | ` | See Pic |
15. | 09-06-2022 | Ropa Betalghat Nainital | Slump Test for Pier 1st Lift Concreting work | Surendra Singh Bisht | ` | ` | See Pic |
16. | 09-06-2022 | Ropa Betalghat Nainital | Pier 1st Lift Concreting work started | Surendra Singh Bisht | ` | ` | See Pic |
17. | 09-06-2022 | Ropa Betalghat Nainital | Pier 1st Lift Shuttering Checking work is in progress | Surendra Singh Bisht | ` | ` | See Pic |
18. | 08-06-2022 | BR 99 | Pier column concreting work is in progress... | Jaspal rawat | ` | ` | See Pic |
19. | 08-06-2022 | BR -99 | Pier column shuttering checking work is in progress... | Jaspal rawat | ` | ` | See Pic |
20. | 07-06-2022 | BR-99 | A1(LHS) abutment approach road (PQC) work is in progress..... | Jaspal rawat | ` | ` | See Pic |
|
|