UDRP/AF/BR/54
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
661 |
Package Name: |
UDRP/AF/BR/54 |
Sanction Cost: |
639.40 lakhs |
District: |
Nainital |
Block: |
Okhal Kanda |
Constituency: |
Bhimtal |
Circle: |
|
DEA: |
DEA Nanital |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4059 Khutani Bhawali Dhanachuli Okhalkanda Khansyu Patlot Bridge in KM-85 (42.000 M.) (in prorgress) |
|
Procurement: |
Package No.: 661
Package Name: UDRP/AF/BR/54
Tender Date: 17-07-2020
Current Status: Agreement signed
Achieved on Date: 26-10-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/54
Contractor Name: M/s Manu Dev Contractor
|
Start Date: 01-12-2020
Intended Completion Date: 22-09-2023
Original End Date: 28-02-2022
|
Total Bond Cost: 57795933.85 (577.96 lakhs)
Variation Cost: 1993061.66 (19.93 lakhs) Hence Total Bond Cost is 59788995.51 (597.89 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 18379128 for 636 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Env. Man & Moni Plan | 25.00 Job | 1.58 | 25.00 Job | 10.00 Job | 0.12 | 0.63 | 2. | Other Allied Works & Finishing Work | 1.00 Job | 20.96 | 1.00 Job | 0.25 Job | 1.02 | 5.24 | 3. | Foundation RHS | 1.00 Job | 26.18 | 1.00 Job | 1.00 Job | 5.07 | 26.18 | 4. | Foundation LHS | 1.00 Job | 45.74 | 1.00 Job | 1.00 Job | 8.86 | 45.74 | 5. | Deck Cable laying, stretching and Fixing Transoms/Deck Slab | 1.00 no | 12.49 | 1.00 no | 0.00 no | 0 | 0.00 | 6. | Steel Railing/crush barrier | 187.90 m | 4.13 | 187.90 m | 0.00 m | 0 | 0.00 | 7. | Approach Ramp /path | 132.00 m | 39.65 | 132.00 m | 30.00 m | 1.75 | 9.01 | 8. | Protection Work | 2.00 Job | 9.56 | 2.00 Job | 1.00 Job | 0.93 | 4.78 | 9. | Errection Work | 1.00 Job | 85.65 | 1.00 Job | 1.00 Job | 16.6 | 85.65 | 10. | Fabrication Work | 1.00 job | 148.86 | 1.00 job | 1.00 job | 28.85 | 148.86 | 11. | Abutment Substructure RHS | 1.00 Job | 60.62 | 1.00 Job | 1.00 Job | 11.75 | 60.62 | 12. | Abutment Substructure LHS | 1.00 Job | 60.62 | 1.00 Job | 1.00 Job | 11.75 | 60.62 |
Total Amount: |
516.04 |
|
86.69 |
447.33 |
|
Remarks:
No Remarks
Work Program Made On:
10-03-2021
Updation of work program on:
28-01-2022
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 22-July-2021 | 54.16 lakhs |
2. | 29-October-2021 | 35.12 lakhs |
3. | 02-March-2022 | 47.71 lakhs |
4. | 09-June-2022 | 49.81 lakhs |
5. | 15-June-2022 | 83.84 lakhs |
6. | 26-July-2022 | 19.08 lakhs |
7. | 22-September-2022 | 48.17 lakhs |
8. | 26-November-2022 | 32.47 lakhs |
9. | 22-December-2022 | 1.15 lakhs |
10. | 03-April-2023 | 48.88 lakhs |
11. | 01-May-2023 | 4.94 lakhs |
12. | 16-May-2023 | 21.01 lakhs |
13. | 03-June-2023 | 15.68 lakhs |
14. | 03-July-2023 | 10.84 lakhs |
15. | 13-September-2023 | 16.79 lakhs |
Total |
489.65 lakhs |
% Payment |
81.9 % |
|
Advance Amount: 73.94 lakhs
Recovered Amount: 65.72 lakhs
Balance to be Recovered 8.23 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | No Pending Issue | Environment & Social Compliances(Sub Project level): | Khutani Bhawali Dhanachuli Okhalkanda Khansyu Patlot Bridge in KM-85(4059) | EMP |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 108 |
No Notice issued. |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 23-06-2022 | Khutani-Khansyu-Patlot Road Km 85 | Bar bending & Shuttering fixing work in progress of 3rd lift A2 Abutment R.H.S | Amit kumar J.E | ` | ` | See Pic |
2. | 13-06-2022 | A 2 Abutment | Concrete Work M35 Second Lift | Santosh Shukla | ` | ` | See Pic |
3. | 13-06-2022 | A 2 Abutment | 2nd Lift cancrete work | Santosh Shukla | ` | ` | See Pic |
4. | 13-06-2022 | A 1 Abutment | M35 Concrete Work Cube Casting | Santosh Shukla | ` | ` | See Pic |
5. | 10-06-2022 | A 1 Abutment | Concrete Work M35 3 Lift | Santosh Shukla | ` | ` | See Pic |
6. | 10-06-2022 | A 1 Abutment | Concrete work M35 3Lift in progress | Santosh Shukla | ` | ` | See Pic |
7. | 10-06-2022 | A 1 Abutment | Beck filing | Santosh Shukla | ` | ` | See Pic |
8. | 10-06-2022 | A 2 Abutment | Steel work Shuttering in progress | Santosh Shukla | ` | ` | See Pic |
9. | 21-05-2022 | Construction of 42 mtr span steel truss motor bridge in km-85 khansyu-patlot motor road in nainital District.... | cube casting of M35 concrete for 1st lift (Stem with Return wall) in A2 Abutment R.H.S. side... | Gangaram Gusain | ` | ` | See Pic |
10. | 21-05-2022 | Construction of 42 mtr span steel truss motor bridge in km-85 khansyu-patlot motor bridge in nainital District.. | M35 Concrete work progress for 1st lift of Stem with Return wall in A2 Abutment.... | Gangaram Gusain | ` | ` | See Pic |
11. | 21-05-2022 | Construction of 42 mtr span steel truss motor bridge km-85 in khansyu-patlot road in nainital District. | Reinforced work and Shuttering work in progress of 1st lift in stem with return wall for A2 abutment R.h.S. Side.... | Gangaram Gusain | ` | ` | See Pic |
12. | 21-05-2022 | Construction of 42 mtr span steel truss motor bridge in km-85 khansyu-patlot Haldwani in Nainital District | Concrete Vibrating work properly in progress of 8th Lift Return wall with stem in A1 Abutment in L.H.S. Side. | Gangaram Gusain | ` | ` | See Pic |
13. | 21-05-2022 | Construction of 42 mtr span steel truss motor Bridge in km-85 khansyu-patlot motor Road in Haldwani Nainital District.. | Concrete work in progress for 8th lift of Return wall with stem in A1 Abutment L.H.S. side.... | Gangaram Gusain | ` | ` | See Pic |
14. | 21-05-2022 | Construction of 42 mtr span steel truss motor Bridge in km-85 in khansyu-patlot motor road in haldwani Nainital. | Medical checking all labour with staff at site.... | Gangaram Gusain | ` | ` | See Pic |
15. | 27-04-2022 | A 2 Site Abutment | Raft concrete work M 35 Slump Testing | Santosh Shukla | ` | ` | See Pic |
16. | 07-04-2022 | A 2 Site Abutment | Raft concrete work cube casting M 35 | Santosh Shukla | ` | ` | See Pic |
17. | 07-04-2022 | A 2 Abutment | Raft concrete work | Santosh Shukla | ` | ` | See Pic |
18. | 07-04-2022 | A 2 Abutment | Raft A2 Abutment concrete work M 35 Slump testing | Santosh Shukla | ` | ` | See Pic |
19. | 07-04-2022 | Construction of 42 mtr span steel truss motor Bridge in km-85 khansyu-patlot motor road in Nainital District. | M35 Concrete work with Proper vibrating for raft foundation in progress of A2 abutment in R.H.S. Side.... | Gangaram Gusain | ` | ` | See Pic |
20. | 24-02-2022 | Fabrication yard at Haridwar | Bridge Inspection of Fabrication yard for Structural Steel Bridge at Ritutech Sidcul Haridwar | Surendra Singh Bisht | ` | ` | See Pic |
|
|