Package Profile Report

UDRP/AF/BR/54 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 661 Package Name: UDRP/AF/BR/54 Sanction Cost: 639.40  lakhs
District: Nainital Block: Okhal Kanda Constituency: Bhimtal Circle:
DEA: DEA Nanital DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4059   Khutani Bhawali Dhanachuli Okhalkanda Khansyu Patlot Bridge in KM-85 (42.000 M.) (in prorgress)
Procurement:
Package No.: 661        Package Name: UDRP/AF/BR/54        Tender Date: 17-07-2020        Current Status: Agreement signed        Achieved on Date: 26-10-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/54        Contractor Name: M/s Manu Dev Contractor       
Start Date: 01-12-2020        Intended Completion Date: 22-09-2023        Original End Date:  28-02-2022
Total Bond Cost: 57795933.85 (577.96 lakhs)        Variation Cost: 1993061.66 (19.93 lakhs)     Hence Total Bond Cost is   59788995.51 (597.89 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 18379128 for 636 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Env. Man & Moni Plan25.00 Job1.5825.00 Job10.00 Job0.120.63
2.Other Allied Works & Finishing Work 1.00 Job20.961.00 Job0.25 Job1.025.24
3.Foundation RHS1.00 Job26.181.00 Job1.00 Job5.0726.18
4.Foundation LHS1.00 Job45.741.00 Job1.00 Job8.8645.74
5.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 1.00 no12.491.00 no0.00 no00.00
6.Steel Railing/crush barrier187.90 m4.13187.90 m0.00 m00.00
7.Approach Ramp /path 132.00 m39.65132.00 m30.00 m1.759.01
8.Protection Work2.00 Job9.562.00 Job1.00 Job0.934.78
9.Errection Work1.00 Job85.651.00 Job1.00 Job16.685.65
10.Fabrication Work1.00 job148.861.00 job1.00 job28.85148.86
11.Abutment Substructure RHS1.00 Job60.621.00 Job1.00 Job11.7560.62
12.Abutment Substructure LHS1.00 Job60.621.00 Job1.00 Job11.7560.62
Total Amount: 516.04 86.69   447.33
Remarks: No Remarks       Work Program Made On: 10-03-2021       Updation of work program on: 28-01-2022      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.22-July-202154.16  lakhs
2.29-October-202135.12  lakhs
3.02-March-202247.71  lakhs
4.09-June-202249.81  lakhs
5.15-June-202283.84  lakhs
6.26-July-202219.08  lakhs
7.22-September-202248.17  lakhs
8.26-November-202232.47  lakhs
9.22-December-20221.15  lakhs
10.03-April-202348.88  lakhs
11.01-May-20234.94  lakhs
12.16-May-202321.01  lakhs
13.03-June-202315.68  lakhs
14.03-July-202310.84  lakhs
15.13-September-202316.79  lakhs
Total 489.65  lakhs
% Payment 81.9 %
Advance Amount:  73.94  lakhs        Recovered Amount:  65.72  lakhs        Balance to be Recovered  8.23  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Environment & Social Compliances(Package level):No Pending Issue
Environment & Social Compliances(Sub Project level):
Khutani Bhawali Dhanachuli Okhalkanda Khansyu Patlot Bridge in KM-85(4059)EMP
Detailed report of this Package
Quality
No. of Test Required : 515     No. of Test Done : 559      No. of Test Passed : 524      No. of Test Failed : 35   Test report of this package
Number of Pics Available on Web Repository: 108
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-06-2022Khutani-Khansyu-Patlot Road Km 85Bar bending & Shuttering fixing work in progress of 3rd lift A2 Abutment R.H.SAmit kumar J.E ` ` See Pic
2.13-06-2022A 2 AbutmentConcrete Work M35 Second LiftSantosh Shukla ` ` See Pic
3.13-06-2022A 2 Abutment2nd Lift cancrete workSantosh Shukla ` ` See Pic
4.13-06-2022A 1 AbutmentM35 Concrete Work Cube CastingSantosh Shukla ` ` See Pic
5.10-06-2022A 1 AbutmentConcrete Work M35 3 LiftSantosh Shukla ` ` See Pic
6.10-06-2022A 1 AbutmentConcrete work M35 3Lift in progressSantosh Shukla ` ` See Pic
7.10-06-2022A 1 AbutmentBeck filingSantosh Shukla ` ` See Pic
8.10-06-2022A 2 AbutmentSteel work Shuttering in progressSantosh Shukla ` ` See Pic
9.21-05-2022Construction of 42 mtr span steel truss motor bridge in km-85 khansyu-patlot motor road in nainital District....cube casting of M35 concrete for 1st lift (Stem with Return wall) in A2 Abutment R.H.S. side...Gangaram Gusain ` ` See Pic
10.21-05-2022Construction of 42 mtr span steel truss motor bridge in km-85 khansyu-patlot motor bridge in nainital District..M35 Concrete work progress for 1st lift of Stem with Return wall in A2 Abutment....Gangaram Gusain ` ` See Pic
11.21-05-2022Construction of 42 mtr span steel truss motor bridge km-85 in khansyu-patlot road in nainital District.Reinforced work and Shuttering work in progress of 1st lift in stem with return wall for A2 abutment R.h.S. Side....Gangaram Gusain ` ` See Pic
12.21-05-2022Construction of 42 mtr span steel truss motor bridge in km-85 khansyu-patlot Haldwani in Nainital DistrictConcrete Vibrating work properly in progress of 8th Lift Return wall with stem in A1 Abutment in L.H.S. Side.Gangaram Gusain ` ` See Pic
13.21-05-2022Construction of 42 mtr span steel truss motor Bridge in km-85 khansyu-patlot motor Road in Haldwani Nainital District..Concrete work in progress for 8th lift of Return wall with stem in A1 Abutment L.H.S. side....Gangaram Gusain ` ` See Pic
14.21-05-2022Construction of 42 mtr span steel truss motor Bridge in km-85 in khansyu-patlot motor road in haldwani Nainital.Medical checking all labour with staff at site....Gangaram Gusain ` ` See Pic
15.27-04-2022A 2 Site AbutmentRaft concrete work M 35 Slump TestingSantosh Shukla ` ` See Pic
16.07-04-2022A 2 Site AbutmentRaft concrete work cube casting M 35Santosh Shukla ` ` See Pic
17.07-04-2022A 2 AbutmentRaft concrete workSantosh Shukla ` ` See Pic
18.07-04-2022A 2 AbutmentRaft A2 Abutment concrete work M 35 Slump testingSantosh Shukla ` ` See Pic
19.07-04-2022Construction of 42 mtr span steel truss motor Bridge in km-85 khansyu-patlot motor road in Nainital District.M35 Concrete work with Proper vibrating for raft foundation in progress of A2 abutment in R.H.S. Side....Gangaram Gusain ` ` See Pic
20.24-02-2022Fabrication yard at HaridwarBridge Inspection of Fabrication yard for Structural Steel Bridge at Ritutech Sidcul HaridwarSurendra Singh Bisht ` ` See Pic