UDRP/AF/BR/93
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
660 |
Package Name: |
UDRP/AF/BR/93 |
Sanction Cost: |
435.09 lakhs |
District: |
Almora |
Block: |
Sult |
Constituency: |
Salt |
Circle: |
|
DEA: |
DEA Bageshwar |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4134 Bridge on Bailkana Gadera on Pipna Manhaith Dangula MR at KM-7 (48.000 M.) (in prorgress) |
|
Procurement: |
Package No.: 660
Package Name: UDRP/AF/BR/93
Tender Date: 02-12-2019
Current Status: Agreement signed
Achieved on Date: 06-07-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/93
Contractor Name: Gaurav Builder
|
Start Date: 27-08-2020
Intended Completion Date: 13-08-2022
Original End Date: 26-11-2021
|
Total Bond Cost: 46814331.2 (468.14 lakhs)
Variation Cost: 2357712.63 (23.58 lakhs) Hence Total Bond Cost is 49172043.83 (491.72 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 11867349 for 507 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Env. Man & Moni Plan | 1.00 Job | 4.56 | 1.00 Job | 1.00 Job | 0.97 | 4.56 | 2. | Other Allied Works & Finishing Work | 1.00 Job | 5.02 | 1.00 Job | 1.00 Job | 1.07 | 5.02 | 3. | Foundation RHS | 1.00 Job | 9.26 | 1.00 Job | 1.00 Job | 1.97 | 9.26 | 4. | Foundation LHS | 1.00 Job | 10.36 | 1.00 Job | 1.00 Job | 2.21 | 10.36 | 5. | Abutment Superstructure RHS | 1.00 Job | 0.22 | 1.00 Job | 1.00 Job | 0.05 | 0.22 | 6. | Abutment Superstructure LHS | 1.00 Job | 0.22 | 1.00 Job | 1.00 Job | 0.05 | 0.22 | 7. | Fixing of chequered Plate/RCC Deck | 257.25 sqm | 20.57 | 257.25 sqm | 257.25 sqm | 4.38 | 20.57 | 8. | Steel Railing/crush barrier | 1.00 m | 6.21 | 1.00 m | 1.00 m | 1.32 | 6.21 | 9. | Approach Ramp /path | 2.00 m | 43.63 | 2.00 m | 2.00 m | 9.3 | 43.63 | 10. | Protection Work | 1.00 Job | 11.79 | 1.00 Job | 1.00 Job | 2.51 | 11.79 | 11. | Errection Work | 1.00 Job | 96.28 | 1.00 Job | 1.00 Job | 20.51 | 96.28 | 12. | Fabrication Work | 1.00 job | 222.82 | 1.00 job | 1.00 job | 47.47 | 222.82 | 13. | Abutment Substructure RHS | 1.00 Job | 19.23 | 1.00 Job | 1.00 Job | 4.1 | 19.23 | 14. | Abutment Substructure LHS | 1.00 Job | 19.23 | 1.00 Job | 1.00 Job | 4.1 | 19.23 |
Total Amount: |
469.4 |
|
100 |
469.4 |
|
Remarks:
No Remarks
Work Program Made On:
14-10-2020
Updation of work program on:
06-05-2022
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 29-December-2020 | 7.96 lakhs |
2. | 27-February-2021 | 28.46 lakhs |
3. | 04-September-2021 | 92.41 lakhs |
4. | 13-October-2021 | 52.35 lakhs |
5. | 02-November-2021 | 31.06 lakhs |
6. | 16-December-2021 | 41.25 lakhs |
7. | 14-March-2022 | 12.45 lakhs |
8. | 14-April-2022 | 89.86 lakhs |
9. | 30-April-2022 | 38.86 lakhs |
10. | 13-July-2022 | 35.65 lakhs |
11. | 17-August-2022 | 11.35 lakhs |
12. | 23-September-2022 | 20.27 lakhs |
13. | 21-October-2022 | 7.52 lakhs |
14. | 28-December-2022 | 24.92 lakhs |
Total |
494.37 lakhs |
% Payment |
100.54 % |
|
Advance Amount: 17.33 lakhs
Recovered Amount: 15.34 lakhs
Balance to be Recovered 1.99 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | No Pending Issue | Environment & Social Compliances(Sub Project level): | Bridge on Bailkana Gadera on Pipna Manhaith Dangula MR at KM-7(4134) | Land Owner Consent, Signs |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 145 |
No Notice issued. |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 23-06-2022 | Pipna Manhaith Dangula Motor road at Km-7 in distt-Almora | Bolt tightening work in progress | Roop | ` | ` | See Pic |
2. | 23-06-2022 | Pipna Manhaith Dangula Motor road at Km-7 in distt-Almora | Gabion filling | Roop | ` | ` | See Pic |
3. | 23-06-2022 | Pipna Manhaith Dangula Motor road at Km-7 in distt-Almora | Cube moulding for RCC of pedestal at RHS abutment | Roop | ` | ` | See Pic |
4. | 23-06-2022 | Pipna Manhaith Dangula Motor road at Km-7 in distt-Almora | RCC of pedestal at RHS abutment | Roop | ` | ` | See Pic |
5. | 23-06-2022 | Pipna Manhaith Dangula Motor road at Km-7 in distt-Almora | RCC of pedestal at RHS abutment | Roop | ` | ` | See Pic |
6. | 21-06-2022 | Pipna Manhaith Dangula Motor road at Km-7 in distt-Almora | LHS approach road RRM work in progress | Roop | ` | ` | See Pic |
7. | 21-06-2022 | Pipna Manhaith Dangula Motor road at Km-7 in distt-Almora | Bolt tightening work in progress | Roop | ` | ` | See Pic |
8. | 19-06-2022 | Pipna Manhaith Dangula Motor road at Km-7 in distt-Almora | LHS approach road RRM work in progres | Roop | ` | ` | See Pic |
9. | 17-06-2022 | Pipna Manhaith Dangula Motor road at Km-7 in distt-Almora | LHS approach road RRM work in progress | Roop | ` | ` | See Pic |
10. | 17-06-2022 | Pipna Manhaith Dangula Motor road at Km-7 in distt-Almora | Bolt tightening work in progress | Roop | ` | ` | See Pic |
11. | 15-06-2022 | Pipna Manhaith Dangula Motor road at Km-7 in distt-Almora | LHS approach road RRM work | Roop | ` | ` | See Pic |
12. | 15-06-2022 | Pipna Manhaith Dangula Motor road at Km-7 in distt-Almora | LHS approach road RRM work in progress | Roop | ` | ` | See Pic |
13. | 09-06-2022 | Pipna Manhaith Dangula Motor road at Km-7 in distt-Almora | Bolt tightening work in progress | Roop | ` | ` | See Pic |
14. | 09-06-2022 | Pipna Manhaith Dangula Motor road at Km-7 in distt-Almora | LHS approach road RRM work in progress | Roop | ` | ` | See Pic |
15. | 08-06-2022 | Pipna Manhaith Dangula Motor road at Km-7 in distt-Almora | Bolt tightening work in progress | Roop | ` | ` | See Pic |
16. | 08-06-2022 | Pipna Manhaith Dangula Motor road at Km-7 in distt-Almora | LHS approach road RRM work in progress | Roop | ` | ` | See Pic |
17. | 27-05-2022 | Pipna Manhaith Dangula Motor road at Km-7 in distt-Almora | Bolt tightening work in progress | Roop | ` | ` | See Pic |
18. | 17-05-2022 | Pipna Manhaith Dangula Motor road at Km-7 in distt-Almora | Bolt tightening work | Roop | ` | ` | See Pic |
19. | 12-05-2022 | Pipna Manhaith Dangula Motor road at Km-7 in distt-Almora | Bolt tightening work in progress | Roop | ` | ` | See Pic |
20. | 11-05-2022 | Pipna Manhaith Dangula Motor road at Km-7 in distt-Almora | Bolt tightening work in progress | Roop | ` | ` | See Pic |
|
|