UDRP/PWD/03/40/RD/056
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
66 |
Package Name: |
UDRP/PWD/03/40/RD/056 |
Sanction Cost: |
354.03 lakhs |
District: |
Rudraprayag |
Block: |
Ukhimath |
Constituency: |
Kedarnath |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Guptkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 2537 Pathali-Paldwari motor road (2.600 KM.) (completed) | 2 2545 Tala Sari motor road (4.000 KM.) (completed) |
|
Procurement: |
Package No.: 66
Package Name: UDRP/PWD/03/40/RD/056
Tender Date: 24-12-2014
Current Status: Agreement signed
Achieved on Date: 02-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/03/40/RD/056
Contractor Name: R. B. Group Developers & Builders
|
Start Date: 09-09-2015
Intended Completion Date: 28-02-2017
Original End Date: 08-12-2016
|
Total Bond Cost: 32989287.78 (329.89 lakhs)
Variation Cost: 1571927.14 (15.72 lakhs) Hence Total Bond Cost is 34561214.92 (345.61 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 758770 for 46 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 6.20 KM | 31.22 | 6.20 KM | 6.20 KM | 10.07 | 31.22 | 2. | R/Wall, B/ Wall Type Protection works | 1140.00 m | 68.41 | 1140.00 m | 1140.00 m | 21.58 | 68.41 | 3. | G-2 | 4.40 KM | 23.38 | 4.40 KM | 4.40 KM | 7.34 | 23.38 | 4. | G-3 | 1.60 KM | 8.50 | 1.60 KM | 1.60 KM | 2.55 | 8.50 | 5. | PC/CC i/c Prime Coat, Tack Coat | 6.20 KM | 79.14 | 6.20 KM | 6.20 KM | 26.17 | 79.14 | 6. | Cause Way | 4.00 No | 5.65 | 4.00 No | 4.00 No | 1.84 | 5.65 | 7. | Culverts/Scupper | 9.00 No | 38.87 | 9.00 No | 9.00 No | 12.52 | 38.87 | 8. | longitudinal Drain | 6100.00 m | 15.92 | 6100.00 m | 6100.00 m | 5.18 | 15.92 | 9. | Crash Barrier | 1500.00 m | 12.75 | 1500.00 m | 1500.00 m | 4.4 | 12.75 | 10. | Parapet | 414.00 No | 15.15 | 414.00 No | 414.00 No | 4.69 | 15.15 | 11. | Road Furniture | 68.00 No | 10.62 | 68.00 No | 68.00 No | 3.65 | 10.62 |
Total Amount: |
309.61 |
|
100 |
309.61 |
|
Remarks:
No Remarks
Work Program Made On:
30-10-2015
Updation of work program on:
19-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-October-2015 | 8.46 lakhs |
2. | 28-January-2016 | 20.90 lakhs |
3. | 29-February-2016 | 31.44 lakhs |
4. | 02-May-2016 | 13.06 lakhs |
5. | 18-May-2016 | 25.88 lakhs |
6. | 09-June-2016 | 46.26 lakhs |
7. | 29-June-2016 | 34.34 lakhs |
8. | 02-August-2016 | 24.88 lakhs |
9. | 14-September-2016 | 51.65 lakhs |
10. | 26-October-2016 | 33.33 lakhs |
11. | 16-February-2017 | 16.89 lakhs |
12. | 24-May-2017 | 36.71 lakhs |
Total |
343.8 lakhs |
% Payment |
99.48 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 106 |
Number of Notice(s) issued: 60 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 27-12-2016 | 4+580 | E.E. sir and A.E. sir visit | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
2. | 13-12-2016 | 1/21 | R/wall completed | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
3. | 13-12-2016 | 3+625 | Clearance or earthen boulder from road. | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
4. | 13-12-2016 | 4+200 | Slip clearnce from road surface | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
5. | 13-12-2016 | 1+150 | Earthen boulder clear from road surface | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
6. | 13-12-2016 | 1+475 | R/wall completed | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
7. | 13-12-2016 | 1+550 | Completed r/wall | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
8. | 13-12-2016 | 2+525 | Slip clearnce from road | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
9. | 13-12-2016 | 2+120 | Old r/wall damaged in rainy season constructed new r/wall | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
10. | 25-11-2016 | 0+550 | World Bank visit | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
11. | 25-11-2016 | 0+00 | World Bank visit | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
12. | 25-11-2016 | 0+00 | World Bank visit | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
13. | 23-11-2016 | 0+300 | Pc Thickness checking by world bank team | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
14. | 23-11-2016 | 0+050 | Road width cheking by world bank team | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
15. | 23-11-2016 | 0+070 | Pc Thickness checking by world bank team | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
16. | 19-11-2016 | 2+600 | Rectangular Sign board quality good. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
17. | 04-11-2016 | KM.2 CH 425 | PC WORK IS RUNNING ON PATHALI PALDWARI ROAD | Shankar Ram | EE | UDRP R&B Guptkashi | See Pic |
18. | 22-10-2016 | 1+525 | Removing undulation instructed by S.E. sir during visit | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
19. | 22-10-2016 | 1+425 | Clearance of surface before p. C. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
20. | 22-10-2016 | 1+425 | Thickness checked by S. E. Sir | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
|
|