Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/03/40/RD/056 Agreement signed
Project: UDRP-RB Package No.: 66 Package Name: UDRP/PWD/03/40/RD/056 Sanction Cost: 354.03  lakhs
District: Rudraprayag Block: Ukhimath Constituency: Kedarnath Circle: Rudraprayag WB Circle
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 2
Subproject in this package
1  2537   Pathali-Paldwari motor road (2.600 KM.) (completed)
2  2545   Tala Sari motor road (4.000 KM.) (completed)
Procurement:
Package No.: 66        Package Name: UDRP/PWD/03/40/RD/056        Tender Date: 24-12-2014        Current Status: Agreement signed        Achieved on Date: 02-09-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/40/RD/056        Contractor Name: R. B. Group Developers & Builders       
Start Date: 09-09-2015        Intended Completion Date: 28-02-2017        Original End Date:  08-12-2016
Total Bond Cost: 32989287.78 (329.89 lakhs)        Variation Cost: 1571927.14 (15.72 lakhs)     Hence Total Bond Cost is   34561214.92 (345.61 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 758770 for 46 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence6.20 KM31.226.20 KM6.20 KM10.0731.22
2.R/Wall, B/ Wall Type Protection works1140.00 m68.411140.00 m1140.00 m21.5868.41
3.G-24.40 KM23.384.40 KM4.40 KM7.3423.38
4.G-31.60 KM8.501.60 KM1.60 KM2.558.50
5.PC/CC i/c Prime Coat, Tack Coat6.20 KM79.146.20 KM6.20 KM26.1779.14
6.Cause Way4.00 No5.654.00 No4.00 No1.845.65
7.Culverts/Scupper 9.00 No38.879.00 No9.00 No12.5238.87
8.longitudinal Drain6100.00 m15.926100.00 m6100.00 m5.1815.92
9.Crash Barrier1500.00 m12.751500.00 m1500.00 m4.412.75
10.Parapet414.00 No15.15414.00 No414.00 No4.6915.15
11.Road Furniture68.00 No10.6268.00 No68.00 No3.6510.62
Total Amount: 309.61 100   309.61
Remarks: No Remarks       Work Program Made On: 30-10-2015       Updation of work program on: 19-05-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-October-20158.46  lakhs
2.28-January-201620.90  lakhs
3.29-February-201631.44  lakhs
4.02-May-201613.06  lakhs
5.18-May-201625.88  lakhs
6.09-June-201646.26  lakhs
7.29-June-201634.34  lakhs
8.02-August-201624.88  lakhs
9.14-September-201651.65  lakhs
10.26-October-201633.33  lakhs
11.16-February-201716.89  lakhs
12.24-May-201736.71  lakhs
Total 343.8  lakhs
% Payment 99.48 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 309     No. of Test Done : 324      No. of Test Passed : 312      No. of Test Failed : 12   Test report of this package
Number of Pics Available on Web Repository: 106
Number of Notice(s) issued: 60

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.27-12-20164+580E.E. sir and A.E. sir visitAnurag DevJEUDRP R&B Guptkashi See Pic
2.13-12-20161/21R/wall completedAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
3.13-12-20163+625Clearance or earthen boulder from road.Anurag Rawat AEAEUDRP R&B Guptkashi See Pic
4.13-12-20164+200Slip clearnce from road surfaceAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
5.13-12-20161+150Earthen boulder clear from road surfaceAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
6.13-12-20161+475R/wall completedAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
7.13-12-20161+550Completed r/wallAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
8.13-12-20162+525Slip clearnce from roadAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
9.13-12-20162+120Old r/wall damaged in rainy season constructed new r/wallAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
10.25-11-20160+550World Bank visitAnurag DevJEUDRP R&B Guptkashi See Pic
11.25-11-20160+00World Bank visitAnurag DevJEUDRP R&B Guptkashi See Pic
12.25-11-20160+00World Bank visitAnurag DevJEUDRP R&B Guptkashi See Pic
13.23-11-20160+300Pc Thickness checking by world bank teamAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
14.23-11-20160+050Road width cheking by world bank teamAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
15.23-11-20160+070Pc Thickness checking by world bank teamAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
16.19-11-20162+600Rectangular Sign board quality good.Anurag DevJEUDRP R&B Guptkashi See Pic
17.04-11-2016KM.2 CH 425PC WORK IS RUNNING ON PATHALI PALDWARI ROADShankar RamEEUDRP R&B Guptkashi See Pic
18.22-10-20161+525Removing undulation instructed by S.E. sir during visitAnurag DevJEUDRP R&B Guptkashi See Pic
19.22-10-20161+425Clearance of surface before p. C.Anurag DevJEUDRP R&B Guptkashi See Pic
20.22-10-20161+425Thickness checked by S. E. SirAnurag DevJEUDRP R&B Guptkashi See Pic