Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/92 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 659 Package Name: UDRP/AF/BR/92 Sanction Cost: 830.16  lakhs
District: Almora Block: Sult Constituency: Salt Circle:
DEA: DEA Bageshwar DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4133   Bridge over Ramganga River on Gagas Udee Mahadev to Selapani Bhikiyasain Marchula MR at KM-37 (84.000 M.) (in prorgress)
Procurement:
Package No.: 659        Package Name: UDRP/AF/BR/92        Tender Date: 02-12-2019        Current Status: Agreement signed        Achieved on Date: 10-06-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/92        Contractor Name: Gaurav Builder       
Start Date: 02-10-2020        Intended Completion Date: 12-06-2023        Original End Date:  01-04-2022
Total Bond Cost: 83269832.13 (832.7 lakhs)        Variation Cost: 3638853.62 (36.39 lakhs)     Hence Total Bond Cost is   86908685.75 (869.09 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 40760665 for 979 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Env. Man & Moni Plan1.00 Job5.511.00 Job1.00 Job0.665.51
2.Other Allied Works & Finishing Work 1.00 Job4.911.00 Job1.00 Job0.594.91
3.Foundation RHS1.00 Job38.181.00 Job1.00 Job4.5938.18
4.Foundation LHS1.00 Job38.181.00 Job1.00 Job4.5938.18
5.Abutment Superstructure RHS1.00 Job0.121.00 Job1.00 Job0.010.12
6.Abutment Superstructure LHS1.00 Job0.121.00 Job1.00 Job0.010.12
7.Fixing of chequered Plate/RCC Deck462.00 sqm50.93462.00 sqm462.00 sqm6.1250.93
8.Steel Railing/crush barrier135.00 m9.77135.00 m135.00 m1.179.77
9.Approach Ramp /path 300.00 m53.64300.00 m300.00 m6.4453.64
10.Protection Work1.00 Job16.071.00 Job1.00 Job1.9316.07
11.Errection Work1.00 Job141.281.00 Job1.00 Job16.97141.28
12.Fabrication Work1.00 job305.681.00 job1.00 job36.71305.68
13.Abutment Substructure RHS1.00 Job84.161.00 Job1.00 Job10.1184.16
14.Abutment Substructure LHS1.00 Job84.161.00 Job1.00 Job10.1184.16
Total Amount: 832.71 100   832.71
Remarks: No Remarks       Work Program Made On: 16-10-2020       Updation of work program on: 24-05-2022      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-March-202111.36  lakhs
2.30-October-202156.20  lakhs
3.16-February-202275.31  lakhs
4.31-May-202217.55  lakhs
5.21-October-202230.16  lakhs
6.27-December-202218.11  lakhs
7.28-January-2023101.29  lakhs
8.31-January-202322.85  lakhs
9.04-March-202317.08  lakhs
10.13-March-202324.83  lakhs
Total 374.74  lakhs
% Payment 43.12 %
Advance Amount:  205.21  lakhs        Recovered Amount:  53.69  lakhs        Balance to be Recovered  151.52  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Environment & Social Compliances(Package level):No Pending Issue
Environment & Social Compliances(Sub Project level):
Bridge over Ramganga River on Gagas Udee Mahadev to Selapani Bhikiyasain Marchula MR at KM-37(4133)EMP Land Owner Consent
Detailed report of this Package
Quality
No. of Test Required : 199     No. of Test Done : 199      No. of Test Passed : 199      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 56
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.03-06-2022A1Caution tapeAzhar (J.E) ` ` See Pic
2.03-06-2022A1Caution tapeAzhar ` ` See Pic
3.03-06-2022A1BR-92Azhar ` ` See Pic
4.03-06-2022A1BR-92Azhar ` ` See Pic
5.03-06-2022A1Reinforcement steelAzhar ` ` See Pic
6.27-05-2022BR92Abutment LHS and RHSRajesh sharma ` ` See Pic
7.26-05-2022A2Reinforcement workAzhar ` ` See Pic
8.26-05-2022A2A2Azhar ` ` See Pic
9.26-05-2022A1Reinforcement steelAzhar ` ` See Pic
10.26-05-2022Km 37Abutment A-2Govind kumar ` ` See Pic
11.09-05-2022Bridge BR92Concrete pouring in progress for 2nd lift of RHS Abutment.Rajesh sharma ` ` See Pic
12.09-05-2022BR-92 (84m span)Pouring of 2nd lift of abutment A-2Govind kumar ` ` See Pic
13.31-01-2022BR-92A-2Govind kumar ` ` See Pic
14.31-01-2022BR-92A-2 1st liftGovind kumar ` ` See Pic
15.17-12-2021Bridge BR92LHS abutmentRajesh sharma ` ` See Pic
16.17-12-2021Bridge BR92RHS Abutment raft preparation in progress.Rajesh sharma ` ` See Pic
17.17-12-2021Bridge BR92Information BoardRajesh sharma ` ` See Pic
18.17-12-2021bridge package BR92Information boardRajesh sharma ` ` See Pic
19.27-11-2021Km -37 BR-92Curing of abutment A-1 's 1st liftGovind kumar ss ` ` See Pic
20.27-11-2021Km 36 BR 92Abutment A-1Govind kumar ss ` ` See Pic