UDRP/AF/BR/91
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
658 |
Package Name: |
UDRP/AF/BR/91 |
Sanction Cost: |
254.59 lakhs |
District: |
Uttarkashi |
Block: |
Naugaon |
Constituency: |
Purola |
Circle: |
|
DEA: |
DEA Uttarkashi |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4132 Bridge near Km-2 of Kund Kotla Motor Road at Kund Khad (50.000 M.) (completed) |
|
Procurement: |
Package No.: 658
Package Name: UDRP/AF/BR/91
Tender Date: 02-12-2019
Current Status: Agreement signed
Achieved on Date: 24-06-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/91
Contractor Name: M/s Harpal singh Kishore singh
|
Start Date: 04-08-2020
Intended Completion Date: 19-01-2022
Original End Date: 03-11-2021
|
Total Bond Cost: 27047423.19 (270.47 lakhs)
Variation Cost: -46691.83 (-0.47 lakhs) Hence Total Bond Cost is 27000731.36 (270.01 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 6126372 for 453 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 33.98 | 1.00 Job | 1.00 Job | 14.07 | 33.98 | 2. | Foundation RHS | 1.00 Job | 4.74 | 1.00 Job | 1.00 Job | 1.96 | 4.74 | 3. | Foundation LHS | 1.00 Job | 4.74 | 1.00 Job | 1.00 Job | 1.96 | 4.74 | 4. | Abutment Superstructure RHS | 1.00 Job | 7.41 | 1.00 Job | 1.00 Job | 3.07 | 7.41 | 5. | Abutment Superstructure LHS | 1.00 Job | 7.41 | 1.00 Job | 1.00 Job | 3.07 | 7.41 | 6. | Fixing of chequered Plate/RCC Deck | 1.00 sqm | 7.42 | 1.00 sqm | 1.00 sqm | 3.07 | 7.42 | 7. | Steel Railing/crush barrier | 1.00 m | 15.65 | 1.00 m | 1.00 m | 6.48 | 15.65 | 8. | Approach Ramp /path | 1.00 m | 23.05 | 1.00 m | 1.00 m | 9.54 | 23.05 | 9. | Protection Work | 1.00 Job | 32.95 | 1.00 Job | 1.00 Job | 13.64 | 32.95 | 10. | Errection Work | 1.00 Job | 41.51 | 1.00 Job | 1.00 Job | 17.19 | 41.51 | 11. | Fabrication Work | 1.00 job | 61.27 | 1.00 job | 1.00 job | 25.37 | 61.27 | 12. | Fixing Bearing/Slab Casting | 4.00 job | 1.37 | 4.00 job | 4.00 job | 0.57 | 1.37 |
Total Amount: |
241.5 |
|
100 |
241.5 |
|
Remarks:
No Remarks
Work Program Made On:
08-10-2020
Updation of work program on:
17-01-2022
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 04-February-2021 | 11.45 lakhs |
2. | 19-March-2021 | 17.38 lakhs |
3. | 10-June-2021 | 15.45 lakhs |
4. | 22-July-2021 | 57.86 lakhs |
5. | 31-July-2021 | 14.46 lakhs |
6. | 30-September-2021 | 22.10 lakhs |
7. | 26-November-2021 | 34.90 lakhs |
8. | 05-February-2022 | 51.06 lakhs |
9. | 31-March-2022 | 12.75 lakhs |
10. | 31-May-2022 | 14.66 lakhs |
Total |
252.07 lakhs |
% Payment |
93.36 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 203 |
No Notice issued. |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 27-12-2021 | BR 91 | Abutment A 1 side Approach road (VIJAY SHEKHAR NAUDIYAL) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
2. | 27-12-2021 | BR 91 | DLC For approach road abutment A2 side has been completed (VIJAY SHEKHAR NAUDIYAL) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
3. | 01-12-2021 | BR91 | site visit AE, AAE and RE Sir for Erection of structural steel work in Progress ( VIJAY SHEKHAR NAUDIYAL) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
4. | 23-11-2021 | BR 91 | Plum concrete &RR 1:5 work in progress abutment A1 side approach road protection (VIJAY SHEKHAR NAUDIYAL) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
5. | 23-11-2021 | BR91 | Erection of structural steel work in progress (VIJAY SHEKHAR NAUDIYAL) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
6. | 16-11-2021 | BR 91 Kud kotla | eraction work is on Progress | Manoj sain QC | ` | ` | See Pic |
7. | 16-11-2021 | Construction of 50 m span steel truss bridle bridge near km 2.kund Kotla motor road at kund khad BR 91 | Erection of structural steel work in progress (Vijay Shekhar Naudiyal) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
8. | 16-11-2021 | Construction of 50 m span steel truss bridle bridge near km 2.kund Kotla motor road at kund khad BR 91 | Erection of structural steel work in progress ( Vijay Shekhar Naudiyal) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
9. | 16-11-2021 | Construction of 50 m span steel truss bridle bridge near km 2.kund Kotla motor road at kund khad BR 91 | Erection of structural steel work in progress (Vijay Shekhar Naudiyal) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
10. | 14-11-2021 | Bingsi chani Bridge | Ericsson work is on progress of bottom chord | AE Pawan Kumar | unknown | unknown | See Pic |
11. | 13-11-2021 | KUND Kotla km.02 | Erection work is progress at BR91 | Sandeep singh | ` | ` | See Pic |
12. | 10-11-2021 | Construction of 50 m span steel truss bridle bridge near km 2.kund Kotla motor road at kund khad BR 91 | Erection of structural steel work in progress (Vijay Shekhar Naudiyal) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
13. | 10-11-2021 | Construction of 50 m span steel truss bridle bridge near km 2.kund Kotla motor road at kund khad BR 91 | Erection of structural steel work in progress (Vijay Shekhar Naudiyal) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
14. | 21-10-2021 | A1 abutment | Erection work in progress | AAE CL Bharti | ` | ` | See Pic |
15. | 21-10-2021 | Construction of 50 m span steel truss bridle bridge near km 2.kund Kotla motor road at kund khad BR 91 | Erection for structural steel work in progress (Vijay Shekhar Naudiyal ) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
16. | 21-10-2021 | Construction of 50 m span steel truss bridle bridge near km 2.kund Kotla motor road at kund khad BR 91 | Protection work for approach road RR 1:5 work in progress abutment A2 side (Vijay Shekhar Naudiyal) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
17. | 17-10-2021 | Construction of 50m span steel truss bridle bridge near km 2.kund Kotla motor road at kund khad BR91 | Ground Erection of structural steel at site work in progress (Vijay Shekhar Naudiyal) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
18. | 06-10-2021 | Construction of 50 m span steel truss bridle bridge near km 2.kund Kotla motor road at kund khad BR 91 | Site visit construction of RR 1:5 work in progress abutment A1 & A2 for approach (Vijay Shekhar Naudiyal) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
19. | 09-09-2021 | Construction of 50 m span steel truss bridle bridge near km 2.kund Kotla motor road at kund khad BR 91 | Laying and placing Gabion boxes abutment A1 side is in progress ( Vijay Shekhar Naudiyal) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
20. | 09-09-2021 | Construction of 50 m span steel truss bridle bridge near km 2.kund Kotla motor road at kund khad BR 91 | Labour Training camp on labour Law and labour safety (Vijay Shekhar Naudiyal ) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
|
|