Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/90 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 657 Package Name: UDRP/AF/BR/90 Sanction Cost: 207.75  lakhs
District: Uttarkashi Block: Dunda Constituency: Gangotri Circle:
DEA: DEA Uttarkashi DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4131   Bridge over Jalkur River on Bagi Gaun Gajna Bridle Road (42.000 M.) (in prorgress)
Procurement:
Package No.: 657        Package Name: UDRP/AF/BR/90        Tender Date: 02-12-2019        Current Status: Agreement signed        Achieved on Date: 24-06-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/90        Contractor Name: M/s Harpal singh Kishore singh       
Start Date: 04-08-2020        Intended Completion Date: 03-11-2021       
Total Bond Cost: 20812945.6 (208.13 lakhs)        Variation Cost: -98047.08 (-0.98 lakhs)     Hence Total Bond Cost is   20714898.52 (207.15 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 4797166 for 461 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job4.431.00 Job0.00 Job00.00
2.Foundation RHS1.00 Job27.031.00 Job1.00 Job5.0227.03
3.Foundation LHS1.00 Job27.031.00 Job1.00 Job5.0227.03
4.Abutment Superstructure RHS1.00 Job11.271.00 Job0.85 Job1.789.58
5.Abutment Superstructure LHS1.00 Job11.271.00 Job1.00 Job2.0911.27
6.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 1.00 no1.361.00 no0.00 no00.00
7.Fixing of chequered Plate/RCC Deck1.00 sqm1.361.00 sqm0.00 sqm00.00
8.Approach Ramp /path 1.00 m17.521.00 m0.00 m00.00
9.Protection Work1.00 Job14.411.00 Job0.00 Job00.00
10.Errection Work1.00 Job12.911.00 Job0.00 Job00.00
11.Fabrication Work1.00 job45.081.00 job0.00 job00.00
12.Fixing Bearing/Slab Casting1.00 job12.221.00 job0.00 job00.00
Total Amount: 185.89 13.9   74.91
Remarks: No Remarks       Work Program Made On: 24-09-2020      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.30-March-202125.98  lakhs
2.03-April-202118.01  lakhs
3.10-June-202118.17  lakhs
4.28-June-20217.77  lakhs
5.22-September-20214.65  lakhs
6.30-September-202137.04  lakhs
7.02-November-202112.46  lakhs
Total 124.08  lakhs
% Payment 59.9 %
Advance Amount:  16.08  lakhs        Recovered Amount:  16.08  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles
Environment & Social Compliances(Sub Project level):
Bridge over Jalkur River on Bagi Gaun Gajna Bridle Road(4131)No Pending Issue
Detailed report of this Package
Quality
No. of Test Required : 316     No. of Test Done : 398      No. of Test Passed : 388      No. of Test Failed : 10   Test report of this package
Number of Pics Available on Web Repository: 73
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.13-11-2021Bagigaon km1Approach road progress A1 side bagigaon gajna bridle bridge BR/90Deepak ` ` See Pic
2.21-09-2021Baghi Gajna BridgeAbutment L.H.S side Top Cap Casting worki is in Progress at baghi Gajna Bridge District UttarkashiYogesh Dobhal ` ` See Pic
3.11-09-2021Bagigaon km1Abutment A1 side Cap casting Bagigaon gajna bridle bridge BR/90Deepak saini ` ` See Pic
4.04-09-2021Baaghi bridge ground erection at Fabrication yard situated at meerutGround erection of baaghi bridge is in progress at Fabrication yard situated at meerut.Abhishek tiwari ` ` See Pic
5.04-09-2021Fabrication yard situated at meerutGround erection of baaghi bridge is in progress at Fabrication yard situated at meerut.Abhishek tiwari ` ` See Pic
6.28-08-2021Km1 bagigaon gajna bridle bridgeAbutment A1 side 6th lift reinforcement checking Bagigaon gajna bridle bridge BR/90Deepak saini ` ` See Pic
7.18-08-2021Bagigaon gajna bridle bridge BR/90M/35 concrete casting for Abutment A2 side 6th liftDeepak Saini ` ` See Pic
8.17-07-2021Bagi/BR/90A2,protection work layout work in progress.Niraj pathakunknownunknown See Pic
9.07-07-2021Bagigaon Gajna Bridle BridgeT.S. survey for Abutment CapAjay Singh Rana ` ` See Pic
10.05-07-2021Bagi BridgeT.s survey is in progress at 42 M span steel Truss Bridge Bagi Gajna Bridge Distt UttarkashiYogesh Dobhalunknownunknown See Pic
11.07-06-2021Bagi BridgeAbutment R.H.S Side Protection work In progress at 42 M Span Bagi Gajna Bridge Dist UttarkashiYogesh Dobhalunknownunknown See Pic
12.07-06-2021Bagi BridgeAbutment R.H.S side Vth Lift Shutting Work In Progress At Bagi Gajna BridgeYogesh Dobhalunknownunknown See Pic
13.07-06-2021Abutment A1Shuttering of 5th lift of abutment A1 Is in progress at baghi bridle bridge.Abhishek tiwari ` ` See Pic
14.07-06-2021Abutment A1HP stone filling behind the abutment A1 is in progress at baghi bridge.Abhishek tiwari ` ` See Pic
15.07-06-2021Abutment A2Protection work of gabions is in progress for abutment A2Abhishek tiwari ` ` See Pic
16.07-06-2021Abutment A1Shuttering of 5th lift of abutment A1 is in progress at baghi bridge in district Uttarkashi.Abhishek tiwari ` ` See Pic
17.27-04-2021Km10Earthwork in excavation for Protection work Abutment R.H.S SideYogesh Dobhalunknownunknown See Pic
18.26-03-2021Baaghi bridgeAbutment A2 completed upto 4th lift.Abhishek tiwari ` ` See Pic
19.26-03-2021Baaghi bridgeShuttering of 5th lift is in progress at baghi bridge in district Uttarkashi.Abhishek tiwari ` ` See Pic
20.26-03-2021Baaghi bridge abutment A1Abutment A1 completed upto 5th lift.Abhishek tiwari ` ` See Pic