Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/89 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 656 Package Name: UDRP/AF/BR/89 Sanction Cost: 167.13  lakhs
District: Uttarkashi Block: Bhatwari Constituency: Gangotri Circle:
DEA: DEA Uttarkashi DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4130   Bridge over Jamak Gadera on Jamak Tala Tok Bridle Road (36.000 M.) (completed)
Procurement:
Package No.: 656        Package Name: UDRP/AF/BR/89        Tender Date: 02-12-2019        Current Status: Agreement signed        Achieved on Date: 30-05-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/89        Contractor Name: Kailash Hillways Engineering Associates       
Start Date: 01-07-2020        Intended Completion Date: 15-03-2022        Original End Date:  30-09-2021
Total Bond Cost: 15736964.06 (157.37 lakhs)        Variation Cost: -733651.94 (-7.34 lakhs)     Hence Total Bond Cost is   15003312.12 (150.03 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 3965472 for 504 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Foundation RHS1.00 Job0.561.00 Job1.00 Job0.40.56
2.Foundation LHS1.00 Job0.561.00 Job1.00 Job0.40.56
3.Abutment Superstructure RHS1.00 Job9.721.00 Job1.00 Job6.949.72
4.Abutment Superstructure LHS1.00 Job9.721.00 Job1.00 Job6.949.72
5.Steel Railing/crush barrier74.40 m1.0974.40 m74.40 m0.781.09
6.Approach Ramp /path 4232.00 m29.714232.00 m4232.00 m21.2129.71
7.Protection Work1.00 Job10.511.00 Job1.00 Job7.510.51
8.Errection Work1.00 Job22.061.00 Job1.00 Job15.7522.06
9.Gabion work240.00 m6.34240.00 m240.00 m4.526.34
10.Fabrication Work44.26 job42.1444.26 job44.26 job30.0842.14
11.Fixing Bearing/Slab Casting1.00 job4.001.00 job1.00 job2.864.00
12.Back Wall/ Approach slab1.00 job3.681.00 job1.00 job2.633.68
Total Amount: 140.09 100   140.09
Remarks: No Remarks       Work Program Made On: 15-07-2020       Updation of work program on: 24-05-2022      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-March-202148.02  lakhs
2.30-September-202125.15  lakhs
3.24-February-202251.57  lakhs
4.31-March-20227.64  lakhs
5.31-May-202217.66  lakhs
Total 150.04  lakhs
% Payment 100 %
Advance Amount:  8.91  lakhs        Recovered Amount:  8.91  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 257     No. of Test Done : 329      No. of Test Passed : 323      No. of Test Failed : 6   Test report of this package
Number of Pics Available on Web Repository: 89
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.27-01-2022Jamak Talla bridgePainting work is on progressAE Pawan Kumarunknownunknown See Pic
2.12-08-2021Coarse Aggregate sampling in progress.Abutment A1 cap level casting at jamak talla tok BridgeBipin Nautiyalunknownunknown See Pic
3.11-08-2021BR/89A1LHS,cap concrete slump test on progress. Concrete grade M35.Niraj pathakunknownunknown See Pic
4.11-08-2021BR/89A1LHS,cap concrete sampling done,concrete grade M35.Niraj pathakunknownunknown See Pic
5.11-08-2021BR/89A1LHS,cap concrete sampling work on progress, concrete grade M35.Niraj pathakunknownunknown See Pic
6.11-08-2021BR/89A1LHS,cap concrete slump test on progress. Concrete grade M35.Niraj pathakunknownunknown See Pic
7.11-08-2021BR/89A1 LHS,cap concreting work in progress. Concrete grade M35.Niraj pathakunknownunknown See Pic
8.11-08-2021BR/89Coarse aggregate gradation test on progress.Niraj pathakunknownunknown See Pic
9.11-08-2021BR/89Coarse aggregate gradation test on progress.Niraj pathakunknownunknown See Pic
10.24-07-2021Jamak Talla Tok Bridge Abutment A2 Cap casting in progress.Abutment A2 Cap casting in Progress.Bipin Nautiyalunknownunknown See Pic
11.23-07-2021Abutment A2 cap level casting in progress at jamak talla tok BridgeAbutment A2 side cap level casting in ProgressBipin Nautiyalunknownunknown See Pic
12.09-07-2021Jamak BridgeCheck vertical load of beringAE Pawan Kumarunknownunknown See Pic
13.09-07-2021Jamak BridgeCheck load test according to IRC part 83AE Pawan Kumarunknownunknown See Pic
14.09-07-2021Jamak BridgeChecking bottom plate dimensions of bearingAE Pawan Kumarunknownunknown See Pic
15.09-07-2021Jamak BridgeCheck thickness of top plate of bearingAE Pawan Kumarunknownunknown See Pic
16.09-07-2021Jamak BridgeCheck dimension of Bottom plate of bearingAE Pawan Kumarunknownunknown See Pic
17.09-07-2021Jamak bridgeDimensions check of top plate outer face of bearingAE Pawan Kumarunknownunknown See Pic
18.09-07-2021Jamak talla BridgeCheck dimension of inner face of bearingAE Pawan Kumarunknownunknown See Pic
19.09-07-2021Jamak tallla bridgeDimensions check of top plate of bearingAE Pawan Kumarunknownunknown See Pic
20.03-07-2021Center line marking at BR 89BR 89 Abutment Cap top level marking and center line markingBipin Nautiyalunknownunknown See Pic