                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/58 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 655 Package Name: UDRP/AF/BR/58 Sanction Cost: 929.72  lakhs
District: Uttarkashi Block: Mori Constituency: Purola Circle:
DEA: DEA Uttarkashi DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4078   Bridge at Tulka Sirga Kunasa Badasu River (90.000 M.) (in prorgress)
Procurement:
Package No.: 655        Package Name: UDRP/AF/BR/58        Tender Date: 05-09-2020        Current Status: Agreement signed        Achieved on Date: 23-12-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/58        Contractor Name: Kailash Hillways Engineering Associates       
Start Date: 08-01-2021        Intended Completion Date: 17-05-2023        Original End Date:  31-03-2022
Total Bond Cost: 89909594.59 (899.1 lakhs)        Variation Cost: 8360183.91 (83.6 lakhs)     Hence Total Bond Cost is   98269778.5 (982.7 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 1753245 for 39 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job2.001.00 Job0.50 Job0.121.00
2.Foundation RHS1.00 Job14.801.00 Job0.85 Job1.5712.58
3.Foundation LHS1.00 Job15.601.00 Job1.00 Job1.9415.60
4.Abutment Superstructure RHS1.00 Job101.401.00 Job0.00 Job00.00
5.Abutment Superstructure LHS1.00 Job160.801.00 Job0.50 Job10.0280.40
6.Anchor Block Main Cable Reinforcement (3-4 Times) 1.00 job165.921.00 job0.70 job14.47116.14
7.Anchor Block for Wind Cable: Reinforcement, Lewis 1.00 job71.161.00 job0.00 job00.00
8.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 2.00 no18.342.00 no0.00 no00.00
9.Fixing of Saddle pulley along with Rib plate and 4.00 no12.754.00 no0.00 no00.00
10.Fixing Suspenders to Main cable with clamps and Ha114.00 no8.04114.00 no0.00 no00.00
11.Stretching Wind Guy cable, Fixing wind Ties with 1528.00 m28.561528.00 m0.00 m00.00
12.Fixing longitudinal Stringers/girders270.00 m10.25270.00 m0.00 m00.00
13.Fixing of chequered Plate/RCC Deck170.00 sqm6.72170.00 sqm0.00 sqm00.00
14.Steel Railing/crush barrier180.00 m0.20180.00 m0.00 m00.00
15.Approach Ramp /path 100.00 m32.58100.00 m30.00 m1.229.77
16.Protection Work1.00 Job10.301.00 Job0.55 Job0.715.66
17.Errection Work54.20 Job25.0654.20 Job0.00 Job00.00
18.Gabion work960.00 m27.60960.00 m400.00 m1.4311.50
19.PCC in Foundation88.70 cum9.2288.70 cum50.93 cum0.665.29
20.Excavation in soil5732.40 cum9.805732.40 cum5732.40 cum1.229.80
21.Fabrication Work54.20 job71.6754.20 job54.20 job8.9371.67
Total Amount: 802.77 42.28   339.41
Remarks: No Remarks       Work Program Made On: 20-02-2021       Updation of work program on: 17-05-2022      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.03-September-202177.14  lakhs
2.26-November-2021155.99  lakhs
3.05-February-202269.12  lakhs
4.31-March-202299.42  lakhs
5.10-May-202251.40  lakhs
6.15-June-202245.77  lakhs
7.06-July-202277.48  lakhs
8.20-October-202230.68  lakhs
9.24-November-202246.76  lakhs
10.29-December-202254.12  lakhs
11.14-February-202373.67  lakhs
12.25-March-202361.86  lakhs
13.08-May-202385.82  lakhs
14.21-August-202353.45  lakhs
Total 982.68  lakhs
% Payment 100 %
Advance Amount:  20.00  lakhs        Recovered Amount:  100.00  lakhs        Balance to be Recovered  -80.00  lakhs        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles
Environment & Social Compliances(Sub Project level):
Bridge at Tulka Sirga Kunasa Badasu River(4078) Glove
Detailed report of this Package
Quality
No. of Test Required : 499     No. of Test Done : 511      No. of Test Passed : 500      No. of Test Failed : 2      No. of Test Result Awaited : 9   Test report of this package
Number of Pics Available on Web Repository: 113
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.25-06-2022BR 58 taluka sirgaAbutement A1 LHS 4th lift part 1 concrete completedManoj sain QC ` ` See Pic
2.25-06-2022BR 58 taluka sirgaAnchor block 4th lift Plum concrete work is in progressManoj sain QC ` ` See Pic
3.25-06-2022BR 58 Taluka sirgaLeval checking of Abutement A1Manp ` ` See Pic
4.25-06-2022BR 58 taluka sirgaRR work is in Progress in A1Side approach roadManoj sain QC ` ` See Pic
5.17-06-2022BR 58Abutment A1 side main anchor block 3rd slab is in progress (Vijay Shekhar Naudiyal)????y ??????? ?????y?? ,?unknownunknown See Pic
6.17-06-2022BR 58Abutment A1 third slab first lift has been completed Vijay Shekhar Naudiyal)????y ??????? ?????y?? ,?unknownunknown See Pic
7.17-06-2022BR58Taluka bridge A1 site main anchor block 3rd slab concrete work is on progress.Yashpal Rawatunknownunknown See Pic
8.17-06-2022BR58Taluka bridge A1 site abument 3rd slab 1St lift concrete work is complete .Yashpal Rawatunknownunknown See Pic
9.17-06-2022BR58Taluka bridge A1 site main anchor block 3rd slab reinforcement work is on is in progress.Yashpal Rawatunknownunknown See Pic
10.10-06-2022BR58Taluka bridge A1 site 3rd lift shuttering work is on progress.Yashpal Rawatunknownunknown See Pic
11.10-06-2022BR58taluka bridge A1 site 3rd lift shuttering work is on progress.Yashpal Rawatunknownunknown See Pic
12.10-06-2022BR58Taluka bridge A1 site main anchor block shuttering work is on progress.Yashpal Rawatunknownunknown See Pic
13.10-06-2022BR58Taluka bridge A1 site main anchor block concert work is on progress.Yashpal Rawatunknownunknown See Pic
14.27-05-2022Taluka bridge A1 site main abutment 3rd part lift concert work is on progress.BR 58Yashpal Rawatunknownunknown See Pic
15.27-05-2022BR58Taluka bridge A1 site main anchor block 2 nd lift part 2 plum concrete work done.Yashpal Rawatunknownunknown See Pic
16.27-05-2022BR 58 Taluka sirgaAbutement A2 side leval checking is in progressManoj Sain QC ` ` See Pic
17.27-05-2022BR 58 Taluka sirgaAbutement A2 side leval checkingManoj sain Qc ` ` See Pic
18.27-05-2022BR 58 Taluka sirgaA1 side Main Abutment 3rd lift part 2 concrete work is in ProgressManoj sain Qc ` ` See Pic
19.26-05-2022BR 58 Taluka sirgaAbutment A1 side main anchor 2nd lift part 2 Plum concrete work doneManoj sain QC ` ` See Pic
20.24-05-2022BR 58Mini crusher shifted abutment A2 side (Manoj Sain QC)????y ??????? ?????y?? ,?unknownunknown See Pic