Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/87 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 654 Package Name: UDRP/AF/BR/87 Sanction Cost: 1170.28  lakhs
District: Almora Block: Chaukhutiya Constituency: Dwarahat Circle:
DEA: DEA Bageshwar DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4127   Suspension Bridge at Tadagtaal near Dhanan (125.000 M.) (in prorgress)
Procurement:
Package No.: 654        Package Name: UDRP/AF/BR/87        Tender Date: 11-11-2019        Current Status: Agreement signed        Achieved on Date: 10-12-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/87        Contractor Name: V. K. Gupta & Associates       
Start Date: 19-12-2020        Intended Completion Date: 31-12-2022        Original End Date:  31-03-2022
Total Bond Cost: 119108640 (1191.09 lakhs)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 25846436 for 434 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Env. Man & Moni Plan1.00 Job38.141.00 Job0.95 Job3.0436.23
2.Other Allied Works & Finishing Work 1.00 Job19.051.00 Job0.40 Job0.647.62
3.Foundation RHS1.00 Job61.401.00 Job1.00 Job5.1661.40
4.Foundation LHS1.00 Job61.401.00 Job1.00 Job5.1661.40
5.Abutment Superstructure RHS1.00 Job7.501.00 Job1.00 Job0.637.50
6.Abutment Superstructure LHS1.00 Job7.501.00 Job1.00 Job0.637.50
7.Fixing of chequered Plate/RCC Deck250.00 sqm30.00250.00 sqm250.00 sqm2.5230.00
8.Steel Railing/crush barrier340.00 m38.13340.00 m293.00 m2.7632.86
9.Approach Ramp /path 140.00 m59.54140.00 m105.00 m3.7544.66
10.Protection Work1.00 Job59.541.00 Job0.00 Job00.00
11.Errection Work1.00 Job139.281.00 Job0.00 Job00.00
12.Fabrication Work1.00 job84.641.00 job0.00 job00.00
13.Abutment Substructure RHS1.00 Job113.021.00 Job1.00 Job9.49113.02
14.Abutment Substructure LHS1.00 Job113.021.00 Job1.00 Job9.49113.02
15.Well-Abutments/Pier/Shafts/Caps2.00 job358.932.00 job2.00 job30.14358.93
Total Amount: 1191.09 73.39   874.14
Remarks: No Remarks       Work Program Made On: 09-03-2021       Updation of work program on: 22-12-2022      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.22-March-2021103.77  lakhs
2.20-May-202178.53  lakhs
3.15-July-2021137.36  lakhs
4.30-September-202120.55  lakhs
5.18-December-202156.97  lakhs
6.30-December-202158.80  lakhs
7.16-February-2022123.00  lakhs
8.22-February-2022118.52  lakhs
9.27-May-202234.26  lakhs
Total 731.76  lakhs
% Payment 61.44 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 482     No. of Test Done : 487      No. of Test Passed : 483      No. of Test Failed : 4   Test report of this package
Number of Pics Available on Web Repository: 131
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.20-06-2022TadagtaalCuring work of coloum a2 side approach road in progress at 125 mtr span bridge at tadagtaalSumit Bisht (ss)unknownunknown See Pic
2.02-06-2022Bridge BR87RHS approach in progress.Rajesh sharma ` ` See Pic
3.02-06-2022Bridge BR87LHS approach in progress.Rajesh sharma ` ` See Pic
4.26-05-2022Tadagtaal (BR-87)Abutment A1 side RR wall masonry work in progress.Lalit Kumar (SS) ` ` See Pic
5.25-05-2022TadagtaalApproach (a2)side column 1St lift casting at 125 mtr span bridge at tadagtaalSumit Bisht (ss)unknownunknown See Pic
6.24-05-2022Tadagtaal (BR-87)Abutment A1 side RR wall masonry work in progress.Lalit Kumar (SS) ` ` See Pic
7.24-05-2022Tadagtaal (BR-87)Abutment A2 side C1 & C2 1st lift casting.Lalit Kumar (SS) ` ` See Pic
8.24-05-2022Tadagtaal (BR-87)Abutment A2 side C1 & C2 1st lift casting.Lalit Kumar (SS) ` ` See Pic
9.20-05-2022Tadagtaal (BR-87)Abutment A2 side C3 column raft casting.Lalit Kumar (SS) ` ` See Pic
10.20-05-2022Tadagtaal (BR-87)Abutment A2 side C3 column raft casting.Lalit Kumar (SS) ` ` See Pic
11.19-05-2022Tadagtaal (BR-87)Abutment A2 side C3 column raft shuttering work in progress.Lalit Kumar (SS) ` ` See Pic
12.19-05-2022Tadagtaal (BR-87)Abutment A2 side C3 column raft shuttering work in progress.Lalit Kumar (SS) ` ` See Pic
13.17-05-2022Tadagtaal (BR-87)Abutment A2 side C2 raft casted cubes.Lalit Kumar (SS) ` ` See Pic
14.17-05-2022Tadagtaal (BR-87)Abutment A2 side C2 raft casting.Lalit Kumar (SS) ` ` See Pic
15.17-05-2022Tadagtaal (BR-87)Abutment A2 side C2 raft casting.Lalit Kumar (SS) ` ` See Pic
16.17-05-2022Tadagtaal (BR-87)Abutment A2 side C1 raft casted cubes.Lalit Kumar (SS) ` ` See Pic
17.17-05-2022Tadagtaal (BR-87)Abutment A2 side C1 raft casting.Lalit Kumar (SS) ` ` See Pic
18.17-05-2022Tadagtaal (BR-87)Abutment A2 side C1 & C2 reinforcement and shuttering.Lalit Kumar (SS) ` ` See Pic
19.17-05-2022Tadagtaal (BR-87)Abutment A2 side C1 & C2 raft reinforcement and shuttering.Lalit Kumar (SS) ` ` See Pic
20.17-05-2022Tadagtaal (BR-87)Abutment A2 side C1 raft cube casting work in progress.Lalit Kumar (SS) ` ` See Pic