Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/86 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 653 Package Name: UDRP/AF/BR/86 Sanction Cost: 1357.63  lakhs
District: Nainital Block: Betalghat Constituency: Nainital Circle:
DEA: DEA Nanital DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4129   Suspension Bridge Between Village Tiwari Goan and Village Ghangreti over Kosi River (160.000 M.) (in prorgress)
Procurement:
Package No.: 653        Package Name: UDRP/AF/BR/86        Tender Date: 11-11-2019        Current Status: Agreement signed        Achieved on Date: 06-10-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/86        Contractor Name: V. K. Gupta & Associates       
Start Date: 13-11-2020        Intended Completion Date: 12-02-2023        Original End Date:  13-03-2022
Total Bond Cost: 138294240 (1382.94 lakhs)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 31047003 for 449 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job22.641.00 Job0.00 Job00.00
2.Group of Pile6.00 No82.761.00 No1.00 No8.0882.76
3.Foundation RHS1.00 Job82.761.00 Job1.00 Job8.0882.76
4.Foundation LHS1.00 Job82.761.00 Job1.00 Job8.0882.76
5.Steel Railing/crush barrier320.00 m9.86320.00 m0.00 m00.00
6.Approach Ramp /path 200.00 m21.68200.00 m0.00 m00.00
7.Errection Work1.00 Job36.331.00 Job0.00 Job00.00
8.Gabion work100.00 m65.48100.00 m0.00 m00.00
9.Fabrication Work1.00 job123.841.00 job0.00 job00.00
10.Abutment Substructure RHS1.00 Job210.341.00 Job1.00 Job20.53210.34
11.Abutment Substructure LHS1.00 Job210.341.00 Job1.00 Job20.53210.34
12.Back Wall/ Approach slab1.00 job75.681.00 job0.00 job00.00
13.Admin Block0.00 Job0.000.00 Job0.00 Job00.00
Total Amount: 1024.47 65.3   668.96
Remarks: No Remarks       Work Program Made On: 25-03-2021       Updation of work program on: 28-01-2022      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.30-March-202179.93  lakhs
2.31-May-2021249.79  lakhs
3.25-September-202159.36  lakhs
4.29-November-2021239.02  lakhs
5.12-January-202294.04  lakhs
6.21-March-2022239.02  lakhs
7.17-May-202223.90  lakhs
8.27-June-202252.90  lakhs
9.25-July-202214.11  lakhs
10.22-September-202227.66  lakhs
11.07-October-202227.66  lakhs
12.26-November-202252.90  lakhs
13.22-December-20225.80  lakhs
14.27-January-202374.31  lakhs
15.25-February-202351.00  lakhs
16.17-April-202351.00  lakhs
17.12-May-202345.96  lakhs
Total 1388.36  lakhs
% Payment 100.39 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 866     No. of Test Done : 903      No. of Test Passed : 867      No. of Test Failed : 36   Test report of this package
Number of Pics Available on Web Repository: 240
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.24-06-2022Tiwari gaon Betalghat NainitalCuring work is in progress for A1 Abutment side approach road Footing & ColumnSurendra Singh ` ` See Pic
2.20-06-2022Tiwari GoanColumn steel fixing is in progress for approach road workShivam ` ` See Pic
3.07-06-2022Tiwari gaon Betalghat NainitalA1 Abutment side approach road F5,F6 & F7 Footing Reinforcement Fixing workSurendra Singh Bisht ` ` See Pic
4.07-06-2022Ghiroli Betalghat NainitalCrash Barrier shuttering fixing is in progressSurendra Singh Bisht ` ` See Pic
5.03-06-2022Tiwari gaon Betalghat NainitalCuring work is in progress for A1 Abutment side approach road Footing & ColumnSurendra Singh Bisht ` ` See Pic
6.03-06-2022Tiwari gaon Betalghat NainitalCuring work is in progress for A1 Abutment side approach road Footing & ColumnSurendra Singh ` ` See Pic
7.03-06-2022Tiwari gaon Betalghat NainitalCuring work is in progress for A1 Abutment side approach road Footing & ColumnSurendra Singh ` ` See Pic
8.03-06-2022Tiwari gaonCuring work is in progress for approach road RCC work A-1 sideShivam ` ` See Pic
9.28-05-2022Tiwari gaon Betalghat NainitalCube casting for A1 Abutment side approach road Footing concreting workSurendra Singh Bisht ` ` See Pic
10.28-05-2022Tiwari gaon Betalghat NainitalA1 Abutment side approach road F1,F2 & F3 Footing concreting work doneSurendra Singh Bisht ` ` See Pic
11.28-05-2022Tiwari gaon Betalghat NainitalA1 Abutment side approach road Footing concreting work is in progressSurendra Singh Bisht ` ` See Pic
12.28-05-2022Tiwari gaon Betalghat NainitalA1 Abutment side approach road Footing concreting work is in progressSurendra Singh Bisht ` ` See Pic
13.27-05-2022Tiwari gaon Betalghat NainitalA1 Abutment side approach road Footing concreting work is in progressSurendra Singh Bisht ` ` See Pic
14.26-05-2022Tiwari gaon Betalghat NainitalA1 Abutment side approach road Steel fixing for F1 ,F2 & F3 footing reinforcement checked and found okSurendra Singh Bisht ` ` See Pic
15.26-05-2022Tiwari gaon Betalghat Nainital.A1 Abutment side Approach Road Steel Checked for F1 ,F2 & F3 footingSurendra Singh Bisht ` ` See Pic
16.26-05-2022Tiwari gaon Betalghat NainitalA1Abutment Side Approach Road Footing steel Fixing work is in progressSurendra Singh Bisht ` ` See Pic
17.26-05-2022Tiwari gaon Betalghat NainitalA1Abutment Side Approach Road Footing steel Fixing work is in progressSurendra Singh Bisht ` ` See Pic
18.21-05-2022Tiwari gaon Betalghat NainitalA1 Side Approach Road footing Excavation work is in progressSurendra Singh Bisht ` ` See Pic
19.20-05-2022Tiwari gaon Betalghat NainitalVT Column Erection work is in progressSurendra Singh Bisht ` ` See Pic
20.20-05-2022Tiwari gaon Betalghat NainitalSite visit with EE sir, AE Sir, & DSC RE sirSurendra Singh Bisht ` ` See Pic