Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/86 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 653 Package Name: UDRP/AF/BR/86 Sanction Cost: 1357.63  lakhs
District: Nainital Block: Betalghat Constituency: Nainital Circle:
DEA: DEA Nanital DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4129   Suspension Bridge Between Village Tiwari Goan and Village Ghangreti over Kosi River (160.000 M.) (in prorgress)
Procurement:
Package No.: 653        Package Name: UDRP/AF/BR/86        Tender Date: 11-11-2019        Current Status: Agreement signed        Achieved on Date: 06-10-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/86        Contractor Name: V. K. Gupta & Associates       
Start Date: 13-11-2020        Intended Completion Date: 31-03-2022        Original End Date:  13-03-2022
Total Bond Cost: 138294240 (1382.94 lakhs)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 28972593 for 419 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job22.641.00 Job0.00 Job00.00
2.Group of Pile6.00 No82.766.00 No0.00 No00.00
3.Foundation RHS1.00 Job82.761.00 Job1.00 Job8.0882.76
4.Foundation LHS1.00 Job82.761.00 Job1.00 Job8.0882.76
5.Steel Railing/crush barrier320.00 m9.86320.00 m0.00 m00.00
6.Approach Ramp /path 200.00 m21.68200.00 m0.00 m00.00
7.Errection Work1.00 Job36.331.00 Job0.00 Job00.00
8.Gabion work100.00 m65.48100.00 m0.00 m00.00
9.Fabrication Work1.00 job123.841.00 job0.00 job00.00
10.Abutment Substructure RHS1.00 Job210.341.00 Job1.00 Job20.53210.34
11.Abutment Substructure LHS1.00 Job210.341.00 Job0.60 Job12.32126.20
12.Back Wall/ Approach slab1.00 job75.681.00 job0.00 job00.00
13.Admin Block0.00 Job0.000.00 Job0.00 Job00.00
Total Amount: 1024.47 49.01   502.06
Remarks: No Remarks       Work Program Made On: 25-03-2021       Updation of work program on: 28-07-2021      
Work Program Status:Work Programme workable.
Financial Progress
SNo. Date Payment
1.30-March-202179.93  lakhs
2.31-May-2021249.79  lakhs
3.25-September-202159.36  lakhs
Total 389.08  lakhs
% Payment 28.13 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 415     No. of Test Done : 452      No. of Test Passed : 416      No. of Test Failed : 36   Test report of this package
Number of Pics Available on Web Repository: 126
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.25-11-2021Tiwari gaon Betalghat NainitalM-35 cube testing for 11th lift A1Abutment (Strength -37.95N/mm2 ) at LHSSurendra Singh Bisht ` ` See Pic
2.25-11-2021Tiwari gaon Betalghat NainitalLatest photo at siteSurendra Singh Bisht ` ` See Pic
3.25-11-2021Tiwari gaon Betalghat NainitalLatest photo at siteSurendra Singh Bisht ` ` See Pic
4.25-11-2021Ghiroli Betalghat NainitalAbutment final lift and abutment cap curing is in progress at A-1Surendra Singh Bisht ` ` See Pic
5.25-11-2021Tiwari goanCuring work is in progress at A-1Shivam ` ` See Pic
6.19-11-2021Ghiroli betalghatErection work preparation is in progressShivam ` ` See Pic
7.19-11-2021Ghiroli betalghatStructural members reached at siteShivam ` ` See Pic
8.17-11-2021Tiwari gaon Betalghat NainitalAbutment final lift and abutment cap curing is in progress at A-1Surendra Singh Bisht ` ` See Pic
9.17-11-2021Tiwari gaon Betalghat NainitalAbutment final lift and abutment cap curing is in progress at A-1Surendra Singh Bisht ` ` See Pic
10.17-11-2021Tiwari gaon Betalghat NainitalSite visit by social and gender officer ( Swati bisht mam) with AE sirSurendra Singh Bisht ` ` See Pic
11.16-11-2021BR 86Social Expart M/S swati bisht visit at site Claint And DSCSantosh Shukla ` ` See Pic
12.16-11-20214129Abutment A1 Work in ProgressSantosh shukla ` ` See Pic
13.16-11-2021Tiwari gaonEnvironmental and social safety visitShivam ` ` See Pic
14.12-11-2021Tiwari gaon Betalghat NainitalCube casting for A1Abutment Shaft And Return wall Final Lift with Cap Concreting workSurendra Singh Bisht ` ` See Pic
15.12-11-2021Tiwari gaon Betalghat NainitalA1 Abutment Shaft And Return wall Final Lift with Cap Concreting workSurendra Singh Bisht ` ` See Pic
16.11-11-2021Tiwari gaon Betalghat NainitalLatest photo at siteSurendra Singh Bisht ` ` See Pic
17.11-11-2021Tiwari gaon Betalghat NainitalA1 Abutment Shaft And Return wall 13th Lift with Cap Reinforcement Fixing work is in progressSurendra Singh Bisht ` ` See Pic
18.29-10-2021Tiwari gaon Betalghat NainitalCube casting for A1Abutment Shaft And Return wall 12th Lift ConcretingSurendra Singh Bisht ` ` See Pic
19.29-10-2021Tiwari gaon Betalghat NainitalA1 Abutment Shaft And Return wall 12th Lift Concreting work is in progress at LHSSurendra Singh Bisht ` ` See Pic
20.29-10-2021Tiwari gaon Betalghat NainitalA1Abutment Shaft And Return wall 12th Lift Concreting work is in progress at LHSSurendra Singh Bisht ` ` See Pic