UDRP/AF/BR/83
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
650 |
Package Name: |
UDRP/AF/BR/83 |
Sanction Cost: |
926.21 lakhs |
District: |
Pauri |
Block: |
Zahrikhal |
Constituency: |
Chaubattakhal |
Circle: |
Tehri WB Circle |
DEA: |
DEA Pauri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4109 60M Span Bridge at Kot Malla talla kandiya kulashu rithakhal MR (70.000 M.) (in prorgress) |
|
Procurement: |
Package No.: 650
Package Name: UDRP/AF/BR/83
Tender Date: 22-01-2020
Current Status: Agreement signed
Achieved on Date: 15-07-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/83
Contractor Name: M/S.ARKS Universal pvt.ltd
|
Start Date: 03-09-2020
Intended Completion Date: 01-02-2023
Original End Date: 01-02-2022
|
Total Bond Cost: 94947092.68 (949.47 lakhs)
Variation Cost: -6244317.40 (-62.44 lakhs) Hence Total Bond Cost is 88702775.28 (887.03 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 28674296 for 604 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 0.20 KM | 9.46 | 0.20 KM | 0.00 KM | 0 | 0.00 | 2. | R/Wall, B/ Wall Type Protection works | 200.00 m | 23.74 | 200.00 m | 25.00 m | 0.31 | 2.97 | 3. | PC/CC i/c Prime Coat, Tack Coat | 0.10 KM | 1.64 | 0.10 KM | 0.00 KM | 0 | 0.00 | 4. | Crash Barrier | 142.00 m | 9.07 | 142.00 m | 0.00 m | 0 | 0.00 | 5. | Road Furniture | 4.00 No | 0.47 | 4.00 No | 4.00 No | 0.05 | 0.47 | 6. | Env. Man & Moni Plan | 1.00 Job | 3.83 | 1.00 Job | 0.66 Job | 0.26 | 2.53 | 7. | Other Allied Works & Finishing Work | 1.00 Job | 4.48 | 1.00 Job | 0.40 Job | 0.18 | 1.79 | 8. | Foundation RHS | 1.00 Job | 4.18 | 1.00 Job | 1.00 Job | 0.43 | 4.18 | 9. | Foundation LHS | 1.00 Job | 4.18 | 1.00 Job | 0.90 Job | 0.39 | 3.76 | 10. | Abutment Superstructure RHS | 1.00 Job | 135.46 | 1.00 Job | 0.90 Job | 12.57 | 121.91 | 11. | Abutment Superstructure LHS | 1.00 Job | 135.46 | 1.00 Job | 0.80 Job | 11.17 | 108.36 | 12. | Deck Cable laying, stretching and Fixing Transoms/Deck Slab | 1.00 no | 28.86 | 1.00 no | 0.00 no | 0 | 0.00 | 13. | Steel Railing/crush barrier | 100.00 m | 4.48 | 100.00 m | 0.00 m | 0 | 0.00 | 14. | Approach Ramp /path | 100.00 m | 46.35 | 100.00 m | 0.00 m | 0 | 0.00 | 15. | Protection Work | 1.00 Job | 28.38 | 1.00 Job | 0.35 Job | 1.02 | 9.93 | 16. | Errection Work | 1.00 Job | 141.95 | 1.00 Job | 0.00 Job | 0 | 0.00 | 17. | PCC in Foundation | 36.30 cum | 2.64 | 36.30 cum | 26.00 cum | 0.19 | 1.89 | 18. | H.P. Stone | 2261.50 cum | 20.44 | 2261.50 cum | 350.00 cum | 0.33 | 3.16 | 19. | Fabrication Work | 1.00 job | 354.92 | 1.00 job | 0.90 job | 32.93 | 319.43 | 20. | Fixing Bearing/Slab Casting | 6.00 job | 6.72 | 6.00 job | 0.00 job | 0 | 0.00 | 21. | Wearing Coat | 26.15 Cum | 3.22 | 26.15 Cum | 0.00 Cum | 0 | 0.00 |
Total Amount: |
969.93 |
|
59.84 |
580.38 |
|
Remarks:
No Remarks
Work Program Made On:
01-10-2020
Updation of work program on:
25-03-2022
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 13-January-2021 | 17.16 lakhs |
2. | 12-July-2021 | 106.66 lakhs |
3. | 03-September-2021 | 25.06 lakhs |
4. | 11-October-2021 | 11.33 lakhs |
5. | 15-March-2022 | 322.80 lakhs |
6. | 31-May-2022 | 8.00 lakhs |
7. | 31-January-2023 | 143.40 lakhs |
8. | 09-March-2023 | 147.09 lakhs |
9. | 31-May-2023 | 126.76 lakhs |
Total |
908.26 lakhs |
% Payment |
102.39 % |
|
Advance Amount: 242.68 lakhs
Recovered Amount: 204.40 lakhs
Balance to be Recovered 38.28 lakhs
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. |
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 694 |
No Notice issued. |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 08-06-2022 | BR-83 kit talla kot Malla | EE Sir site visit | Bharat Bhoosan Sharma | unknown | unknown | See Pic |
2. | 07-06-2022 | Abutment A-2 RHS | Erection work is in progress | Bharat Bhoosan Sharma | unknown | unknown | See Pic |
3. | 07-06-2022 | BR-83 Kot malla talla bridge Under FPIU Pauri | Site visit of ExEn sir and RE DSC-1 for errection work inspection. | Jitendra Rawat | ` | ` | See Pic |
4. | 07-06-2022 | BR-83 Kot malla talla Bridge under FPIU Pauri. | Site visit of ExEn sir with RE for errection work. | Jitendra Rawat | ` | ` | See Pic |
5. | 04-06-2022 | Kot talla kot malla | Errection work is in progress. | Sukhchain | ` | ` | See Pic |
6. | 03-06-2022 | Errection work is in progress | Errection work is in progress | Jai Prakash Narayan Singh | unknown | unknown | See Pic |
7. | 02-06-2022 | RHS Approach Road cutting work is in progress | RHS Approach Road cutting work is in progress | Jai Prakash Narayan Singh | unknown | unknown | See Pic |
8. | 01-06-2022 | Rope fixing work is in progress | Rope fixing work is in progress | Jai Prakash Narayan Singh | unknown | unknown | See Pic |
9. | 01-06-2022 | RHS Rope Fixing work is in progress | RHS Rope Fixing work is in progress | Jai Prakash Narayan Singh | unknown | unknown | See Pic |
10. | 27-05-2022 | LHS Tower Errection and Rope Fixing work | LHS Tower Errection and Rope Fixing work is in progress | Jai Prakash Narayan Singh | unknown | unknown | See Pic |
11. | 27-05-2022 | RHS curing work is in progress | RHS curing work is in progress | Jai Prakash Narayan Singh | unknown | unknown | See Pic |
12. | 27-05-2022 | LHS Tower Errection and Rope Fixing work | LHS Tower Errection and Rope Fixing work | Jai Prakash Narayan Singh | unknown | unknown | See Pic |
13. | 26-05-2022 | RHS Tower Errection and Rope Fixing work | RHS Tower Errection and Rope Fixing work | Jai Prakash Narayan Singh | unknown | unknown | See Pic |
14. | 26-05-2022 | RHS RR Masonry work is in progress | RHS RR Masonry work is in progress | Jai Prakash Narayan Singh | unknown | unknown | See Pic |
15. | 26-05-2022 | RHS Tower Errection and Rope Fixing work is in progress | RHS Tower Errection and Rope Fixing work is in progress | Jai Prakash Narayan Singh | unknown | unknown | See Pic |
16. | 26-05-2022 | RHS RR Masonry work is in progress | RHS RR Masonry work is in progress | Jai Prakash Narayan Singh | unknown | unknown | See Pic |
17. | 26-05-2022 | Deevin Sesmic System Bhopal | Bearing testing for BR-83 is in progress | Bharat Bhoosan Sharma | unknown | unknown | See Pic |
18. | 25-05-2022 | LHS Tower Errection and Rope Fixing work is in progress | LHS Tower Errection and Rope Fixing work is in progress | Jai Prakash Narayan Singh | unknown | unknown | See Pic |
19. | 25-05-2022 | RHS RR Masonry work is in progress | RHS RR Masonry work is in progress | Jai Prakash Narayan Singh | unknown | unknown | See Pic |
20. | 25-05-2022 | RHS RR Masonry work is in progress | RHS RR Masonry work is in progress | Jai Prakash Narayan Singh | unknown | unknown | See Pic |
|
|