Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/83 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 650 Package Name: UDRP/AF/BR/83 Sanction Cost: 926.21  lakhs
District: Pauri Block: Zahrikhal Constituency: Chaubattakhal Circle: Tehri WB Circle
DEA: DEA Pauri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4109   60M Span Bridge at Kot Malla talla kandiya kulashu rithakhal MR (70.000 M.) (in prorgress)
Procurement:
Package No.: 650        Package Name: UDRP/AF/BR/83        Tender Date: 22-01-2020        Current Status: Agreement signed        Achieved on Date: 15-07-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/83        Contractor Name: M/S.ARKS Universal pvt.ltd       
Start Date: 03-09-2020        Intended Completion Date: 31-03-2022        Original End Date:  01-02-2022
Total Bond Cost: 94947092.68 (949.47 lakhs)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 23831948 for 502 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence0.20 KM9.460.20 KM0.00 KM00.00
2.R/Wall, B/ Wall Type Protection works200.00 m23.74200.00 m25.00 m0.312.97
3.PC/CC i/c Prime Coat, Tack Coat0.10 KM1.640.10 KM0.00 KM00.00
4.Crash Barrier142.00 m9.07142.00 m0.00 m00.00
5.Road Furniture4.00 No0.474.00 No4.00 No0.050.47
6.Env. Man & Moni Plan1.00 Job3.831.00 Job0.66 Job0.262.53
7.Other Allied Works & Finishing Work 1.00 Job4.481.00 Job0.20 Job0.090.90
8.Foundation RHS1.00 Job4.181.00 Job1.00 Job0.434.18
9.Foundation LHS1.00 Job4.181.00 Job1.00 Job0.434.18
10.Abutment Superstructure RHS1.00 Job135.461.00 Job0.90 Job12.57121.91
11.Abutment Superstructure LHS1.00 Job135.461.00 Job0.80 Job11.17108.36
12.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 1.00 no28.861.00 no0.00 no00.00
13.Steel Railing/crush barrier100.00 m4.48100.00 m0.00 m00.00
14.Approach Ramp /path 100.00 m46.35100.00 m0.00 m00.00
15.Protection Work1.00 Job28.381.00 Job0.35 Job1.029.93
16.Errection Work1.00 Job141.951.00 Job0.00 Job00.00
17.PCC in Foundation36.30 cum2.6436.30 cum26.00 cum0.191.89
18.H.P. Stone2261.50 cum20.442261.50 cum350.00 cum0.333.16
19.Fabrication Work1.00 job354.921.00 job0.20 job7.3270.98
20.Fixing Bearing/Slab Casting6.00 job6.726.00 job0.00 job00.00
21.Wearing Coat26.15 Cum3.2226.15 Cum0.00 Cum00.00
Total Amount: 969.93 34.18   331.46
Remarks: No Remarks       Work Program Made On: 01-10-2020       Updation of work program on: 17-09-2021      
Work Program Status:Program Failed
Financial Progress
SNo. Date Payment
1.13-January-202117.16  lakhs
2.12-July-2021106.66  lakhs
3.03-September-202125.06  lakhs
4.11-October-202111.33  lakhs
Total 160.21  lakhs
% Payment 16.87 %
Advance Amount:  204.40  lakhs        Recovered Amount:  52.53  lakhs        Balance to be Recovered  151.87  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 429     No. of Test Done : 429      No. of Test Passed : 429      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 524
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.25-11-2021Br83LHS Abutment completedKrishnan gopalunknownunknown See Pic
2.22-11-2021Br51Abutment backfilling work is in progressKrishnan gopalunknownunknown See Pic
3.18-11-2021RHS protection wall 2nd step 1st lift steel binding and shuttering work is in progressRHS protection wall 2nd step 1st lift steel binding and shuttering work is in progressJai Prakash Narayan Singhunknownunknown See Pic
4.18-11-2021Br83RHS Abutment protection work is in progressKrishnan gopalunknownunknown See Pic
5.18-11-2021Br83LHS Abutment cap completed, protection work is in progressKrishnan gopalunknownunknown See Pic
6.17-11-2021RHS protection wall 2nd step 1st lift steel binding and shuttering work is in progressRHS protection wall 2nd step 1st lift steel binding and shuttering work is in progressJai Prakash Narayan Singhunknownunknown See Pic
7.17-11-2021LHS cube casting work is in progressLHS cube casting work is in progressJai Prakash Narayan Singhunknownunknown See Pic
8.17-11-2021Cube casting work is in progressCube casting work is in progressJai Prakash Narayan Singhunknownunknown See Pic
9.17-11-2021LHS slump checked found 90mmLHS slump checked found 90mmJai Prakash Narayan Singh ` ` See Pic
10.17-11-2021LHS abutment à1 cap M 35 concrete pouring work is in progressLHS abutment à1 cap M35 concrete pouring work is in progressJai Prakash Narayan Singhunknownunknown See Pic
11.15-11-2021Br83LHS Abutment cap completedKrishnan gopalunknownunknown See Pic
12.01-11-2021Br83LHS Abutment cap and return wall concrete work is in progress,cube casting.Krishnan gopalunknownunknown See Pic
13.01-11-2021Br83Gabion wall for dumping zoneKrishnan gopalunknownunknown See Pic
14.01-11-2021Br83LHS Abutment cap and return wall concrete work is in progressKrishnan gopalunknownunknown See Pic
15.01-11-2021Br83LHS Abutment cap and return wall concrete work is in progressKrishnan gopalunknownunknown See Pic
16.01-11-2021Br83LHS Abutment cap and return wall concrete work is in progress, cube casting doneKrishnan gopalunknownunknown See Pic
17.31-10-2021Br-83 Kot malla talla bridge under FPIU Pauri.Cube casting for Abutment cap of A1(LHS) during cap casting with RCC-M-35 grade concrete under progress.Jitendra Rawat ` ` See Pic
18.31-10-2021Br-83 kot malla talla bridge, under FPIU Pauri divisionAbutment cap A1 (LHS) casing with RCC M-35 grade concrete under progress.Jitendra Rawat ` ` See Pic
19.30-10-2021LHS abutment à1 cap Rainforcement checking work is in progressLHS abutment à1 cap steel checking work is in progressJai Prakash Narayan Singhunknownunknown See Pic
20.30-10-2021LHS abutment à1 cap and Return wall steel binding and shuttering work is in progressLHS abutment à1 cap and Return wall steel binding and shuttering work is in progressJai Prakash Narayan Singhunknownunknown See Pic