Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/83 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 650 Package Name: UDRP/AF/BR/83 Sanction Cost: 926.21  lakhs
District: Pauri Block: Zahrikhal Constituency: Chaubattakhal Circle: Tehri WB Circle
DEA: DEA Pauri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4109   60M Span Bridge at Kot Malla talla kandiya kulashu rithakhal MR (70.000 M.) (in prorgress)
Procurement:
Package No.: 650        Package Name: UDRP/AF/BR/83        Tender Date: 22-01-2020        Current Status: Agreement signed        Achieved on Date: 15-07-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/83        Contractor Name: M/S.ARKS Universal pvt.ltd       
Start Date: 03-09-2020        Intended Completion Date: 01-02-2023        Original End Date:  01-02-2022
Total Bond Cost: 94947092.68 (949.47 lakhs)        Variation Cost: -6244317.40 (-62.44 lakhs)     Hence Total Bond Cost is   88702775.28 (887.03 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 28674296 for 604 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence0.20 KM9.460.20 KM0.00 KM00.00
2.R/Wall, B/ Wall Type Protection works200.00 m23.74200.00 m25.00 m0.312.97
3.PC/CC i/c Prime Coat, Tack Coat0.10 KM1.640.10 KM0.00 KM00.00
4.Crash Barrier142.00 m9.07142.00 m0.00 m00.00
5.Road Furniture4.00 No0.474.00 No4.00 No0.050.47
6.Env. Man & Moni Plan1.00 Job3.831.00 Job0.66 Job0.262.53
7.Other Allied Works & Finishing Work 1.00 Job4.481.00 Job0.40 Job0.181.79
8.Foundation RHS1.00 Job4.181.00 Job1.00 Job0.434.18
9.Foundation LHS1.00 Job4.181.00 Job0.90 Job0.393.76
10.Abutment Superstructure RHS1.00 Job135.461.00 Job0.90 Job12.57121.91
11.Abutment Superstructure LHS1.00 Job135.461.00 Job0.80 Job11.17108.36
12.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 1.00 no28.861.00 no0.00 no00.00
13.Steel Railing/crush barrier100.00 m4.48100.00 m0.00 m00.00
14.Approach Ramp /path 100.00 m46.35100.00 m0.00 m00.00
15.Protection Work1.00 Job28.381.00 Job0.35 Job1.029.93
16.Errection Work1.00 Job141.951.00 Job0.00 Job00.00
17.PCC in Foundation36.30 cum2.6436.30 cum26.00 cum0.191.89
18.H.P. Stone2261.50 cum20.442261.50 cum350.00 cum0.333.16
19.Fabrication Work1.00 job354.921.00 job0.90 job32.93319.43
20.Fixing Bearing/Slab Casting6.00 job6.726.00 job0.00 job00.00
21.Wearing Coat26.15 Cum3.2226.15 Cum0.00 Cum00.00
Total Amount: 969.93 59.84   580.38
Remarks: No Remarks       Work Program Made On: 01-10-2020       Updation of work program on: 25-03-2022      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.13-January-202117.16  lakhs
2.12-July-2021106.66  lakhs
3.03-September-202125.06  lakhs
4.11-October-202111.33  lakhs
5.15-March-2022322.80  lakhs
6.31-May-20228.00  lakhs
7.31-January-2023143.40  lakhs
8.09-March-2023147.09  lakhs
9.31-May-2023126.76  lakhs
Total 908.26  lakhs
% Payment 102.39 %
Advance Amount:  242.68  lakhs        Recovered Amount:  204.40  lakhs        Balance to be Recovered  38.28  lakhs        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 462     No. of Test Done : 462      No. of Test Passed : 462      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 694
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.08-06-2022BR-83 kit talla kot MallaEE Sir site visitBharat Bhoosan Sharmaunknownunknown See Pic
2.07-06-2022Abutment A-2 RHSErection work is in progressBharat Bhoosan Sharmaunknownunknown See Pic
3.07-06-2022BR-83 Kot malla talla bridge Under FPIU PauriSite visit of ExEn sir and RE DSC-1 for errection work inspection.Jitendra Rawat ` ` See Pic
4.07-06-2022BR-83 Kot malla talla Bridge under FPIU Pauri.Site visit of ExEn sir with RE for errection work.Jitendra Rawat ` ` See Pic
5.04-06-2022Kot talla kot mallaErrection work is in progress.Sukhchain ` ` See Pic
6.03-06-2022Errection work is in progressErrection work is in progressJai Prakash Narayan Singhunknownunknown See Pic
7.02-06-2022RHS Approach Road cutting work is in progressRHS Approach Road cutting work is in progressJai Prakash Narayan Singhunknownunknown See Pic
8.01-06-2022Rope fixing work is in progressRope fixing work is in progressJai Prakash Narayan Singhunknownunknown See Pic
9.01-06-2022RHS Rope Fixing work is in progressRHS Rope Fixing work is in progressJai Prakash Narayan Singhunknownunknown See Pic
10.27-05-2022LHS Tower Errection and Rope Fixing workLHS Tower Errection and Rope Fixing work is in progressJai Prakash Narayan Singhunknownunknown See Pic
11.27-05-2022RHS curing work is in progressRHS curing work is in progressJai Prakash Narayan Singhunknownunknown See Pic
12.27-05-2022LHS Tower Errection and Rope Fixing workLHS Tower Errection and Rope Fixing workJai Prakash Narayan Singhunknownunknown See Pic
13.26-05-2022RHS Tower Errection and Rope Fixing workRHS Tower Errection and Rope Fixing workJai Prakash Narayan Singhunknownunknown See Pic
14.26-05-2022RHS RR Masonry work is in progressRHS RR Masonry work is in progressJai Prakash Narayan Singhunknownunknown See Pic
15.26-05-2022RHS Tower Errection and Rope Fixing work is in progressRHS Tower Errection and Rope Fixing work is in progressJai Prakash Narayan Singhunknownunknown See Pic
16.26-05-2022RHS RR Masonry work is in progressRHS RR Masonry work is in progressJai Prakash Narayan Singhunknownunknown See Pic
17.26-05-2022Deevin Sesmic System BhopalBearing testing for BR-83 is in progressBharat Bhoosan Sharmaunknownunknown See Pic
18.25-05-2022LHS Tower Errection and Rope Fixing work is in progressLHS Tower Errection and Rope Fixing work is in progressJai Prakash Narayan Singhunknownunknown See Pic
19.25-05-2022RHS RR Masonry work is in progressRHS RR Masonry work is in progressJai Prakash Narayan Singhunknownunknown See Pic
20.25-05-2022RHS RR Masonry work is in progressRHS RR Masonry work is in progressJai Prakash Narayan Singhunknownunknown See Pic