Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/82 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 649 Package Name: UDRP/AF/BR/82 Sanction Cost: 143.04  lakhs
District: Uttarkashi Block: Dunda Constituency: Yamunotri Circle:
DEA: DEA Uttarkashi DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4124   Steel Tuss Bridle Bridge over Khurmola Gard at Hayudai Tok (40.000 M.) (completed)
Procurement:
Package No.: 649        Package Name: UDRP/AF/BR/82        Tender Date: 11-11-2019        Current Status: Agreement signed        Achieved on Date: 05-11-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/82        Contractor Name: M/S Utsav Associate       
Start Date: 21-11-2020        Intended Completion Date: 07-05-2022        Original End Date:  20-02-2022
Total Bond Cost: 12316116.71 (123.16 lakhs)        Variation Cost: 2937755.87 (29.38 lakhs)     Hence Total Bond Cost is   15253872.58 (152.54 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 2752626 for 447 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job14.451.00 Job1.00 Job13.1414.45
2.Foundation RHS1.00 Job0.371.00 Job1.00 Job0.340.37
3.Foundation LHS1.00 Job0.371.00 Job1.00 Job0.340.37
4.Abutment Superstructure RHS1.00 Job8.211.00 Job1.00 Job7.478.21
5.Abutment Superstructure LHS1.00 Job8.211.00 Job1.00 Job7.478.21
6.Steel Railing/crush barrier1.00 m8.091.00 m1.00 m7.368.09
7.Approach Ramp /path 1.00 m31.051.00 m1.00 m28.2431.05
8.Protection Work1.00 Job1.771.00 Job1.00 Job1.611.77
9.Errection Work1.00 Job7.641.00 Job1.00 Job6.957.64
10.Fabrication Work1.00 job26.851.00 job1.00 job24.4226.85
11.Fixing Bearing/Slab Casting4.00 job2.954.00 job4.00 job2.682.95
Total Amount: 109.96 100   109.96
Remarks: No Remarks       Work Program Made On: 29-01-2021       Updation of work program on: 24-05-2022      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-June-202116.93  lakhs
2.29-December-202127.23  lakhs
3.31-March-202257.84  lakhs
4.15-June-202223.00  lakhs
5.20-October-202227.54  lakhs
Total 152.54  lakhs
% Payment 100 %
Advance Amount:  25.61  lakhs        Recovered Amount:  25.61  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 386     No. of Test Done : 472      No. of Test Passed : 462      No. of Test Failed : 10   Test report of this package
Number of Pics Available on Web Repository: 18
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.15-02-2022Hayundadi tok BR- 80M35 concrete casting is completed of 3rd lift of Abutment A2 sideAzad singh ` ` See Pic
2.17-07-2021BR/82A1cap concrete work in progress, concrete grade M35.Niraj pathakunknownunknown See Pic
3.17-07-2021BR/82Slump test on progress, concrete grade M35,A1,cap.Niraj pathakunknownunknown See Pic
4.04-05-2021Abutment A1 at hyundadi tok bridge.Abutment A 1 completed upto 9 lits at hyundadi tok bridge.Abhishek tiwari ` ` See Pic
5.04-05-2021Abutment A2 completed upto 9 lifts at hyundadi tok bridge in district Uttarkashi.Abutmemt A2 completed upto 9 lifts at hyundadi tok bridge in district Uttarkashi.Abhishek tiwari ` ` See Pic
6.06-04-2021BR/82/uttarkashi.Medical health checkup camp.Niraj pathakunknownunknown See Pic
7.06-04-2021BR/82/uttarkashi.Medical health checkup camp.Niraj pathakunknownunknown See Pic
8.06-04-2021BR/82/uttarkashi.Construction material testing work on progress.Niraj pathakunknownunknown See Pic
9.06-04-2021BR/82/uttarkashi.Cube testing work in progress,Niraj pathakunknownunknown See Pic
10.06-04-2021BR/82/uttarkashi.Fine aggregate gradation test on progress,Niraj pathakunknownunknown See Pic
11.06-04-2021BR/82/uttarkashi.Coarse aggregate gradation test on progress.Niraj pathakunknownunknown See Pic
12.05-04-2021Hyundadi tok,BR/82A1,,LHS,wall 5th lift concrete work in progress, concrete grade M/35/Niraj pathakunknownunknown See Pic
13.02-04-2021Hayundadi tok Abutment A1 4th lift readyBridge no 82Arun kumar ` ` See Pic
14.20-03-2021A1 Side 3rd liftA1 side 3 rd lift complete of khurmola gaad hyundadi tokANKIT KURIYAL ` ` See Pic
15.20-02-2021Reinforcement and shuttering checking at Br-82 kurmola gaad Abutment A2 1st liftAbutment A2 first lift reinforcement checking kurmola gaadArun kumar R.E ` ` See Pic
16.20-02-2021Hayundadi TokSieve analysis for first lift Abutment A2Azad Rana ` ` See Pic
17.20-02-2021Hayundadi TokLevel checking by Resident Engineer with DSC Team for Abutment A1Imteyaj Ansariunknownunknown See Pic
18.18-01-2021Hayundadi tok bridge no-82Survey and layoutDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic