UDRP/AF/BR/82
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
649 |
Package Name: |
UDRP/AF/BR/82 |
Sanction Cost: |
143.04 lakhs |
District: |
Uttarkashi |
Block: |
Dunda |
Constituency: |
Yamunotri |
Circle: |
|
DEA: |
DEA Uttarkashi |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4124 Steel Tuss Bridle Bridge over Khurmola Gard at Hayudai Tok (40.000 M.) (completed) |
|
Procurement: |
Package No.: 649
Package Name: UDRP/AF/BR/82
Tender Date: 11-11-2019
Current Status: Agreement signed
Achieved on Date: 05-11-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/82
Contractor Name: M/S Utsav Associate
|
Start Date: 21-11-2020
Intended Completion Date: 07-05-2022
Original End Date: 20-02-2022
|
Total Bond Cost: 12316116.71 (123.16 lakhs)
Variation Cost: 2937755.87 (29.38 lakhs) Hence Total Bond Cost is 15253872.58 (152.54 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 2752626 for 447 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 14.45 | 1.00 Job | 1.00 Job | 13.14 | 14.45 | 2. | Foundation RHS | 1.00 Job | 0.37 | 1.00 Job | 1.00 Job | 0.34 | 0.37 | 3. | Foundation LHS | 1.00 Job | 0.37 | 1.00 Job | 1.00 Job | 0.34 | 0.37 | 4. | Abutment Superstructure RHS | 1.00 Job | 8.21 | 1.00 Job | 1.00 Job | 7.47 | 8.21 | 5. | Abutment Superstructure LHS | 1.00 Job | 8.21 | 1.00 Job | 1.00 Job | 7.47 | 8.21 | 6. | Steel Railing/crush barrier | 1.00 m | 8.09 | 1.00 m | 1.00 m | 7.36 | 8.09 | 7. | Approach Ramp /path | 1.00 m | 31.05 | 1.00 m | 1.00 m | 28.24 | 31.05 | 8. | Protection Work | 1.00 Job | 1.77 | 1.00 Job | 1.00 Job | 1.61 | 1.77 | 9. | Errection Work | 1.00 Job | 7.64 | 1.00 Job | 1.00 Job | 6.95 | 7.64 | 10. | Fabrication Work | 1.00 job | 26.85 | 1.00 job | 1.00 job | 24.42 | 26.85 | 11. | Fixing Bearing/Slab Casting | 4.00 job | 2.95 | 4.00 job | 4.00 job | 2.68 | 2.95 |
Total Amount: |
109.96 |
|
100 |
109.96 |
|
Remarks:
No Remarks
Work Program Made On:
29-01-2021
Updation of work program on:
24-05-2022
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-June-2021 | 16.93 lakhs |
2. | 29-December-2021 | 27.23 lakhs |
3. | 31-March-2022 | 57.84 lakhs |
4. | 15-June-2022 | 23.00 lakhs |
5. | 20-October-2022 | 27.54 lakhs |
Total |
152.54 lakhs |
% Payment |
100 % |
|
Advance Amount: 25.61 lakhs
Recovered Amount: 25.61 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 18 |
No Notice issued. |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 15-02-2022 | Hayundadi tok BR- 80 | M35 concrete casting is completed of
3rd lift of Abutment A2 side | Azad singh | ` | ` | See Pic |
2. | 17-07-2021 | BR/82 | A1cap concrete work in progress, concrete grade M35. | Niraj pathak | unknown | unknown | See Pic |
3. | 17-07-2021 | BR/82 | Slump test on progress, concrete grade M35,A1,cap. | Niraj pathak | unknown | unknown | See Pic |
4. | 04-05-2021 | Abutment A1 at hyundadi tok bridge. | Abutment A 1 completed upto 9 lits at hyundadi tok bridge. | Abhishek tiwari | ` | ` | See Pic |
5. | 04-05-2021 | Abutment A2 completed upto 9 lifts at hyundadi tok bridge in district Uttarkashi. | Abutmemt A2 completed upto 9 lifts at hyundadi tok bridge in district Uttarkashi. | Abhishek tiwari | ` | ` | See Pic |
6. | 06-04-2021 | BR/82/uttarkashi. | Medical health checkup camp. | Niraj pathak | unknown | unknown | See Pic |
7. | 06-04-2021 | BR/82/uttarkashi. | Medical health checkup camp. | Niraj pathak | unknown | unknown | See Pic |
8. | 06-04-2021 | BR/82/uttarkashi. | Construction material testing work on progress. | Niraj pathak | unknown | unknown | See Pic |
9. | 06-04-2021 | BR/82/uttarkashi. | Cube testing work in progress, | Niraj pathak | unknown | unknown | See Pic |
10. | 06-04-2021 | BR/82/uttarkashi. | Fine aggregate gradation test on progress, | Niraj pathak | unknown | unknown | See Pic |
11. | 06-04-2021 | BR/82/uttarkashi. | Coarse aggregate gradation test on progress. | Niraj pathak | unknown | unknown | See Pic |
12. | 05-04-2021 | Hyundadi tok,BR/82 | A1,,LHS,wall 5th lift concrete work in progress, concrete grade M/35/ | Niraj pathak | unknown | unknown | See Pic |
13. | 02-04-2021 | Hayundadi tok Abutment A1 4th lift ready | Bridge no 82 | Arun kumar | ` | ` | See Pic |
14. | 20-03-2021 | A1 Side 3rd lift | A1 side 3 rd lift complete of khurmola gaad hyundadi tok | ANKIT KURIYAL | ` | ` | See Pic |
15. | 20-02-2021 | Reinforcement and shuttering checking at Br-82 kurmola gaad Abutment A2 1st lift | Abutment A2 first lift reinforcement checking kurmola gaad | Arun kumar R.E | ` | ` | See Pic |
16. | 20-02-2021 | Hayundadi Tok | Sieve analysis for first lift Abutment A2 | Azad Rana | ` | ` | See Pic |
17. | 20-02-2021 | Hayundadi Tok | Level checking by Resident Engineer with DSC Team for Abutment A1 | Imteyaj Ansari | unknown | unknown | See Pic |
18. | 18-01-2021 | Hayundadi tok bridge no-82 | Survey and layout | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
|
|