UDRP/AF/BR/81
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
648 |
Package Name: |
UDRP/AF/BR/81 |
Sanction Cost: |
517.54 lakhs |
District: |
Uttarkashi |
Block: |
Puraula |
Constituency: |
Purola |
Circle: |
|
DEA: |
DEA Uttarkashi |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4123 Steel Truss Bridle Bridge over Kamal River at Bingsi Chaini (70.000 M.) (completed) |
|
Procurement: |
Package No.: 648
Package Name: UDRP/AF/BR/81
Tender Date: 20-11-2019
Current Status: Agreement signed
Achieved on Date: 10-06-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/81
Contractor Name: Border Builders
|
Start Date: 01-07-2020
Intended Completion Date: 09-02-2022
Original End Date: 30-09-2021
|
Total Bond Cost: 51557276.96 (515.57 lakhs)
Variation Cost: 2597413.21 (25.97 lakhs) Hence Total Bond Cost is 54154690.17 (541.55 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 10827180 for 420 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 46.67 | 1.00 Job | 1.00 Job | 10.14 | 46.67 | 2. | Foundation RHS | 1.00 Job | 20.28 | 1.00 Job | 1.00 Job | 4.41 | 20.28 | 3. | Foundation LHS | 1.00 Job | 20.28 | 1.00 Job | 1.00 Job | 4.41 | 20.28 | 4. | Abutment Superstructure RHS | 1.00 Job | 40.85 | 1.00 Job | 1.00 Job | 8.87 | 40.85 | 5. | Abutment Superstructure LHS | 1.00 Job | 40.85 | 1.00 Job | 1.00 Job | 8.87 | 40.85 | 6. | Fixing of chequered Plate/RCC Deck | 1.00 sqm | 34.38 | 1.00 sqm | 1.00 sqm | 7.47 | 34.38 | 7. | Steel Railing/crush barrier | 150.00 m | 8.47 | 150.00 m | 150.00 m | 1.84 | 8.47 | 8. | Approach Ramp /path | 1.00 m | 21.93 | 1.00 m | 1.00 m | 4.76 | 21.93 | 9. | Protection Work | 204.00 Job | 20.44 | 204.00 Job | 204.00 Job | 4.44 | 20.44 | 10. | Errection Work | 1.00 Job | 42.90 | 1.00 Job | 1.00 Job | 9.32 | 42.90 | 11. | Fabrication Work | 117.00 job | 161.30 | 117.00 job | 117.00 job | 35.04 | 161.30 | 12. | Fixing Bearing/Slab Casting | 4.00 job | 2.00 | 4.00 job | 4.00 job | 0.43 | 2.00 |
Total Amount: |
460.35 |
|
100 |
460.35 |
|
Remarks:
No Remarks
Work Program Made On:
22-08-2020
Updation of work program on:
24-05-2022
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 04-February-2021 | 51.73 lakhs |
2. | 30-March-2021 | 37.42 lakhs |
3. | 22-July-2021 | 145.71 lakhs |
4. | 25-August-2021 | 60.66 lakhs |
5. | 30-September-2021 | 61.05 lakhs |
6. | 06-November-2021 | 13.39 lakhs |
7. | 07-January-2022 | 20.28 lakhs |
8. | 24-February-2022 | 72.15 lakhs |
9. | 31-March-2022 | 33.26 lakhs |
10. | 31-May-2022 | 45.26 lakhs |
Total |
540.91 lakhs |
% Payment |
99.88 % |
|
Advance Amount: 38.78 lakhs
Recovered Amount: 38.78 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 198 |
No Notice issued. |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 31-01-2022 | BR 81 | Erection of structural is in progress and bolts tightening(vijay shekhar Naudiyal) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
2. | 30-01-2022 | BR 81 | Erection of structural steel work is in progress (Vijay Shekhar Naudiyal) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
3. | 30-01-2022 | BR 81 | Erection of structural steel work is in progress (Vijay Shekhar Naudiyal) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
4. | 28-01-2022 | BR 81 | Pitching on slope laid over prepared filter media including boulder apron laid dry kharanja over embankment for base of DLC /dry lean concrete work in progress for Approach Road Abutment A1 and A2 side (Vijay Shekhar Naudiyal) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
5. | 28-01-2022 | BR81 | Erection of structural steel work in progress (Vijay Shekhar Naudiyal ) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
6. | 14-01-2022 | BR 81 bingsi chaini | Eraction work is on progress | Manoj sain QC | ` | ` | See Pic |
7. | 14-01-2022 | BR 81 bingsi chaini | Eraction work is on progress . | Manoj sain QC | ` | ` | See Pic |
8. | 10-01-2022 | BR 81 bingsi chaini | Work stopped due to rain. | Manoj sain QC | ` | ` | See Pic |
9. | 05-01-2022 | BR81 BINGSHI CHANI | Erection work is progress | Sandeep singh | ` | ` | See Pic |
10. | 05-01-2022 | BINGSHI CHANII | Erection work is progress at BR81 | Sandeep singh | ` | ` | See Pic |
11. | 20-12-2021 | BR 81 bingsi chaini | Eraction work is in progress | Sandeep kumar | unknown | unknown | See Pic |
12. | 20-12-2021 | BR81 | BR 81 A2 approach work in progress. | Sandeep kumar | unknown | unknown | See Pic |
13. | 09-12-2021 | BR81 | Erection work is progress at br 81 | Sandeep singh | ` | ` | See Pic |
14. | 09-12-2021 | BR81 | Erection work is progress | Sandeep singh | ` | ` | See Pic |
15. | 09-12-2021 | BR81 | Erection work is progress bingshi chanii | Sandeep singh | ` | ` | See Pic |
16. | 23-11-2021 | BINSGHI CHANNI BR81 | Erection work is progress | Sandeep singh | ` | ` | See Pic |
17. | 23-11-2021 | BR81 | RR 1:5 for approach road abutment A2 side is in progress (VIJAY SHEKHAR NAUDIYAL) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
18. | 23-11-2021 | BR81 | Erection of structural steel work in progress (vijay Shekhar Naudiyal) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
19. | 23-11-2021 | BR 81 | Erection of structural steel work in progress (VIJAY SHEKHAR NAUDIYAl) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
20. | 21-11-2021 | Bingsi chani bridge | Ericsson work is on progress. Bottom chord cross girder work is completed | AE Pawan Kumar | unknown | unknown | See Pic |
|
|