Package Profile Report

UDRP/AF/BR/81 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 648 Package Name: UDRP/AF/BR/81 Sanction Cost: 517.54  lakhs
District: Uttarkashi Block: Puraula Constituency: Purola Circle:
DEA: DEA Uttarkashi DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4123   Steel Truss Bridle Bridge over Kamal River at Bingsi Chaini (70.000 M.) (completed)
Procurement:
Package No.: 648        Package Name: UDRP/AF/BR/81        Tender Date: 20-11-2019        Current Status: Agreement signed        Achieved on Date: 10-06-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/81        Contractor Name: Border Builders       
Start Date: 01-07-2020        Intended Completion Date: 09-02-2022        Original End Date:  30-09-2021
Total Bond Cost: 51557276.96 (515.57 lakhs)        Variation Cost: 2597413.21 (25.97 lakhs)     Hence Total Bond Cost is   54154690.17 (541.55 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 10827180 for 420 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job46.671.00 Job1.00 Job10.1446.67
2.Foundation RHS1.00 Job20.281.00 Job1.00 Job4.4120.28
3.Foundation LHS1.00 Job20.281.00 Job1.00 Job4.4120.28
4.Abutment Superstructure RHS1.00 Job40.851.00 Job1.00 Job8.8740.85
5.Abutment Superstructure LHS1.00 Job40.851.00 Job1.00 Job8.8740.85
6.Fixing of chequered Plate/RCC Deck1.00 sqm34.381.00 sqm1.00 sqm7.4734.38
7.Steel Railing/crush barrier150.00 m8.47150.00 m150.00 m1.848.47
8.Approach Ramp /path 1.00 m21.931.00 m1.00 m4.7621.93
9.Protection Work204.00 Job20.44204.00 Job204.00 Job4.4420.44
10.Errection Work1.00 Job42.901.00 Job1.00 Job9.3242.90
11.Fabrication Work117.00 job161.30117.00 job117.00 job35.04161.30
12.Fixing Bearing/Slab Casting4.00 job2.004.00 job4.00 job0.432.00
Total Amount: 460.35 100   460.35
Remarks: No Remarks       Work Program Made On: 22-08-2020       Updation of work program on: 24-05-2022      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.04-February-202151.73  lakhs
2.30-March-202137.42  lakhs
3.22-July-2021145.71  lakhs
4.25-August-202160.66  lakhs
5.30-September-202161.05  lakhs
6.06-November-202113.39  lakhs
7.07-January-202220.28  lakhs
8.24-February-202272.15  lakhs
9.31-March-202233.26  lakhs
10.31-May-202245.26  lakhs
Total 540.91  lakhs
% Payment 99.88 %
Advance Amount:  38.78  lakhs        Recovered Amount:  38.78  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 921     No. of Test Done : 989      No. of Test Passed : 984      No. of Test Failed : 5   Test report of this package
Number of Pics Available on Web Repository: 198
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.31-01-2022BR 81Erection of structural is in progress and bolts tightening(vijay shekhar Naudiyal)????y ??????? ?????y?? ,?unknownunknown See Pic
2.30-01-2022BR 81Erection of structural steel work is in progress (Vijay Shekhar Naudiyal)????y ??????? ?????y?? ,?unknownunknown See Pic
3.30-01-2022BR 81Erection of structural steel work is in progress (Vijay Shekhar Naudiyal)????y ??????? ?????y?? ,?unknownunknown See Pic
4.28-01-2022BR 81Pitching on slope laid over prepared filter media including boulder apron laid dry kharanja over embankment for base of DLC /dry lean concrete work in progress for Approach Road Abutment A1 and A2 side (Vijay Shekhar Naudiyal)????y ??????? ?????y?? ,?unknownunknown See Pic
5.28-01-2022BR81Erection of structural steel work in progress (Vijay Shekhar Naudiyal )????y ??????? ?????y?? ,?unknownunknown See Pic
6.14-01-2022BR 81 bingsi chainiEraction work is on progressManoj sain QC ` ` See Pic
7.14-01-2022BR 81 bingsi chainiEraction work is on progress .Manoj sain QC ` ` See Pic
8.10-01-2022BR 81 bingsi chainiWork stopped due to rain.Manoj sain QC ` ` See Pic
9.05-01-2022BR81 BINGSHI CHANIErection work is progressSandeep singh ` ` See Pic
10.05-01-2022BINGSHI CHANIIErection work is progress at BR81Sandeep singh ` ` See Pic
11.20-12-2021BR 81 bingsi chainiEraction work is in progressSandeep kumarunknownunknown See Pic
12.20-12-2021BR81BR 81 A2 approach work in progress.Sandeep kumarunknownunknown See Pic
13.09-12-2021BR81Erection work is progress at br 81Sandeep singh ` ` See Pic
14.09-12-2021BR81Erection work is progressSandeep singh ` ` See Pic
15.09-12-2021BR81Erection work is progress bingshi chaniiSandeep singh ` ` See Pic
16.23-11-2021BINSGHI CHANNI BR81Erection work is progressSandeep singh ` ` See Pic
17.23-11-2021BR81RR 1:5 for approach road abutment A2 side is in progress (VIJAY SHEKHAR NAUDIYAL)????y ??????? ?????y?? ,?unknownunknown See Pic
18.23-11-2021BR81Erection of structural steel work in progress (vijay Shekhar Naudiyal)????y ??????? ?????y?? ,?unknownunknown See Pic
19.23-11-2021BR 81Erection of structural steel work in progress (VIJAY SHEKHAR NAUDIYAl)????y ??????? ?????y?? ,?unknownunknown See Pic
20.21-11-2021Bingsi chani bridgeEricsson work is on progress. Bottom chord cross girder work is completedAE Pawan Kumarunknownunknown See Pic