Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/65 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 645 Package Name: UDRP/AF/BR/65 Sanction Cost: 194.62  lakhs
District: Nainital Block: Bhimtal Constituency: Kaladhungi Circle:
DEA: DEA Nanital DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4057   Bridge on Basutiya Dogda Motor Road (Km-1) (32.000 M.) (completed)
Procurement:
Package No.: 645        Package Name: UDRP/AF/BR/65        Tender Date: 22-10-2019        Current Status: Agreement signed        Achieved on Date: 24-06-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/65        Contractor Name: Gaurav Builder       
Start Date: 10-09-2020        Intended Completion Date: 14-02-2022        Original End Date:  09-09-2021
Total Bond Cost: 20663226.08 (206.63 lakhs)        Variation Cost: -469579.27 (-4.7 lakhs)     Hence Total Bond Cost is   20193646.81 (201.94 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 3151260 for 305 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Env. Man & Moni Plan25.00 Job4.3325.00 Job25.00 Job2.14.33
2.Other Allied Works & Finishing Work 1.00 Job5.101.00 Job1.00 Job2.475.10
3.Foundation RHS1.00 Job9.721.00 Job1.00 Job4.79.72
4.Foundation LHS1.00 Job13.451.00 Job1.00 Job6.5113.45
5.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 1.00 no17.761.00 no1.00 no8.5917.76
6.Steel Railing/crush barrier78.00 m4.8978.00 m78.00 m2.374.89
7.Approach Ramp /path 100.00 m37.38120.00 m120.00 m18.0937.38
8.Protection Work1.00 Job15.351.00 Job1.00 Job7.4315.35
9.Errection Work1.00 Job31.461.00 Job1.00 Job15.2231.46
10.Fabrication Work1.00 job40.491.00 job1.00 job19.640.49
11.Abutment Substructure RHS1.00 Job9.061.00 Job1.00 Job4.399.06
12.Abutment Substructure LHS1.00 Job17.651.00 Job1.00 Job8.5417.65
Total Amount: 206.64 100   206.64
Remarks: No Remarks       Work Program Made On: 28-01-2021       Updation of work program on: 29-01-2022      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.14-January-202128.83  lakhs
2.30-March-202159.23  lakhs
3.31-May-202136.90  lakhs
4.19-August-202119.46  lakhs
5.06-November-202114.03  lakhs
6.19-February-202215.02  lakhs
7.05-May-202228.42  lakhs
Total 201.89  lakhs
% Payment 99.98 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 410     No. of Test Done : 435      No. of Test Passed : 415      No. of Test Failed : 20   Test report of this package
Number of Pics Available on Web Repository: 118
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.10-06-2022BR 6532 Metter Span Steel bridge CompletedSantosh Shukla ` ` See Pic
2.22-02-202200 + 160OGPC And seal coatSantosh Shukla ` ` See Pic
3.22-02-202200TO 160OGPC And Seal coat in progressSantosh Shukla ` ` See Pic
4.20-02-2022130 TO 160OGPC ONE Site CompletedSantosh Shukla ` ` See Pic
5.20-02-2022130 +160 A2 SiteOrOpen graded PC WorkSantosh Shukla ` ` See Pic
6.20-02-2022Ch 130 to 160Open Grade Premix Carpet Laying 20 mm thick (A2 Side)Chhatrapati Pant ` ` See Pic
7.20-02-2022Ch 130 to Ch 160Preparation for Laying Open Grade BC (A2 Side)Chhatrapati Pant ` ` See Pic
8.30-01-2022A1Concrete workRajesh Bhatt ` ` See Pic
9.29-01-202232 m span Steel truss BridgePainting work in progressChhatrapati Pant ` ` See Pic
10.27-01-2022BR 65Crash Barrier penting workSantosh Shukla ` ` See Pic
11.29-12-2021126.5 To 155 5Compection WBMSantosh shukla ` ` See Pic
12.25-12-2021Ch 0 to 87.5Backfilling Work @A1 sideChhatrapati Pant ` ` See Pic
13.14-12-2021B R 65R R masonry workSantosh shukla ` ` See Pic
14.11-12-2021A1 SiteRR masonry work in ProgressSantosh shukla ` ` See Pic
15.10-12-2021A1 Side approach RR Masonary work & BackfillingBackfilling & R R Masonary workChhatrapati Pant ` ` See Pic
16.09-12-2021Abutment A1Earth Work in ProgressSantosh shukla ` ` See Pic
17.09-12-2021A2 siteEarth work compectionSantosh shukla ` ` See Pic
18.09-12-2021A1 AbutmentEarth work at siteSantosh shukla ` ` See Pic
19.01-12-202100+ 100 chainageEarth work filling at sait work is ProgressSantosh shukla ` ` See Pic
20.30-11-202100+150MEarth work at siteSantosh shukla ` ` See Pic