Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/75 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 643 Package Name: UDRP/AF/BR/75 Sanction Cost: 549.91  lakhs
District: Nainital Block: Betalghat Constituency: Nainital Circle:
DEA: DEA Nanital DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4058   Ghughutiyadhar Betalghat Khairna Suyalwadi Odakhan Pasiyapani Bhateliya Mukteshwar MR Km 35 (60.000 M.) (in prorgress)
Procurement:
Package No.: 643        Package Name: UDRP/AF/BR/75        Tender Date: 11-11-2019        Current Status: Agreement signed        Achieved on Date: 15-09-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/75        Contractor Name: M/S.KGL Infrastructure       
Start Date: 29-10-2020        Intended Completion Date: 28-06-2022        Original End Date:  29-01-2022
Total Bond Cost: 57926186 (579.26 lakhs)        Variation Cost: 7678183.98 (76.78 lakhs)     Hence Total Bond Cost is   65604369.98 (656.04 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 11411422 for 394 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.R/Wall, B/ Wall Type Protection works140.00 m20.57140.00 m140.00 m4.420.57
2.Env. Man & Moni Plan28.00 Job2.8628.00 Job28.00 Job0.612.86
3.Other Allied Works & Finishing Work 1.00 Job3.981.00 Job1.00 Job0.853.98
4.Foundation RHS1.00 Job13.931.00 Job1.00 Job2.9813.93
5.Foundation LHS1.00 Job13.931.00 Job1.00 Job2.9813.93
6.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 1.00 no28.171.00 no1.00 no6.0328.17
7.Steel Railing/crush barrier120.00 m8.04120.00 m120.00 m1.728.04
8.Approach Ramp /path 100.00 m22.00100.00 m100.00 m4.7122.00
9.Errection Work190.86 Job113.89190.86 Job190.86 Job24.38113.89
10.Gabion work186.00 m14.42186.00 m186.00 m3.0914.42
11.PCC in Foundation29.90 cum2.3629.90 cum29.90 cum0.512.36
12.Excavation in soil6688.32 cum5.226688.32 cum6688.32 cum1.125.22
13.Fabrication Work184.80 job177.82184.80 job184.80 job38.07177.82
14.Abutment Substructure RHS1.00 Job16.321.00 Job1.00 Job3.4916.32
15.Abutment Substructure LHS1.00 Job16.321.00 Job1.00 Job3.4916.32
16.Fixing Bearing/Slab Casting6.00 job2.926.00 job6.00 job0.632.92
17.Back Wall/ Approach slab2.00 job1.332.00 job2.00 job0.281.33
18.Wearing Coat23.40 Cum3.0423.40 Cum23.40 Cum0.653.04
Total Amount: 467.12 100   467.12
Remarks: No Remarks       Work Program Made On: 26-01-2021       Updation of work program on: 20-12-2022      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.16-March-202168.26  lakhs
2.09-April-202127.59  lakhs
3.22-July-202160.40  lakhs
4.24-September-202153.04  lakhs
5.02-November-2021156.78  lakhs
6.30-December-202147.10  lakhs
7.10-March-202258.56  lakhs
8.31-March-202295.11  lakhs
9.31-May-202230.80  lakhs
10.31-August-202234.74  lakhs
11.25-November-202223.64  lakhs
Total 656.02  lakhs
% Payment 100 %
Advance Amount:  57.73  lakhs        Recovered Amount:  57.73  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Environment & Social Compliances(Package level):No Pending Issue
Environment & Social Compliances(Sub Project level):
Ghughutiyadhar Betalghat Khairna Suyalwadi Odakhan Pasiyapani Bhateliya Mukteshwar MR Km 35(4058) Land Owner Consent
Detailed report of this Package
Quality
No. of Test Required : 474     No. of Test Done : 519      No. of Test Passed : 485      No. of Test Failed : 34   Test report of this package
Number of Pics Available on Web Repository: 301
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-06-2022Ghiroli Betalghat NainitalDirt wall Reinforcement fixing work is in progress at BR-75Surendra Singh ` ` See Pic
2.23-06-2022Ghiroli Betalghat NainitalLatest photos at siteSurendra Singh ` ` See Pic
3.23-06-2022Ghiroli Betalghat NainitalLatest photos at siteSurendra Singh ` ` See Pic
4.22-06-2022Ghiroli betalghatApproach slab pcc laying is in progressShivam ` ` See Pic
5.22-06-2022Ghiroli betalghatPCC laying for approach slab At A-1 sideShivam ` ` See Pic
6.22-06-2022BR 75Crush berrier work in progressSantosh Shukla ` ` See Pic
7.20-06-2022Ghiroli BetalghatWearing coat laying is in progress BR-75Shivam ` ` See Pic
8.13-06-2022Ghiroli BetalghatCrash Barrier Curing work is in progress BR-75Shivam ` ` See Pic
9.13-06-2022Ghiroli BetalghatDirt wall concreting is in progress BR-75 A-1 sideShivam ` ` See Pic
10.09-06-2022Ghiroli Betalghat NainitalCrash Barrier Curing work is in progressSurendra Singh Bisht ` ` See Pic
11.09-06-2022Ghiroli Betalghat NainitalCrash Barrier concreting work is in progressSurendra Singh Bisht ` ` See Pic
12.09-06-2022Ghiroli Betalghat NainitalDeck slab Curing work is in progressSurendra Singh Bisht ` ` See Pic
13.05-06-2022Ghiroli Betalghat NainitalDeck slab Curing work is in progressSurendra Singh Bisht ` ` See Pic
14.04-06-2022Ghiroli Betalghat NainitalDeck slab Curing work is in progressSurendra Singh Bisht ` ` See Pic
15.03-06-2022Ghiroli Betalghat NainitalDeck slab Curing work is in progressSurendra Singh Bisht ` ` See Pic
16.03-06-2022Ghiroli BetalghatDeck slab Curing work is in progressShivam ` ` See Pic
17.01-06-2022BR 75Deck Slab M 35 Concrete workSantosh Shukla ` ` See Pic
18.01-06-2022BR 75Gradation fine. AggregateSantosh Shukla ` ` See Pic
19.01-06-2022BR 75Gradation curse Aggregate 20MMSantosh Shukla ` ` See Pic
20.01-06-2022BR 75Deck Slab Concrete workSantosh Shukla ` ` See Pic