Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/75 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 643 Package Name: UDRP/AF/BR/75 Sanction Cost: 549.91  lakhs
District: Nainital Block: Betalghat Constituency: Nainital Circle:
DEA: DEA Nanital DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4058   Ghughutiyadhar Betalghat Khairna Suyalwadi Odakhan Pasiyapani Bhateliya Mukteshwar MR Km 35 (60.000 M.) (in prorgress)
Procurement:
Package No.: 643        Package Name: UDRP/AF/BR/75        Tender Date: 11-11-2019        Current Status: Agreement signed        Achieved on Date: 15-09-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/75        Contractor Name: M/S.KGL Infrastructure       
Start Date: 29-10-2020        Intended Completion Date: 31-03-2022        Original End Date:  29-01-2022
Total Bond Cost: 57926186 (579.26 lakhs)        Variation Cost: 4351816.27 (43.52 lakhs)     Hence Total Bond Cost is   62278002.27 (622.78 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 11411422 for 394 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.R/Wall, B/ Wall Type Protection works140.00 m20.57140.00 m140.00 m4.2120.57
2.Env. Man & Moni Plan28.00 Job2.8628.00 Job12.00 Job0.251.23
3.Other Allied Works & Finishing Work 1.00 Job3.981.00 Job0.00 Job00.00
4.Foundation RHS1.00 Job13.931.00 Job1.00 Job2.8513.93
5.Foundation LHS1.00 Job13.931.00 Job1.00 Job2.8513.93
6.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 1.00 no28.171.00 no0.00 no00.00
7.Steel Railing/crush barrier120.00 m8.04120.00 m0.00 m00.00
8.Approach Ramp /path 100.00 m22.00100.00 m70.00 m3.1515.40
9.Errection Work184.80 Job113.89184.80 Job184.80 Job23.29113.89
10.Gabion work80.00 m36.6880.00 m0.00 m00.00
11.PCC in Foundation25.80 cum2.0425.80 cum0.00 cum00.00
12.Excavation in soil6688.32 cum5.226688.32 cum6688.32 cum1.075.22
13.Fabrication Work184.80 job177.82184.80 job184.80 job36.36177.82
14.Abutment Substructure RHS1.00 Job16.321.00 Job1.00 Job3.3416.32
15.Abutment Substructure LHS1.00 Job16.321.00 Job1.00 Job3.3416.32
16.Fixing Bearing/Slab Casting4.00 job2.324.00 job0.00 job00.00
17.Back Wall/ Approach slab1.00 job1.331.00 job0.00 job00.00
18.Wearing Coat28.35 Cum3.6928.35 Cum0.00 Cum00.00
Total Amount: 489.11 80.68   394.63
Remarks: No Remarks       Work Program Made On: 26-01-2021       Updation of work program on: 31-08-2021      
Work Program Status:Work Programme workable.
Financial Progress
SNo. Date Payment
1.16-March-202168.26  lakhs
2.09-April-202127.59  lakhs
3.22-July-202160.40  lakhs
4.24-September-202153.04  lakhs
5.02-November-2021156.78  lakhs
Total 366.07  lakhs
% Payment 58.78 %
Advance Amount:  57.73  lakhs        Recovered Amount:  57.73  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles
Environment & Social Compliances(Sub Project level):
Ghughutiyadhar Betalghat Khairna Suyalwadi Odakhan Pasiyapani Bhateliya Mukteshwar MR Km 35(4058) Land Owner Consent, Boot, Glove
Detailed report of this Package
Quality
No. of Test Required : 373     No. of Test Done : 418      No. of Test Passed : 384      No. of Test Failed : 34   Test report of this package
Number of Pics Available on Web Repository: 146
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.25-11-2021Ghiroli Betalghat NainitalLatest update on siteSurendra Singh Bisht ` ` See Pic
2.25-11-2021Ghiroli betalghatSite latest photographShivam ` ` See Pic
3.23-11-2021Ghiroli Betalghat NainitalLatest photo at siteSurendra Singh Bisht ` ` See Pic
4.23-11-2021Ghiroli Betalghat NainitalLatest photo at siteSurendra Singh Bisht ` ` See Pic
5.23-11-2021Ghiroli Betalghat NainitalLatest photo at siteSurendra Singh Bisht ` ` See Pic
6.23-11-2021Ghiroli Betalghat Nainital10 members reached at siteSurendra Singh Bisht ` ` See Pic
7.21-11-2021Ghiroli betalghatStructural members reached at site BR-75Shivam ` ` See Pic
8.17-11-2021Ghiroli Betalghat NainitalErection work preparation is in progressSurendra Singh Bisht ` ` See Pic
9.17-11-2021Ghiroli Betalghat NainitalSite visit by social and gender officer ( Swati bisht mam) with AE sirSurendra Singh Bisht ` ` See Pic
10.15-11-2021Ghiroli betalghatStructural members reached at siteShivam ` ` See Pic
11.26-10-2021Ghiroli Betalghat NainitalLatest photo at siteSurendra Singh Bisht ` ` See Pic
12.26-10-2021Tiwari gaon Betalghat NainitalLatest photo at siteSurendra Singh Bisht ` ` See Pic
13.26-10-2021Ghiroli Betalghat NainitalLatest photo at siteSurendra Singh Bisht ` ` See Pic
14.23-10-2021Ghiroli Betalghat NainitalLatest photo at siteSurendra Singh Bisht ` ` See Pic
15.23-10-2021Ghiroli Betalghat NainitalLatest photo at siteSurendra Singh Bisht ` ` See Pic
16.23-10-2021Ghiroli Betalghat NainitalLatest photo at siteSurendra Singh Bisht ` ` See Pic
17.23-10-2021Ghiroli Betalghat NainitalLatest photo at siteSurendra Singh Bisht ` ` See Pic
18.17-10-2021Ghiroli betalghatSlump test for cap concreting BR-75 A-2Shivam ` ` See Pic
19.17-10-2021Ghiroli betalghatAbutment cap concreting is in progress at LHS A-2 BR-75Shivam ` ` See Pic
20.14-10-2021Ghiroli betalghatVertical members reached at siteShivam ` ` See Pic