UDRP/AF/BR/75
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
643 |
Package Name: |
UDRP/AF/BR/75 |
Sanction Cost: |
549.91 lakhs |
District: |
Nainital |
Block: |
Betalghat |
Constituency: |
Nainital |
Circle: |
|
DEA: |
DEA Nanital |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4058 Ghughutiyadhar Betalghat Khairna Suyalwadi Odakhan Pasiyapani Bhateliya Mukteshwar MR Km 35 (60.000 M.) (in prorgress) |
|
Procurement: |
Package No.: 643
Package Name: UDRP/AF/BR/75
Tender Date: 11-11-2019
Current Status: Agreement signed
Achieved on Date: 15-09-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/75
Contractor Name: M/S.KGL Infrastructure
|
Start Date: 29-10-2020
Intended Completion Date: 28-06-2022
Original End Date: 29-01-2022
|
Total Bond Cost: 57926186 (579.26 lakhs)
Variation Cost: 7678183.98 (76.78 lakhs) Hence Total Bond Cost is 65604369.98 (656.04 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 11411422 for 394 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | R/Wall, B/ Wall Type Protection works | 140.00 m | 20.57 | 140.00 m | 140.00 m | 4.4 | 20.57 | 2. | Env. Man & Moni Plan | 28.00 Job | 2.86 | 28.00 Job | 28.00 Job | 0.61 | 2.86 | 3. | Other Allied Works & Finishing Work | 1.00 Job | 3.98 | 1.00 Job | 1.00 Job | 0.85 | 3.98 | 4. | Foundation RHS | 1.00 Job | 13.93 | 1.00 Job | 1.00 Job | 2.98 | 13.93 | 5. | Foundation LHS | 1.00 Job | 13.93 | 1.00 Job | 1.00 Job | 2.98 | 13.93 | 6. | Deck Cable laying, stretching and Fixing Transoms/Deck Slab | 1.00 no | 28.17 | 1.00 no | 1.00 no | 6.03 | 28.17 | 7. | Steel Railing/crush barrier | 120.00 m | 8.04 | 120.00 m | 120.00 m | 1.72 | 8.04 | 8. | Approach Ramp /path | 100.00 m | 22.00 | 100.00 m | 100.00 m | 4.71 | 22.00 | 9. | Errection Work | 190.86 Job | 113.89 | 190.86 Job | 190.86 Job | 24.38 | 113.89 | 10. | Gabion work | 186.00 m | 14.42 | 186.00 m | 186.00 m | 3.09 | 14.42 | 11. | PCC in Foundation | 29.90 cum | 2.36 | 29.90 cum | 29.90 cum | 0.51 | 2.36 | 12. | Excavation in soil | 6688.32 cum | 5.22 | 6688.32 cum | 6688.32 cum | 1.12 | 5.22 | 13. | Fabrication Work | 184.80 job | 177.82 | 184.80 job | 184.80 job | 38.07 | 177.82 | 14. | Abutment Substructure RHS | 1.00 Job | 16.32 | 1.00 Job | 1.00 Job | 3.49 | 16.32 | 15. | Abutment Substructure LHS | 1.00 Job | 16.32 | 1.00 Job | 1.00 Job | 3.49 | 16.32 | 16. | Fixing Bearing/Slab Casting | 6.00 job | 2.92 | 6.00 job | 6.00 job | 0.63 | 2.92 | 17. | Back Wall/ Approach slab | 2.00 job | 1.33 | 2.00 job | 2.00 job | 0.28 | 1.33 | 18. | Wearing Coat | 23.40 Cum | 3.04 | 23.40 Cum | 23.40 Cum | 0.65 | 3.04 |
Total Amount: |
467.12 |
|
100 |
467.12 |
|
Remarks:
No Remarks
Work Program Made On:
26-01-2021
Updation of work program on:
20-12-2022
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 16-March-2021 | 68.26 lakhs |
2. | 09-April-2021 | 27.59 lakhs |
3. | 22-July-2021 | 60.40 lakhs |
4. | 24-September-2021 | 53.04 lakhs |
5. | 02-November-2021 | 156.78 lakhs |
6. | 30-December-2021 | 47.10 lakhs |
7. | 10-March-2022 | 58.56 lakhs |
8. | 31-March-2022 | 95.11 lakhs |
9. | 31-May-2022 | 30.80 lakhs |
10. | 31-August-2022 | 34.74 lakhs |
11. | 25-November-2022 | 23.64 lakhs |
Total |
656.02 lakhs |
% Payment |
100 % |
|
Advance Amount: 57.73 lakhs
Recovered Amount: 57.73 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | No Pending Issue | Environment & Social Compliances(Sub Project level): | Ghughutiyadhar Betalghat Khairna Suyalwadi Odakhan Pasiyapani Bhateliya Mukteshwar MR Km 35(4058) | Land Owner Consent |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 301 |
No Notice issued. |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 23-06-2022 | Ghiroli Betalghat Nainital | Dirt wall Reinforcement fixing work is in progress at BR-75 | Surendra Singh | ` | ` | See Pic |
2. | 23-06-2022 | Ghiroli Betalghat Nainital | Latest photos at site | Surendra Singh | ` | ` | See Pic |
3. | 23-06-2022 | Ghiroli Betalghat Nainital | Latest photos at site | Surendra Singh | ` | ` | See Pic |
4. | 22-06-2022 | Ghiroli betalghat | Approach slab pcc laying is in progress | Shivam | ` | ` | See Pic |
5. | 22-06-2022 | Ghiroli betalghat | PCC laying for approach slab At A-1 side | Shivam | ` | ` | See Pic |
6. | 22-06-2022 | BR 75 | Crush berrier work in progress | Santosh Shukla | ` | ` | See Pic |
7. | 20-06-2022 | Ghiroli Betalghat | Wearing coat laying is in progress BR-75 | Shivam | ` | ` | See Pic |
8. | 13-06-2022 | Ghiroli Betalghat | Crash Barrier Curing work is in progress BR-75 | Shivam | ` | ` | See Pic |
9. | 13-06-2022 | Ghiroli Betalghat | Dirt wall concreting is in progress BR-75 A-1 side | Shivam | ` | ` | See Pic |
10. | 09-06-2022 | Ghiroli Betalghat Nainital | Crash Barrier Curing work is in progress | Surendra Singh Bisht | ` | ` | See Pic |
11. | 09-06-2022 | Ghiroli Betalghat Nainital | Crash Barrier concreting work is in progress | Surendra Singh Bisht | ` | ` | See Pic |
12. | 09-06-2022 | Ghiroli Betalghat Nainital | Deck slab Curing work is in progress | Surendra Singh Bisht | ` | ` | See Pic |
13. | 05-06-2022 | Ghiroli Betalghat Nainital | Deck slab Curing work is in progress | Surendra Singh Bisht | ` | ` | See Pic |
14. | 04-06-2022 | Ghiroli Betalghat Nainital | Deck slab Curing work is in progress | Surendra Singh Bisht | ` | ` | See Pic |
15. | 03-06-2022 | Ghiroli Betalghat Nainital | Deck slab Curing work is in progress | Surendra Singh Bisht | ` | ` | See Pic |
16. | 03-06-2022 | Ghiroli Betalghat | Deck slab Curing work is in progress | Shivam | ` | ` | See Pic |
17. | 01-06-2022 | BR 75 | Deck Slab M 35 Concrete work | Santosh Shukla | ` | ` | See Pic |
18. | 01-06-2022 | BR 75 | Gradation fine. Aggregate | Santosh Shukla | ` | ` | See Pic |
19. | 01-06-2022 | BR 75 | Gradation curse Aggregate 20MM | Santosh Shukla | ` | ` | See Pic |
20. | 01-06-2022 | BR 75 | Deck Slab Concrete work | Santosh Shukla | ` | ` | See Pic |
|
|