UDRP/AF/BR/62
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
641 |
Package Name: |
UDRP/AF/BR/62 |
Sanction Cost: |
696.66 lakhs |
District: |
Bageshwar |
Block: |
Bageshwar |
Constituency: |
Bageshwar |
Circle: |
|
DEA: |
DEA Bageshwar |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4112 70M Span steel Motor Bridge at Bageshwar Dafaut MR (70.000 M.) (in prorgress) |
|
Procurement: |
Package No.: 641
Package Name: UDRP/AF/BR/62
Tender Date: 17-06-2020
Current Status: Agreement signed
Achieved on Date: 12-11-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/62
Contractor Name: M/s Hillways Construction Company Pvt. Ltd.
|
Start Date: 10-12-2020
Intended Completion Date: 22-02-2023
Original End Date: 09-03-2022
|
Total Bond Cost: 70802432.96 (708.02 lakhs)
Variation Cost: -2702365.79 (-27.02 lakhs) Hence Total Bond Cost is 68100067.17 (681 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 9593671 for 271 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Env. Man & Moni Plan | 1.00 Job | 4.64 | 1.00 Job | 1.00 Job | 0.66 | 4.64 | 2. | Other Allied Works & Finishing Work | 1.00 Job | 91.51 | 1.00 Job | 1.00 Job | 12.93 | 91.51 | 3. | Foundation RHS | 1.00 Job | 13.19 | 1.00 Job | 1.00 Job | 1.86 | 13.19 | 4. | Foundation LHS | 1.00 Job | 13.19 | 1.00 Job | 1.00 Job | 1.86 | 13.19 | 5. | Abutment Superstructure RHS | 1.00 Job | 9.26 | 1.00 Job | 1.00 Job | 1.31 | 9.26 | 6. | Abutment Superstructure LHS | 1.00 Job | 9.26 | 1.00 Job | 1.00 Job | 1.31 | 9.26 | 7. | Fixing of chequered Plate/RCC Deck | 1.00 sqm | 14.93 | 1.00 sqm | 0.00 sqm | 0 | 0.00 | 8. | Steel Railing/crush barrier | 1.00 m | 8.15 | 1.00 m | 0.00 m | 0 | 0.00 | 9. | Approach Ramp /path | 1.00 m | 50.89 | 1.00 m | 1.00 m | 7.19 | 50.89 | 10. | Protection Work | 1.00 Job | 23.39 | 1.00 Job | 1.00 Job | 3.3 | 23.39 | 11. | Errection Work | 1.00 Job | 101.51 | 1.00 Job | 1.00 Job | 14.34 | 101.51 | 12. | Fabrication Work | 1.00 job | 328.20 | 1.00 job | 1.00 job | 46.36 | 328.20 | 13. | Abutment Substructure RHS | 1.00 Job | 19.95 | 1.00 Job | 1.00 Job | 2.82 | 19.95 | 14. | Abutment Substructure LHS | 1.00 Job | 19.95 | 1.00 Job | 1.00 Job | 2.82 | 19.95 |
Total Amount: |
708.02 |
|
96.74 |
684.94 |
|
Remarks:
No Remarks
Work Program Made On:
30-01-2021
Updation of work program on:
23-04-2022
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-March-2021 | 7.04 lakhs |
2. | 27-May-2021 | 35.29 lakhs |
3. | 30-June-2021 | 267.83 lakhs |
4. | 31-August-2021 | 65.55 lakhs |
5. | 27-April-2022 | 27.16 lakhs |
6. | 31-May-2022 | 86.49 lakhs |
7. | 15-June-2022 | 36.75 lakhs |
8. | 23-September-2022 | 34.25 lakhs |
9. | 28-December-2022 | 66.39 lakhs |
Total |
626.75 lakhs |
% Payment |
92.03 % |
|
Advance Amount: 124.87 lakhs
Recovered Amount: 124.87 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | PUC vehicles | Environment & Social Compliances(Sub Project level): | 70M Span steel Motor Bridge at Bageshwar Dafaut MR(4112) | EMP Land Owner Consent |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 190 |
No Notice issued. |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 04-06-2022 | Dafaut motor road at km-36 District - Bageshwar | Nut and bolt tighting work in a progress | Abhay Singh negi | unknown | unknown | See Pic |
2. | 25-04-2022 | 70 span steel truss bridge BR62 Bageshwar Dafaut m/ r km36 | "Open to communication" Road Open at km 29 for heavy vehicle | Mukesh Kumar | ` | ` | See Pic |
3. | 25-04-2022 | 70mtr span steel truss bridge BR62 Bageshwar Dafaut m/ r km36 | "Open to communication"Road Open at km.31 for heavy vehicle | Mukesh Kumar | ` | ` | See Pic |
4. | 25-04-2022 | 70mtr span steel truss bridge BR62 Bageshwar Dafaut m/ r km36 | "Open to communication" road open at km32 for heavy vehicle | Mukesh Kumar | ` | ` | See Pic |
5. | 25-04-2022 | 70mtr span steel truss bridge BR62 Bageshwar Dafaut m/r km36 | Fabricated member reached at site | Mukesh Kumar | ` | ` | See Pic |
6. | 25-04-2022 | 70mtr span steel truss bridge BR62 Bageshwar Dafaut m/ r km36 | Fabricated parts at site | Mukesh Kumar | ` | ` | See Pic |
7. | 25-04-2022 | 70mtr span steel truss bridge BR62 Bageshwar Dafaut m/r km36 | Fabricated member at site | Mukesh Kumar | ` | ` | See Pic |
8. | 25-04-2022 | 70mtr span steel truss bridge BR62 Bageshwar Dafaut m/r km36 | Fabricated member at site | Mukesh Kumar | ` | ` | See Pic |
9. | 25-04-2022 | 70mtr span steel truss bridge BR62 Bageshwar Dafaut m/r km36 | Fabricated member reached at site | Mukesh Kumar | ` | ` | See Pic |
10. | 25-04-2022 | 70mtr span steel truss bridge BR62 Bageshwar Dafaut m/r km36 | Slip clearance RHS abutment | Mukesh Kumar | ` | ` | See Pic |
11. | 04-02-2022 | Km-32 Bageshwar-dafaut motor road | SE sir visit on Bageshwar-dafaut motor road | Madhav Singh (SS) | ` | ` | See Pic |
12. | 17-01-2022 | BR 62 Bageshwar Dafaut steel truss bridge km36 | RHS Abutment land slide | Mukesh Kumar | ` | ` | See Pic |
13. | 17-01-2022 | 70 mtr span steel bridge at km 36 Bageshwar dafaut mr | LHS side abutment | Jagdish narayan meena | ` | ` | See Pic |
14. | 17-01-2022 | 70 mtr span steel bridge at km 36 Bageshwar dafaut mr | Land Slide at RHS side abutment | Jagdish narayan meena | ` | ` | See Pic |
15. | 01-12-2021 | Km-36 Bageshwar-dafaut motor road | Landslide on RHS side Abutment at Dafaut site BR-62 Km-36 Bageshwar | Madhav Singh | ` | ` | See Pic |
16. | 01-12-2021 | Km-36 Bageshwar-dafaut motor road | LHS side Abutment and Approach road At Dafaut site BR-62 Km-36 Bageshwar | Madhav Singh | ` | ` | See Pic |
17. | 22-10-2021 | Km-36 Bageshwar-dafaut motor road | Landslide on RHS side Abutment due to heavy rainfall at Dafaut site BR-62 Km-36 Bageshwar | Madhav Singh | ` | ` | See Pic |
18. | 22-10-2021 | Km-36 Bageshwar-dafaut motor road | Washout of LHS side Approach road HPS filling and Embankment Beck of RRM retaining wall due to heavy rainfall at Dafaut site BR-62 Km-36 Bageshwar | Madhav Singh | ` | ` | See Pic |
19. | 22-10-2021 | 70mtr span BR62 Bageshwar Dafaut steel truss bridge km36 | RHS Abutment heavy boulder/land slide during heavy rainfall | Mukesh Kumar | ` | ` | See Pic |
20. | 22-10-2021 | 70mtr span BR62 Bageshwar Dafaut steel truss bridge km36 | RHS Abutment land slide during heavy rainfall | Mukesh Kumar | ` | ` | See Pic |
|
|