Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/78 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 640 Package Name: UDRP/AF/BR/78 Sanction Cost: 555.58  lakhs
District: Pithoragarh Block: Didihat Constituency: Didihat Circle:
DEA: DEA Munsyari DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4097   Khoja (80.000 M.) (in prorgress)
Procurement:
Package No.: 640        Package Name: UDRP/AF/BR/78        Tender Date: 11-11-2019        Current Status: Agreement signed        Achieved on Date: 23-05-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/78        Contractor Name: M/S Aggarwal Brothers       
Start Date: 09-07-2020        Intended Completion Date: 30-09-2023        Original End Date:  08-10-2021
Total Bond Cost: 52547592.61 (525.48 lakhs)        Variation Cost: -884923.05 (-8.85 lakhs)     Hence Total Bond Cost is   51662669.56 (516.63 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 18812184 for 716 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job12.751.00 Job0.10 Job0.241.28
2.Foundation RHS1.00 Job13.601.00 Job1.00 Job2.5913.60
3.Foundation LHS1.00 Job13.601.00 Job1.00 Job2.5913.60
4.Abutment Superstructure RHS1.00 Job20.001.00 Job1.00 Job3.8120.00
5.Abutment Superstructure LHS1.00 Job20.001.00 Job1.00 Job3.8120.00
6.Fixing of chequered Plate/RCC Deck160.00 sqm9.94160.00 sqm0.00 sqm00.00
7.Steel Railing/crush barrier162.00 m2.65162.00 m0.00 m00.00
8.Approach Ramp /path 100.00 m46.93100.00 m100.00 m8.9346.93
9.Protection Work1.00 Job41.741.00 Job1.00 Job7.9441.74
10.Errection Work1.00 Job127.791.00 Job1.00 Job24.32127.79
11.Fabrication Work1.00 job216.461.00 job1.00 job41.19216.46
Total Amount: 525.46 95.42   501.4
Remarks: No Remarks       Work Program Made On: 18-11-2020       Updation of work program on: 22-05-2022      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.04-September-202125.40  lakhs
2.15-March-202241.86  lakhs
3.28-April-2022160.64  lakhs
4.13-May-202248.89  lakhs
5.31-May-202210.86  lakhs
6.21-October-20228.32  lakhs
7.09-January-202319.61  lakhs
8.10-February-202311.82  lakhs
9.31-March-20234.13  lakhs
10.31-August-2023134.73  lakhs
Total 466.26  lakhs
% Payment 90.25 %
Advance Amount:  22.20  lakhs        Recovered Amount:  22.20  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Environment & Social Compliances(Package level):No Pending Issue
Environment & Social Compliances(Sub Project level):
Khoja(4097) Sanitation Facility, water sprinkling
Detailed report of this Package
Quality
No. of Test Required : 224     No. of Test Done : 234      No. of Test Passed : 234      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 84
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.21-05-2022At yardGround erection checking.Neeraj Tewari ` ` See Pic
2.21-05-2022Abutment LHSRCC work of shaft & R/wallNeeraj Tewari ` ` See Pic
3.21-05-2022Abutment LHSRCC work of shaft.Neeraj Tewari ` ` See Pic
4.21-05-2022Abutment LHSRaft Reinforcement work in progress.Neeraj Tewari ` ` See Pic
5.21-05-2022Abutment RHSSite visit by CME sir & Environment expertNeeraj Tewari ` ` See Pic
6.21-05-2022At siteSite visit by CME sir & checking of registers.Neeraj Tewari ` ` See Pic
7.21-05-2022Abutment RHSRCC work of cap.Neeraj Tewari ` ` See Pic
8.21-05-2022Abutment RHSShuttering work final liftNeeraj Tewari ` ` See Pic
9.19-05-2022Khoja riverCamera fixed at siteMukul Saxena ` ` See Pic
10.19-05-2022Khoja riverCamera fixed at siteMukul saxena ` ` See Pic
11.19-05-2022Khoja riverCamera setup at khoja riverMukul saxena ` ` See Pic
12.28-03-2022Abutment A2RCC M35 pouring in 3rd lift of abutment A2 ,work in progress.Anuj shekhar ` ` See Pic
13.28-03-2022Abutment A2RCC M35 pouring in 2nd lift of abutment A2, work in progress.Anuj shekhar ` ` See Pic
14.28-03-2022Abutment A2RCC M35 Pouring in 2nd lift of abutment A2 ,work in progress.Anuj shekhar ` ` See Pic
15.28-03-2022Abutment A1HP stone filling behind abutment and R/Wall ,work in progress.Anuj shekhar ` ` See Pic
16.28-03-2022Abutment A1RR masonry work in approach road ,work in progress.Anuj shekhar ` ` See Pic
17.28-03-2022Abutment A2Slump test for 1st lift of abutment A2 ,Result found Ok.Anuj shekhar ` ` See Pic
18.28-03-2022Abutment A2RCC M35 Pouring in 1st lift of abutment A2 ,work in progress.Anuj shekhar ` ` See Pic
19.28-03-2022Abutment A2RCC M35 pouring in 1st lift of abutment A2,work in progress.Anuj shekhar ` ` See Pic
20.28-03-2022Khoja siteHealth camp at Khoja river BR-78Anuj shekhar ` ` See Pic