UDRP/AF/BR/78
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
640 |
Package Name: |
UDRP/AF/BR/78 |
Sanction Cost: |
555.58 lakhs |
District: |
Pithoragarh |
Block: |
Didihat |
Constituency: |
Didihat |
Circle: |
|
DEA: |
DEA Munsyari |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4097 Khoja (80.000 M.) (in prorgress) |
|
Procurement: |
Package No.: 640
Package Name: UDRP/AF/BR/78
Tender Date: 11-11-2019
Current Status: Agreement signed
Achieved on Date: 23-05-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/78
Contractor Name: M/S Aggarwal Brothers
|
Start Date: 09-07-2020
Intended Completion Date: 30-09-2023
Original End Date: 08-10-2021
|
Total Bond Cost: 52547592.61 (525.48 lakhs)
Variation Cost: -884923.05 (-8.85 lakhs) Hence Total Bond Cost is 51662669.56 (516.63 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 18812184 for 716 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 12.75 | 1.00 Job | 0.10 Job | 0.24 | 1.28 | 2. | Foundation RHS | 1.00 Job | 13.60 | 1.00 Job | 1.00 Job | 2.59 | 13.60 | 3. | Foundation LHS | 1.00 Job | 13.60 | 1.00 Job | 1.00 Job | 2.59 | 13.60 | 4. | Abutment Superstructure RHS | 1.00 Job | 20.00 | 1.00 Job | 1.00 Job | 3.81 | 20.00 | 5. | Abutment Superstructure LHS | 1.00 Job | 20.00 | 1.00 Job | 1.00 Job | 3.81 | 20.00 | 6. | Fixing of chequered Plate/RCC Deck | 160.00 sqm | 9.94 | 160.00 sqm | 0.00 sqm | 0 | 0.00 | 7. | Steel Railing/crush barrier | 162.00 m | 2.65 | 162.00 m | 0.00 m | 0 | 0.00 | 8. | Approach Ramp /path | 100.00 m | 46.93 | 100.00 m | 100.00 m | 8.93 | 46.93 | 9. | Protection Work | 1.00 Job | 41.74 | 1.00 Job | 1.00 Job | 7.94 | 41.74 | 10. | Errection Work | 1.00 Job | 127.79 | 1.00 Job | 1.00 Job | 24.32 | 127.79 | 11. | Fabrication Work | 1.00 job | 216.46 | 1.00 job | 1.00 job | 41.19 | 216.46 |
Total Amount: |
525.46 |
|
95.42 |
501.4 |
|
Remarks:
No Remarks
Work Program Made On:
18-11-2020
Updation of work program on:
22-05-2022
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 04-September-2021 | 25.40 lakhs |
2. | 15-March-2022 | 41.86 lakhs |
3. | 28-April-2022 | 160.64 lakhs |
4. | 13-May-2022 | 48.89 lakhs |
5. | 31-May-2022 | 10.86 lakhs |
6. | 21-October-2022 | 8.32 lakhs |
7. | 09-January-2023 | 19.61 lakhs |
8. | 10-February-2023 | 11.82 lakhs |
9. | 31-March-2023 | 4.13 lakhs |
10. | 31-August-2023 | 134.73 lakhs |
Total |
466.26 lakhs |
% Payment |
90.25 % |
|
Advance Amount: 22.20 lakhs
Recovered Amount: 22.20 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | No Pending Issue | Environment & Social Compliances(Sub Project level): | Khoja(4097) | Sanitation Facility, water sprinkling |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 84 |
No Notice issued. |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 21-05-2022 | At yard | Ground erection checking. | Neeraj Tewari | ` | ` | See Pic |
2. | 21-05-2022 | Abutment LHS | RCC work of shaft & R/wall | Neeraj Tewari | ` | ` | See Pic |
3. | 21-05-2022 | Abutment LHS | RCC work of shaft. | Neeraj Tewari | ` | ` | See Pic |
4. | 21-05-2022 | Abutment LHS | Raft Reinforcement work in progress. | Neeraj Tewari | ` | ` | See Pic |
5. | 21-05-2022 | Abutment RHS | Site visit by CME sir & Environment expert | Neeraj Tewari | ` | ` | See Pic |
6. | 21-05-2022 | At site | Site visit by CME sir & checking of registers. | Neeraj Tewari | ` | ` | See Pic |
7. | 21-05-2022 | Abutment RHS | RCC work of cap. | Neeraj Tewari | ` | ` | See Pic |
8. | 21-05-2022 | Abutment RHS | Shuttering work final lift | Neeraj Tewari | ` | ` | See Pic |
9. | 19-05-2022 | Khoja river | Camera fixed at site | Mukul Saxena | ` | ` | See Pic |
10. | 19-05-2022 | Khoja river | Camera fixed at site | Mukul saxena | ` | ` | See Pic |
11. | 19-05-2022 | Khoja river | Camera setup at khoja river | Mukul saxena | ` | ` | See Pic |
12. | 28-03-2022 | Abutment A2 | RCC M35 pouring in 3rd lift of abutment A2 ,work in progress. | Anuj shekhar | ` | ` | See Pic |
13. | 28-03-2022 | Abutment A2 | RCC M35 pouring in 2nd lift of abutment A2, work in progress. | Anuj shekhar | ` | ` | See Pic |
14. | 28-03-2022 | Abutment A2 | RCC M35 Pouring in 2nd lift of abutment A2 ,work in progress. | Anuj shekhar | ` | ` | See Pic |
15. | 28-03-2022 | Abutment A1 | HP stone filling behind abutment and R/Wall ,work in progress. | Anuj shekhar | ` | ` | See Pic |
16. | 28-03-2022 | Abutment A1 | RR masonry work in approach road ,work in progress. | Anuj shekhar | ` | ` | See Pic |
17. | 28-03-2022 | Abutment A2 | Slump test for 1st lift of abutment A2 ,Result found Ok. | Anuj shekhar | ` | ` | See Pic |
18. | 28-03-2022 | Abutment A2 | RCC M35 Pouring in 1st lift of abutment A2 ,work in progress. | Anuj shekhar | ` | ` | See Pic |
19. | 28-03-2022 | Abutment A2 | RCC M35 pouring in 1st lift of abutment A2,work in progress. | Anuj shekhar | ` | ` | See Pic |
20. | 28-03-2022 | Khoja site | Health camp at Khoja river BR-78 | Anuj shekhar | ` | ` | See Pic |
|
|