UDRP/AF/BR/72
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
639 |
Package Name: |
UDRP/AF/BR/72 |
Sanction Cost: |
565.31 lakhs |
District: |
Uttarkashi |
Block: |
Bhatwari |
Constituency: |
Gangotri |
Circle: |
|
DEA: |
DEA Uttarkashi |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4083 Bridge Over Bhagirathi River at Chamkot Village (84.000 M.) (in prorgress) |
|
Procurement: |
Package No.: 639
Package Name: UDRP/AF/BR/72
Tender Date: 24-10-2019
Current Status: Agreement signed
Achieved on Date: 07-02-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/72
Contractor Name: Kailash Hillways Engineering Associates
|
Start Date: 15-02-2020
Intended Completion Date: 03-01-2023
Original End Date: 14-08-2021
|
Total Bond Cost: 54743128.72 (547.43 lakhs)
Variation Cost: -2168556.31 (-21.69 lakhs) Hence Total Bond Cost is 52574572.41 (525.75 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 19488864 for 712 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | R/Wall, B/ Wall Type Protection works | 1.00 m | 21.12 | 1.00 m | 1.00 m | 4.32 | 21.12 | 2. | Other Allied Works & Finishing Work | 1.00 Job | 4.61 | 1.00 Job | 0.65 Job | 0.61 | 3.00 | 3. | Foundation RHS | 1.00 Job | 6.86 | 1.00 Job | 1.00 Job | 1.4 | 6.86 | 4. | Foundation LHS | 1.00 Job | 6.86 | 1.00 Job | 1.00 Job | 1.4 | 6.86 | 5. | Abutment Superstructure RHS | 1.00 Job | 23.27 | 1.00 Job | 1.00 Job | 4.76 | 23.27 | 6. | Abutment Superstructure LHS | 1.00 Job | 23.27 | 1.00 Job | 1.00 Job | 4.76 | 23.27 | 7. | Steel Railing/crush barrier | 170.00 m | 6.40 | 170.00 m | 0.00 m | 0 | 0.00 | 8. | Approach Ramp /path | 8400.00 m | 17.69 | 8400.00 m | 8400.00 m | 3.62 | 17.69 | 9. | Protection Work | 1.00 Job | 15.88 | 1.00 Job | 1.00 Job | 3.25 | 15.88 | 10. | Errection Work | 1.00 Job | 59.25 | 1.00 Job | 0.00 Job | 0 | 0.00 | 11. | Gabion work | 300.00 m | 23.40 | 300.00 m | 300.00 m | 4.79 | 23.40 | 12. | Fabrication Work | 211.60 job | 277.21 | 211.60 job | 211.60 job | 56.72 | 277.21 | 13. | Fixing Bearing/Slab Casting | 1.00 job | 1.88 | 1.00 job | 0.00 job | 0 | 0.00 | 14. | Back Wall/ Approach slab | 1.00 job | 1.09 | 1.00 job | 0.00 job | 0 | 0.00 |
Total Amount: |
488.79 |
|
85.63 |
418.56 |
|
Remarks:
No Remarks
Work Program Made On:
26-06-2020
Updation of work program on:
30-05-2022
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 11-November-2020 | 34.80 lakhs |
2. | 08-January-2021 | 9.92 lakhs |
3. | 10-June-2021 | 41.86 lakhs |
4. | 06-November-2021 | 25.27 lakhs |
5. | 07-January-2022 | 103.47 lakhs |
6. | 20-January-2022 | 62.08 lakhs |
7. | 10-May-2022 | 61.82 lakhs |
8. | 20-October-2022 | 15.41 lakhs |
9. | 29-December-2022 | 0.83 lakhs |
10. | 04-March-2023 | 105.12 lakhs |
11. | 08-May-2023 | 75.17 lakhs |
Total |
535.75 lakhs |
% Payment |
101.9 % |
|
Advance Amount: 17.78 lakhs
Recovered Amount: 17.78 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | No Pending Issue | Environment & Social Compliances(Sub Project level): | Bridge Over Bhagirathi River at Chamkot Village(4083) | EMP, Query |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 100 |
No Notice issued. |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 06-05-2022 | Chamkot | Protection work in progress at LHS side | Rajesh Uniyal | ` | ` | See Pic |
2. | 06-05-2022 | Chamkot | Steel structure Erection work in progress | Rajesh Uniyal | ` | ` | See Pic |
3. | 16-11-2021 | Chamkot,uttarkashi | Concrete sampling work on progress. Concrete grade .M/35. | Niraj pathak | unknown | unknown | See Pic |
4. | 09-09-2021 | BR/72 | Surface water sampling. | Niraj pathak | unknown | unknown | See Pic |
5. | 08-09-2021 | KM-1 | Soil testing | Rajesh Uniyal | ` | ` | See Pic |
6. | 08-09-2021 | BR/72 | Noise monitoring test At R.H.S side at chamkot site | Rajesh Uniyal | ` | ` | See Pic |
7. | 08-09-2021 | BR/72 | Soil sampling. | Niraj pathak | unknown | unknown | See Pic |
8. | 08-09-2021 | BR/72 | Noise monitoring. | Niraj pathak | unknown | unknown | See Pic |
9. | 30-08-2021 | BR/72 | Ambient air monitoring. | Niraj pathak | unknown | unknown | See Pic |
10. | 30-08-2021 | BR/72 | Noise monitoring. | Niraj pathak | unknown | unknown | See Pic |
11. | 30-08-2021 | Chamkot,uttarkashi | Concrete sampling work on progress. Concrete grade .M/35. | Niraj pathak | unknown | unknown | See Pic |
12. | 24-08-2021 | Chamkot,uttarkashi | Concrete sampling work on progress. Concrete grade .M/35. | Niraj pathak | unknown | unknown | See Pic |
13. | 08-08-2021 | BR/72 | A2,LHS, cap concrete sampling done.concrete grade M35. | Niraj pathak | unknown | unknown | See Pic |
14. | 08-08-2021 | BR/72 | A2,LHS, cap concrete slump test on progress, concrete grade M35. | Niraj pathak | unknown | unknown | See Pic |
15. | 08-08-2021 | BR/72 | A2 LHS,cap concrete slump test on progress. | Niraj pathak | unknown | unknown | See Pic |
16. | 08-08-2021 | BR/72 | A2LHS,cap concrete sampling work on progress. Concrete grade M35. | Niraj pathak | unknown | unknown | See Pic |
17. | 08-08-2021 | KM-1 | L.H.S side Cap concerting Slump test on progress | Rajesh Uniyal | ` | ` | See Pic |
18. | 08-08-2021 | KM-1 | L.H.S Side cap concerting sampling work on progress | Rajesh Uniyal | ` | ` | See Pic |
19. | 08-08-2021 | KM-1 | L.H.S side Cap concerting work in progress | Rajesh Uniyal | ` | ` | See Pic |
20. | 15-06-2021 | BR/72 | A2,LHS,wall 8th lift concrete mix slump test on progress. Concrete grade M35. | Niraj pathak | unknown | unknown | See Pic |
|
|