Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/72 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 639 Package Name: UDRP/AF/BR/72 Sanction Cost: 565.31  lakhs
District: Uttarkashi Block: Bhatwari Constituency: Gangotri Circle:
DEA: DEA Uttarkashi DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4083   Bridge Over Bhagirathi River at Chamkot Village (84.000 M.) (in prorgress)
Procurement:
Package No.: 639        Package Name: UDRP/AF/BR/72        Tender Date: 24-10-2019        Current Status: Agreement signed        Achieved on Date: 07-02-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/72        Contractor Name: Kailash Hillways Engineering Associates       
Start Date: 15-02-2020        Intended Completion Date: 03-01-2023        Original End Date:  14-08-2021
Total Bond Cost: 54743128.72 (547.43 lakhs)        Variation Cost: -2168556.31 (-21.69 lakhs)     Hence Total Bond Cost is   52574572.41 (525.75 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 19488864 for 712 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.R/Wall, B/ Wall Type Protection works1.00 m21.121.00 m1.00 m4.3221.12
2.Other Allied Works & Finishing Work 1.00 Job4.611.00 Job0.65 Job0.613.00
3.Foundation RHS1.00 Job6.861.00 Job1.00 Job1.46.86
4.Foundation LHS1.00 Job6.861.00 Job1.00 Job1.46.86
5.Abutment Superstructure RHS1.00 Job23.271.00 Job1.00 Job4.7623.27
6.Abutment Superstructure LHS1.00 Job23.271.00 Job1.00 Job4.7623.27
7.Steel Railing/crush barrier170.00 m6.40170.00 m0.00 m00.00
8.Approach Ramp /path 8400.00 m17.698400.00 m8400.00 m3.6217.69
9.Protection Work1.00 Job15.881.00 Job1.00 Job3.2515.88
10.Errection Work1.00 Job59.251.00 Job0.00 Job00.00
11.Gabion work300.00 m23.40300.00 m300.00 m4.7923.40
12.Fabrication Work211.60 job277.21211.60 job211.60 job56.72277.21
13.Fixing Bearing/Slab Casting1.00 job1.881.00 job0.00 job00.00
14.Back Wall/ Approach slab1.00 job1.091.00 job0.00 job00.00
Total Amount: 488.79 85.63   418.56
Remarks: No Remarks       Work Program Made On: 26-06-2020       Updation of work program on: 30-05-2022      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.11-November-202034.80  lakhs
2.08-January-20219.92  lakhs
3.10-June-202141.86  lakhs
4.06-November-202125.27  lakhs
5.07-January-2022103.47  lakhs
6.20-January-202262.08  lakhs
7.10-May-202261.82  lakhs
8.20-October-202215.41  lakhs
9.29-December-20220.83  lakhs
10.04-March-2023105.12  lakhs
11.08-May-202375.17  lakhs
Total 535.75  lakhs
% Payment 101.9 %
Advance Amount:  17.78  lakhs        Recovered Amount:  17.78  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):No Pending Issue
Environment & Social Compliances(Sub Project level):
Bridge Over Bhagirathi River at Chamkot Village(4083)EMP, Query
Detailed report of this Package
Quality
No. of Test Required : 335     No. of Test Done : 409      No. of Test Passed : 397      No. of Test Failed : 12   Test report of this package
Number of Pics Available on Web Repository: 100
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.06-05-2022ChamkotProtection work in progress at LHS sideRajesh Uniyal ` ` See Pic
2.06-05-2022ChamkotSteel structure Erection work in progressRajesh Uniyal ` ` See Pic
3.16-11-2021Chamkot,uttarkashiConcrete sampling work on progress. Concrete grade .M/35.Niraj pathakunknownunknown See Pic
4.09-09-2021BR/72Surface water sampling.Niraj pathakunknownunknown See Pic
5.08-09-2021KM-1Soil testingRajesh Uniyal ` ` See Pic
6.08-09-2021BR/72Noise monitoring test At R.H.S side at chamkot siteRajesh Uniyal ` ` See Pic
7.08-09-2021BR/72Soil sampling.Niraj pathakunknownunknown See Pic
8.08-09-2021BR/72Noise monitoring.Niraj pathakunknownunknown See Pic
9.30-08-2021BR/72Ambient air monitoring.Niraj pathakunknownunknown See Pic
10.30-08-2021BR/72Noise monitoring.Niraj pathakunknownunknown See Pic
11.30-08-2021Chamkot,uttarkashiConcrete sampling work on progress. Concrete grade .M/35.Niraj pathakunknownunknown See Pic
12.24-08-2021Chamkot,uttarkashiConcrete sampling work on progress. Concrete grade .M/35.Niraj pathakunknownunknown See Pic
13.08-08-2021BR/72A2,LHS, cap concrete sampling done.concrete grade M35.Niraj pathakunknownunknown See Pic
14.08-08-2021BR/72A2,LHS, cap concrete slump test on progress, concrete grade M35.Niraj pathakunknownunknown See Pic
15.08-08-2021BR/72A2 LHS,cap concrete slump test on progress.Niraj pathakunknownunknown See Pic
16.08-08-2021BR/72A2LHS,cap concrete sampling work on progress. Concrete grade M35.Niraj pathakunknownunknown See Pic
17.08-08-2021KM-1L.H.S side Cap concerting Slump test on progressRajesh Uniyal ` ` See Pic
18.08-08-2021KM-1L.H.S Side cap concerting sampling work on progressRajesh Uniyal ` ` See Pic
19.08-08-2021KM-1L.H.S side Cap concerting work in progressRajesh Uniyal ` ` See Pic
20.15-06-2021BR/72A2,LHS,wall 8th lift concrete mix slump test on progress. Concrete grade M35.Niraj pathakunknownunknown See Pic