Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/45 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 636 Package Name: UDRP/AF/BR/45 Sanction Cost: 360.74  lakhs
District: Rudraprayag Block: Jakholi Constituency: Kedarnath Circle:
DEA: DEA Guptkashi DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4065   Vijaynagar Taila MR (36.000 M.) (in prorgress)
Procurement:
Package No.: 636        Package Name: UDRP/AF/BR/45        Tender Date: 11-11-2019        Current Status: Agreement signed        Achieved on Date: 16-10-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/45        Contractor Name: M/s Harpal singh Kishore singh       
Start Date: 10-11-2020        Intended Completion Date: 22-06-2022        Original End Date:  10-02-2022
Total Bond Cost: 28562466.08 (285.62 lakhs)        Variation Cost: -951797.11 (-9.52 lakhs)     Hence Total Bond Cost is   27610668.97 (276.11 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 5812367 for 407 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Env. Man & Moni Plan1.00 Job3.561.00 Job1.00 Job1.173.56
2.Other Allied Works & Finishing Work 1.00 Job3.041.00 Job1.00 Job13.04
3.Foundation RHS1.00 Job15.831.00 Job1.00 Job5.2215.83
4.Foundation LHS1.00 Job15.831.00 Job1.00 Job5.2215.83
5.Abutment Superstructure RHS1.00 Job8.751.00 Job1.00 Job2.888.75
6.Abutment Superstructure LHS1.00 Job8.751.00 Job1.00 Job2.888.75
7.Steel Railing/crush barrier72.00 m4.3672.00 m72.00 m1.444.36
8.Approach Ramp /path 100.00 m48.79100.00 m0.30 m0.050.15
9.Protection Work1.00 Job54.581.00 Job0.80 Job14.3843.66
10.Errection Work1.00 Job20.071.00 Job1.00 Job6.6120.07
11.Fabrication Work1.00 job53.571.00 job1.00 job17.6553.57
12.Abutment Substructure RHS1.00 Job32.271.00 Job1.00 Job10.6332.27
13.Abutment Substructure LHS1.00 Job32.271.00 Job1.00 Job10.6332.27
14.Fixing Bearing/Slab Casting1.00 job1.861.00 job1.00 job0.611.86
Total Amount: 303.53 80.38   243.97
Remarks: No Remarks       Work Program Made On: 22-01-2021       Updation of work program on: 03-05-2022      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.26-March-202120.84  lakhs
2.31-May-202120.62  lakhs
3.01-July-20219.94  lakhs
4.31-July-202112.96  lakhs
5.04-September-202113.73  lakhs
6.30-October-202139.09  lakhs
7.30-November-202128.50  lakhs
8.02-February-202216.68  lakhs
9.26-February-202229.72  lakhs
10.31-March-202226.24  lakhs
11.31-May-202214.55  lakhs
Total 232.87  lakhs
% Payment 84.34 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Environment & Social Compliances(Package level):No Pending Issue
Environment & Social Compliances(Sub Project level):
Vijaynagar Taila MR(4065)EMP, water sprinkling
Detailed report of this Package
Quality
No. of Test Required : 1452     No. of Test Done : 1452      No. of Test Passed : 1450      No. of Test Failed : 2   Test report of this package
Number of Pics Available on Web Repository: 84
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.27-05-2022Br 45 vijaynagar tellaWearing coat M 30 Br 45Arun kumar ` ` See Pic
2.26-04-2022Vijaynagar Taila Rudraprayag Br/45World Bank Team visit at siteEr. Vipin Tomar ` ` See Pic
3.26-04-2022Vijaynagar Taila Bridge Br/45 RudraprayagSlab Cube testing for 14 days.Er.Vipin Tomar, AE ` ` See Pic
4.26-04-2022Vijayanagar Taila Br/45, RudraprayagReinforcement work in progressEr. Vipin Tomar , AE ` ` See Pic
5.22-02-2022Vijaynagar tailaM35 concrete work in progressAnkit kumar ` ` See Pic
6.17-02-2022Vijaynagar Taila Rudraprayag, Br/45Cube casting of Return wall for M35Er.Vipin Tomar, AE ` ` See Pic
7.17-02-2022Vijaynagar Taila Rudraprayag, Br/45Concreting work in progress.Er. Vipin Tomar, AE ` ` See Pic
8.17-02-2022Vijaynagar Taila Rudraprayag Br/45Retaining wall concreting at A2 sideEr. Vipin Tomar, AE ` ` See Pic
9.17-02-2022Vijaynagar Taila Rudraprayag Br/45Measurement of Reinforcement of retaining wall of A2 Side.Er. Vipin Tomar, AE ` ` See Pic
10.17-02-2022Vijaynagar Taila Bridge (Br/45) RudraprayagThird-party Test of M40 Trail MixEr. VIPIN TOMAR, AE ` ` See Pic
11.28-01-2022Vijaynagar Taila Bridge Br/45, RudraprayagTrail Mix Cube test of M40 for pedestal Conreting.ER. VIPIN TOMAR ` ` See Pic
12.28-01-2022Vijaynagar Taila Bridge Br/45, RudraprayagCive testing of M35Er. Vipin Tomar, AE ` ` See Pic
13.28-01-2022BR45Trial cube testing for M40, Found satisfactoryRohit Kumar Dubey ` ` See Pic
14.28-01-2022BR45Cube strength checking for RCC protection keyRohit Kumar Dubey ` ` See Pic
15.28-01-2022Vijaynagar Taila Rudraprayag Br/45Pedestal Concreting work in progressEr. Vipin Tomar , AE ` ` See Pic
16.28-01-2022Vijaynagar Taila Rudraprayag Br/45Erection work in progress. Check auto level.Er. Vipin Tomar, AE ` ` See Pic
17.27-01-2022Vijay nagar tailla bridgeGobion work progressAnkit uniyal ` ` See Pic
18.27-01-2022Vijay nagar tailla bridgeBucket with sandAnkit uniyal ` ` See Pic
19.27-01-2022Vijay nagar tailla bridgeFire extinguisherAnkit uniyal ` ` See Pic
20.27-01-2022Vijay nagar tailla bridgeToiletAnkit uniyal ` ` See Pic