UDRP/AF/BR/63
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
632 |
Package Name: |
UDRP/AF/BR/63 |
Sanction Cost: |
218.42 lakhs |
District: |
Tehri |
Block: |
Narendra Nagar |
Constituency: |
Narendra Nagar |
Circle: |
|
DEA: |
DEA Tehri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4061 Bridge on KM-7 of Agrakhal Kusraila MR (30.000 M.) (completed) |
|
Procurement: |
Package No.: 632
Package Name: UDRP/AF/BR/63
Tender Date: 11-10-2019
Current Status: Agreement signed
Achieved on Date: 12-02-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/63
Contractor Name: M/S Beer Chandra Ramola
|
Start Date: 20-02-2020
Intended Completion Date: 27-10-2021
Original End Date: 19-02-2021
|
Total Bond Cost: 20571232.64 (205.71 lakhs)
Variation Cost: -2393377.63 (-23.93 lakhs) Hence Total Bond Cost is 18177855.01 (181.78 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 4278976 for 416 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 7.78 | 1.00 Job | 1.00 Job | 3.78 | 7.78 | 2. | Foundation RHS | 1.00 Job | 6.32 | 1.00 Job | 1.00 Job | 3.07 | 6.32 | 3. | Foundation LHS | 1.00 Job | 6.32 | 1.00 Job | 1.00 Job | 3.07 | 6.32 | 4. | Steel Railing/crush barrier | 110.00 m | 3.33 | 110.00 m | 110.00 m | 1.62 | 3.33 | 5. | Approach Ramp /path | 95.00 m | 45.31 | 95.00 m | 95.00 m | 22.03 | 45.31 | 6. | Protection Work | 1.00 Job | 20.65 | 1.00 Job | 1.00 Job | 10.04 | 20.65 | 7. | Errection Work | 1.00 Job | 20.91 | 1.00 Job | 1.00 Job | 10.16 | 20.91 | 8. | Fabrication Work | 1.00 job | 49.82 | 1.00 job | 1.00 job | 24.22 | 49.82 | 9. | Abutment Substructure RHS | 1.00 Job | 15.98 | 1.00 Job | 1.00 Job | 7.77 | 15.98 | 10. | Abutment Substructure LHS | 1.00 Job | 15.98 | 1.00 Job | 1.00 Job | 7.77 | 15.98 | 11. | Fixing Bearing/Slab Casting | 1.00 job | 11.80 | 1.00 job | 1.00 job | 5.74 | 11.80 | 12. | Wearing Coat | 12.31 Cum | 1.52 | 12.31 Cum | 12.31 Cum | 0.74 | 1.52 |
Total Amount: |
205.72 |
|
100 |
205.72 |
|
Remarks:
No Remarks
Work Program Made On:
19-02-2021
Updation of work program on:
21-09-2021
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-March-2021 | 99.77 lakhs |
2. | 28-June-2021 | 36.44 lakhs |
3. | 21-September-2021 | 15.77 lakhs |
4. | 21-March-2022 | 29.79 lakhs |
Total |
181.77 lakhs |
% Payment |
100 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 75 |
No Notice issued. |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 06-04-2022 | Agrakhal Kushrela km 7 | Bridge work Completed | Sudhir Kumar | ` | ` | See Pic |
2. | 21-03-2022 | Agrakhal-Kusraila KM-07 | Approach road LHS to RHS | Suresh Prasad | ` | ` | See Pic |
3. | 21-03-2022 | Agrakhal-Kusraila KM-07 | Agrakhal-Kusraila KM-07 bridge LHS SIDE | Suresh Prasad | ` | ` | See Pic |
4. | 21-03-2022 | Agrakhal-Kusraila KM-07 | Up stream side of bridge | Suresh Prasad | ` | ` | See Pic |
5. | 21-03-2022 | Agrakhal-Kusraila KM-07 | Down stream side of bridge | Suresh Prasad | ` | ` | See Pic |
6. | 21-03-2022 | Agrakhal-Kusraila KM-07 | Agrakhal-Kusraila KM-07 RHS SIDE | Suresh Prasad | ` | ` | See Pic |
7. | 24-07-2021 | Agrakhal kusherela km 7 | Crush Barrier M -40 Casting work on progress | Vikash Baboo | unknown | unknown | See Pic |
8. | 10-07-2021 | Agrakhal Kushrela km 7 | Slab Casting | Sudhir Kumar | ` | ` | See Pic |
9. | 07-07-2021 | Agrakhal Km-07 | Deck Slab casting | Vikas Verma | unknown | unknown | See Pic |
10. | 06-07-2021 | Agrakhal-Kusraila KM-07 | Agrakhal-Kusraila KM-07 Deck Slab RCC M-35 Casting Done | Suresh Prasad | ` | ` | See Pic |
11. | 06-07-2021 | Agrakhal kusherela km 7 | Agrakhal kusherela km 7 Deck Slab Casting completed M-35 | Vikash Baboo | unknown | unknown | See Pic |
12. | 03-07-2021 | Agrakhal kusrila Km-7 | Deck Slab steel bar binding work | Vikas Verma | unknown | unknown | See Pic |
13. | 17-06-2021 | Agrakhal kusherela km 7 | AB1 Side Shaft & Retaining wall1st Lift Casting | Vikash Baboo | unknown | unknown | See Pic |
14. | 16-06-2021 | KM-7 Agrakhal Kushraila | Bar Binding work in progress Deck Slab | Vikas Verma | unknown | unknown | See Pic |
15. | 12-06-2021 | Agrakhal Kushrela km 7 | Bearing Testing | Sudhir Kumar | ` | ` | See Pic |
16. | 25-05-2021 | Chamasari Majhada km 2 | Concrete work in progress Return Wall | Sudhir Kumar | ` | ` | See Pic |
17. | 25-05-2021 | Agrakhal Kushrela km 7 | Errection work in progress | Sudhir Kumar | ` | ` | See Pic |
18. | 15-05-2021 | Agrakhal Kushrela km 7 | Errection work in progress | Sudhir Kumar | ` | ` | See Pic |
19. | 06-05-2021 | Agrakhal Kushrela km 7 | Errection work in progress | Sudhir Kumar | ` | ` | See Pic |
20. | 06-05-2021 | Agrakhal Kushrela km 7 | Errection work in progress | Sudhir Kumar | ` | ` | See Pic |
|
|