UDRP/AF/BR/64
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
631 |
Package Name: |
UDRP/AF/BR/64 |
Sanction Cost: |
523.10 lakhs |
District: |
Uttarkashi |
Block: |
Naugaon |
Constituency: |
Purola |
Circle: |
|
DEA: |
DEA Uttarkashi |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4108 Steel Truss Bridge over Kamal River for Village Thali at Sada TOK (48.000 M.) (completed) |
|
Procurement: |
Package No.: 631
Package Name: UDRP/AF/BR/64
Tender Date: 11-10-2019
Current Status: Agreement signed
Achieved on Date: 07-02-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/64
Contractor Name: Tons Builderes
|
Start Date: 15-02-2020
Intended Completion Date: 12-01-2022
Original End Date: 14-05-2021
|
Total Bond Cost: 49381334.18 (493.81 lakhs)
Variation Cost: 11713148.98 (117.13 lakhs) Hence Total Bond Cost is 61094483.16 (610.94 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 9209743 for 373 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 6.06 | 1.00 Job | 1.00 Job | 1.38 | 6.06 | 2. | Foundation RHS | 1.00 Job | 14.16 | 1.00 Job | 1.00 Job | 3.21 | 14.16 | 3. | Foundation LHS | 1.00 Job | 14.16 | 1.00 Job | 1.00 Job | 3.21 | 14.16 | 4. | Abutment Superstructure RHS | 1.00 Job | 22.00 | 1.00 Job | 1.00 Job | 4.99 | 22.00 | 5. | Abutment Superstructure LHS | 1.00 Job | 22.00 | 1.00 Job | 1.00 Job | 4.99 | 22.00 | 6. | Fixing of chequered Plate/RCC Deck | 1.00 sqm | 4.50 | 1.00 sqm | 1.00 sqm | 1.02 | 4.50 | 7. | Steel Railing/crush barrier | 1.00 m | 5.71 | 1.00 m | 1.00 m | 1.3 | 5.71 | 8. | Approach Ramp /path | 1.00 m | 59.05 | 1.00 m | 1.00 m | 13.39 | 59.05 | 9. | Protection Work | 1.00 Job | 42.18 | 1.00 Job | 1.00 Job | 9.57 | 42.18 | 10. | Errection Work | 1.00 Job | 71.83 | 1.00 Job | 1.00 Job | 16.29 | 71.83 | 11. | Fabrication Work | 1.00 job | 176.45 | 1.00 job | 1.00 job | 40.02 | 176.45 | 12. | Fixing Bearing/Slab Casting | 4.00 job | 2.81 | 4.00 job | 4.00 job | 0.64 | 2.81 |
Total Amount: |
440.91 |
|
100 |
440.91 |
|
Remarks:
No Remarks
Work Program Made On:
06-03-2020
Updation of work program on:
30-05-2022
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 14-October-2020 | 104.51 lakhs |
2. | 30-December-2020 | 39.98 lakhs |
3. | 30-March-2021 | 199.22 lakhs |
4. | 10-June-2021 | 25.33 lakhs |
5. | 22-September-2021 | 24.96 lakhs |
6. | 06-November-2021 | 133.29 lakhs |
7. | 24-February-2022 | 53.97 lakhs |
8. | 31-May-2022 | 29.68 lakhs |
Total |
610.94 lakhs |
% Payment |
100 % |
|
Advance Amount: 115.92 lakhs
Recovered Amount: 115.92 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 111 |
No Notice issued. |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 17-02-2022 | BR64 | Sada thali bridge deck slab reinforcement work is completed. And shuttering work is on progress . | Yashpal Rawat | unknown | unknown | See Pic |
2. | 17-02-2022 | BR 64 | Sada thali bridge painting work is on progress | Yashpal Rawat | unknown | unknown | See Pic |
3. | 06-01-2022 | BR 64 | Sada thali bridge reinforcement work in on progress. | Yashpal Rawat | unknown | unknown | See Pic |
4. | 06-01-2022 | BR 64 | Sada thali bridge reinforcement work in on progress | Yashpal Rawat | unknown | unknown | See Pic |
5. | 03-01-2022 | BR 64 | Sada thali bridge painting work is on progress | Yashpal Rawat | unknown | unknown | See Pic |
6. | 03-01-2022 | BR64 | Sada thali bridge reinforcement work is on progress | Yashpal Rawat | unknown | unknown | See Pic |
7. | 25-12-2021 | BR64 | Sada thali bridge painting and shuttering work is on progress | Yashpal Rawat | unknown | unknown | See Pic |
8. | 25-12-2021 | BR 64 | Sada thali bridge painting and shuttering work is on progress | Yashpal Rawat | unknown | unknown | See Pic |
9. | 18-12-2021 | BR64 | Sada thali bridge erection work is on progress | Yashpal Rawat | unknown | unknown | See Pic |
10. | 18-12-2021 | BR 64 | Sada thali bridge erection work is on progress | Yashpal Rawat | unknown | unknown | See Pic |
11. | 18-12-2021 | BR 64 | Sada thali bridge erection and shataring work is on progress | Yashpal Rawat | unknown | unknown | See Pic |
12. | 15-12-2021 | BR64 | Sada thali motor bridge, padestral work has been completed both side. | Yashpal Rawat | unknown | unknown | See Pic |
13. | 14-12-2021 | Sada Bridge | Painting work in progress | AAE CL Bharti | ` | ` | See Pic |
14. | 14-12-2021 | BR 64 sada thalli motor bridge | Padestral concrete work has been completed , painting work is in Progress . | Manoj sain QC | ` | ` | See Pic |
15. | 09-12-2021 | BR 64 Sada thalli | M 40 concrete work is in progress for padestral work. | Manoj sain QC | ` | ` | See Pic |
16. | 09-12-2021 | Sada thali bridge erection work is on progress | Sada thali bridge erection work is on progress | Yashpal Rawat | unknown | unknown | See Pic |
17. | 09-12-2021 | BR64 | Sada thali bridge erection work is on progress | Yashpal Rawat | unknown | unknown | See Pic |
18. | 09-12-2021 | BR64 | Sada thali bridge padestral concert work is on progress. | Yashpal Rawat | unknown | unknown | See Pic |
19. | 21-11-2021 | BR 64 sada thalli motor bridge | Eraction work is on progress | Manoj sain | ` | ` | See Pic |
20. | 21-11-2021 | BR64 | Sada thali bridge erection work is on progress | Yashpal Rawat | unknown | unknown | See Pic |
|
|