Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/64 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 631 Package Name: UDRP/AF/BR/64 Sanction Cost: 523.10  lakhs
District: Uttarkashi Block: Naugaon Constituency: Purola Circle:
DEA: DEA Uttarkashi DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4108   Steel Truss Bridge over Kamal River for Village Thali at Sada TOK (48.000 M.) (completed)
Procurement:
Package No.: 631        Package Name: UDRP/AF/BR/64        Tender Date: 11-10-2019        Current Status: Agreement signed        Achieved on Date: 07-02-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/64        Contractor Name: Tons Builderes       
Start Date: 15-02-2020        Intended Completion Date: 12-01-2022        Original End Date:  14-05-2021
Total Bond Cost: 49381334.18 (493.81 lakhs)        Variation Cost: 11713148.98 (117.13 lakhs)     Hence Total Bond Cost is   61094483.16 (610.94 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 9209743 for 373 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job6.061.00 Job1.00 Job1.386.06
2.Foundation RHS1.00 Job14.161.00 Job1.00 Job3.2114.16
3.Foundation LHS1.00 Job14.161.00 Job1.00 Job3.2114.16
4.Abutment Superstructure RHS1.00 Job22.001.00 Job1.00 Job4.9922.00
5.Abutment Superstructure LHS1.00 Job22.001.00 Job1.00 Job4.9922.00
6.Fixing of chequered Plate/RCC Deck1.00 sqm4.501.00 sqm1.00 sqm1.024.50
7.Steel Railing/crush barrier1.00 m5.711.00 m1.00 m1.35.71
8.Approach Ramp /path 1.00 m59.051.00 m1.00 m13.3959.05
9.Protection Work1.00 Job42.181.00 Job1.00 Job9.5742.18
10.Errection Work1.00 Job71.831.00 Job1.00 Job16.2971.83
11.Fabrication Work1.00 job176.451.00 job1.00 job40.02176.45
12.Fixing Bearing/Slab Casting4.00 job2.814.00 job4.00 job0.642.81
Total Amount: 440.91 100   440.91
Remarks: No Remarks       Work Program Made On: 06-03-2020       Updation of work program on: 30-05-2022      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.14-October-2020104.51  lakhs
2.30-December-202039.98  lakhs
3.30-March-2021199.22  lakhs
4.10-June-202125.33  lakhs
5.22-September-202124.96  lakhs
6.06-November-2021133.29  lakhs
7.24-February-202253.97  lakhs
8.31-May-202229.68  lakhs
Total 610.94  lakhs
% Payment 100 %
Advance Amount:  115.92  lakhs        Recovered Amount:  115.92  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 778     No. of Test Done : 811      No. of Test Passed : 804      No. of Test Failed : 7   Test report of this package
Number of Pics Available on Web Repository: 111
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.17-02-2022BR64Sada thali bridge deck slab reinforcement work is completed. And shuttering work is on progress .Yashpal Rawatunknownunknown See Pic
2.17-02-2022BR 64Sada thali bridge painting work is on progressYashpal Rawatunknownunknown See Pic
3.06-01-2022BR 64Sada thali bridge reinforcement work in on progress.Yashpal Rawatunknownunknown See Pic
4.06-01-2022BR 64Sada thali bridge reinforcement work in on progressYashpal Rawatunknownunknown See Pic
5.03-01-2022BR 64Sada thali bridge painting work is on progressYashpal Rawatunknownunknown See Pic
6.03-01-2022BR64Sada thali bridge reinforcement work is on progressYashpal Rawatunknownunknown See Pic
7.25-12-2021BR64Sada thali bridge painting and shuttering work is on progressYashpal Rawatunknownunknown See Pic
8.25-12-2021BR 64Sada thali bridge painting and shuttering work is on progressYashpal Rawatunknownunknown See Pic
9.18-12-2021BR64Sada thali bridge erection work is on progressYashpal Rawatunknownunknown See Pic
10.18-12-2021BR 64Sada thali bridge erection work is on progressYashpal Rawatunknownunknown See Pic
11.18-12-2021BR 64Sada thali bridge erection and shataring work is on progressYashpal Rawatunknownunknown See Pic
12.15-12-2021BR64Sada thali motor bridge, padestral work has been completed both side.Yashpal Rawatunknownunknown See Pic
13.14-12-2021Sada BridgePainting work in progressAAE CL Bharti ` ` See Pic
14.14-12-2021BR 64 sada thalli motor bridgePadestral concrete work has been completed , painting work is in Progress .Manoj sain QC ` ` See Pic
15.09-12-2021BR 64 Sada thalliM 40 concrete work is in progress for padestral work.Manoj sain QC ` ` See Pic
16.09-12-2021Sada thali bridge erection work is on progressSada thali bridge erection work is on progressYashpal Rawatunknownunknown See Pic
17.09-12-2021BR64Sada thali bridge erection work is on progressYashpal Rawatunknownunknown See Pic
18.09-12-2021BR64Sada thali bridge padestral concert work is on progress.Yashpal Rawatunknownunknown See Pic
19.21-11-2021BR 64 sada thalli motor bridgeEraction work is on progressManoj sain ` ` See Pic
20.21-11-2021BR64Sada thali bridge erection work is on progressYashpal Rawatunknownunknown See Pic