Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/69 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 630 Package Name: UDRP/AF/BR/69 Sanction Cost: 530.95  lakhs
District: Uttarkashi Block: Bhatwari Constituency: Gangotri Circle:
DEA: DEA Uttarkashi DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4071   Over Bhagirathi River at Harsil (42.000 M.) (in prorgress)
Procurement:
Package No.: 630        Package Name: UDRP/AF/BR/69        Tender Date: 22-01-2020        Current Status: Agreement signed        Achieved on Date: 18-01-2021

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/69        Contractor Name: M/s. Valley Construction Company Pvt.Ltd.       
Start Date: 06-02-2021        Intended Completion Date: 30-07-2023        Original End Date:  31-03-2022
Total Bond Cost: 54397225.21 (543.97 lakhs)        Variation Cost: 2904028.71 (29.04 lakhs)     Hence Total Bond Cost is   57301253.92 (573.01 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 22139986 for 814 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job57.411.00 Job0.00 Job00.00
2.Foundation RHS1.00 Job31.311.00 Job1.00 Job6.1731.31
3.Foundation LHS1.00 Job31.311.00 Job1.00 Job6.1731.31
4.Abutment Superstructure RHS1.00 Job19.411.00 Job1.00 Job3.8319.41
5.Abutment Superstructure LHS1.00 Job19.411.00 Job1.00 Job3.8319.41
6.Steel Railing/crush barrier1.00 m23.931.00 m0.00 m00.00
7.Approach Ramp /path 1.00 m19.621.00 m0.00 m00.00
8.Protection Work1.00 Job21.981.00 Job0.20 Job0.874.40
9.Errection Work1.00 Job73.571.00 Job0.00 Job00.00
10.Fabrication Work1.00 job184.251.00 job0.40 job14.5373.70
11.Fixing Bearing/Slab Casting4.00 job25.014.00 job0.00 job00.00
Total Amount: 507.21 35.4   179.54
Remarks: No Remarks       Work Program Made On: 16-03-2021       Updation of work program on: 25-05-2022      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.22-September-202144.52  lakhs
2.11-March-202241.58  lakhs
3.15-June-20228.43  lakhs
4.28-July-20229.25  lakhs
5.24-November-202213.55  lakhs
6.28-January-202333.61  lakhs
7.25-March-202367.24  lakhs
8.11-April-202348.37  lakhs
9.25-April-202370.25  lakhs
10.26-May-202344.87  lakhs
11.15-July-202341.84  lakhs
12.26-July-202313.78  lakhs
13.10-August-20236.36  lakhs
14.15-September-202333.81  lakhs
15.05-October-202351.41  lakhs
16.19-October-202333.55  lakhs
17.06-November-202359.58  lakhs
18.30-December-202328.52  lakhs
Total 650.52  lakhs
% Payment 113.53 %
Advance Amount:  30.07  lakhs        Recovered Amount:  27.26  lakhs        Balance to be Recovered  2.81  lakhs        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):No Pending Issue
Environment & Social Compliances(Sub Project level):
Over Bhagirathi River at Harsil(4071)EMP
Detailed report of this Package
Quality
No. of Test Required : 159     No. of Test Done : 188      No. of Test Passed : 185      No. of Test Failed : 3   Test report of this package
Number of Pics Available on Web Repository: 84
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.22-04-2022Harsil motor bridgeShuttering of abutment A1 first lift is in progress.Abhishek tiwari ` ` See Pic
2.22-04-2022Harsil motor bridgeShuttering of abutment A2 2nd lift is in progress.Abhishek tiwari ` ` See Pic
3.21-04-2022HarsilA1,wall 1st lift concrete sampling done.concrete grade M35.Niraj pathak ` ` See Pic
4.21-04-2022HarsilA1, wall 1st lift concrete sampling done, concrete grade M35.Niraj pathak ` ` See Pic
5.21-04-2022HarsilA2,wall 2nd lift shuttering work in progress.Niraj pathak ` ` See Pic
6.21-04-2022HarsilA2,wall 2nd lift shuttering work in progress.Niraj pathak ` ` See Pic
7.23-12-2021Harsil bridge A1 siteExcavation Abutment A1Arun kumar ` ` See Pic
8.23-12-2021Harsil bridge no-69Survey Abutment bagori sideArun kumar ` ` See Pic
9.23-12-2021Harsil bridge no-69TS survey Abutment A2Arun kumar ` ` See Pic
10.23-12-2021Harsil bridge no-69TS serveyArun kumar R.E ` ` See Pic
11.16-11-2021BR/69A2, footing concrete sampling work in progress, concrete grade M35.Niraj pathakunknownunknown See Pic
12.16-11-2021BR/69Slump test is progress, concrete grade M35,A2 footing concrete.Niraj pathakunknownunknown See Pic
13.11-10-2021Harsil Bridge Abutment Bagori A2Bridge no 69Arun kumar ` ` See Pic
14.29-09-2021Harshil BridgeH.p Stone Filling Work in progress for Abutment R.H S Side ISt lift at 42m span steel Truss Bridge at Harshil District UttarkashiYogesh Dobhal ` ` See Pic
15.11-09-2021Abutment A2 raftConcreting of abutment A2 raft is in progress at harsil bridge in district UttarkashiAbhishek tiwari ` ` See Pic
16.11-09-2021Abutment A2 raftConcreting of abutment A2 raft foundation is in progress at harsil bridge in district UttarkashiAbhishek tiwari ` ` See Pic
17.11-09-2021Abutment A2 raftConcreting of abutment A2 raft foundation is in progress at harsil bridge in district UttarkashiAbhishek tiwari ` ` See Pic
18.11-09-2021Abutment A1PCC work of abutment A1 done.Abhishek tiwari ` ` See Pic
19.11-09-2021Abutment A2 raftConcreting of abutment A2 raft foundation is in progress at harsil bridge in district UttarkashiAbhishek tiwari ` ` See Pic
20.11-09-2021Abutment A2Concreting of abutment A2 raft foundation is in progress at harsil bridge in district Uttarkashi.Abhishek tiwari ` ` See Pic