UDRP/PWD/03/39/RD/027(a)
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
63 |
Package Name: |
UDRP/PWD/03/39/RD/027(a) |
Sanction Cost: |
400.74 lakhs |
District: |
Rudraprayag |
Block: |
August Muni |
Constituency: |
Rudraprayag |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Guptkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 2544 Syuri-Taithi-Pata Motor Road (5.250 KM.) (completed) |
|
Procurement: |
Package No.: 63
Package Name: UDRP/PWD/03/39/RD/027(a)
Tender Date: 20-11-2014
Current Status: Agreement signed
Achieved on Date: 08-03-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/03/39/RD/027(a)
Contractor Name: Shivom Construction
|
Start Date: 15-03-2016
Intended Completion Date: 31-10-2018
Original End Date: 14-12-2016
|
Total Bond Cost: 30771037.95 (307.71 lakhs)
Variation Cost: 6661072.91 (66.61 lakhs) Hence Total Bond Cost is 37432110.86 (374.32 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 1477056 for 96 days
LD Analysis for Milestone2: calculated LD is Rs 4231150 for 275 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 5.25 KM | 33.58 | 5.25 KM | 5.25 KM | 10.64 | 33.58 | 2. | R/Wall, B/ Wall Type Protection works | 1310.00 m | 58.09 | 1526.00 m | 1526.00 m | 18.41 | 58.09 | 3. | G-2 | 10.50 KM | 52.12 | 10.50 KM | 10.50 KM | 16.52 | 52.12 | 4. | G-3 | 5.25 KM | 36.20 | 5.25 KM | 5.25 KM | 11.47 | 36.20 | 5. | PC/CC i/c Prime Coat, Tack Coat | 5.25 KM | 52.53 | 5.25 KM | 5.25 KM | 16.65 | 52.53 | 6. | Cause Way | 3.00 No | 20.71 | 3.00 No | 3.00 No | 6.56 | 20.71 | 7. | Culverts/Scupper | 17.00 No | 30.26 | 17.00 No | 17.00 No | 9.59 | 30.26 | 8. | longitudinal Drain | 5200.00 m | 20.92 | 5200.00 m | 5200.00 m | 6.63 | 20.92 | 9. | Crash Barrier | 0.00 m | 0.00 | 0.00 m | 0.00 m | 0 | 0.00 | 10. | Parapet | 340.00 No | 9.77 | 340.00 No | 340.00 No | 3.1 | 9.77 | 11. | Road Furniture | 68.00 No | 1.38 | 68.00 No | 68.00 No | 0.44 | 1.38 |
Total Amount: |
315.56 |
|
100 |
315.56 |
|
Remarks:
No Remarks
Work Program Made On:
18-05-2016
Updation of work program on:
12-11-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 20-May-2016 | 24.52 lakhs |
2. | 30-August-2016 | 24.20 lakhs |
3. | 21-September-2016 | 14.54 lakhs |
4. | 15-November-2016 | 18.80 lakhs |
5. | 28-February-2017 | 25.79 lakhs |
6. | 18-May-2017 | 34.92 lakhs |
7. | 03-August-2017 | 29.16 lakhs |
8. | 21-September-2017 | 31.01 lakhs |
9. | 15-October-2017 | 22.23 lakhs |
10. | 28-November-2017 | 19.08 lakhs |
11. | 24-January-2018 | 23.87 lakhs |
12. | 13-March-2018 | 19.26 lakhs |
13. | 24-April-2018 | 11.77 lakhs |
14. | 16-May-2018 | 17.31 lakhs |
15. | 06-July-2018 | 3.53 lakhs |
16. | 19-July-2018 | 13.75 lakhs |
17. | 30-July-2019 | 40.76 lakhs |
Total |
374.5 lakhs |
% Payment |
100.05 % |
|
Advance Amount: 204.23 lakhs
Recovered Amount: 204.23 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 103 |
Number of Notice(s) issued: 102 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 21-03-2018 | | S. E. Sir site visit | Prashant Kumar | QC | DSC WB SPW Rudraprayag | See Pic |
2. | 21-03-2018 | 3+300 | S. E. SIR site visit | Prashant Kumar | QC | DSC WB SPW Rudraprayag | See Pic |
3. | 24-02-2018 | 1+300 | Site visit EE sir and RE sir | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
4. | 20-11-2017 | Ch 2.200 | G3 laying in progress | Rahul Panwar | Survey Engineer | NH Srinagar | See Pic |
5. | 17-11-2017 | 1+900 | B/wall work in progress | Prashant Kumar | QC | DSC WB SPW Rudraprayag | See Pic |
6. | 14-11-2017 | Ch 1.450 | C.E. sir site visit | Rahul Panwar | Survey Engineer | NH Srinagar | See Pic |
7. | 13-11-2017 | 2+900 | Pc rolling | Prashant Kumar | QC | DSC WB SPW Rudraprayag | See Pic |
8. | 03-11-2017 | 3+650 | Pc laying | Prashant Kumar | QC | DSC WB SPW Rudraprayag | See Pic |
9. | 05-07-2017 | 2+775 | Subgrade work progress | Prashant Kumar | QC | DSC WB SPW Rudraprayag | See Pic |
10. | 08-06-2017 | 0+775 | 3m span culvert Slab casting work in progress. | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
11. | 12-05-2017 | 1+100 | Stone blast collection work. | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
12. | 03-05-2017 | 4+240 | Thickness checking by chief sir Pauri | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
13. | 17-03-2017 | 2+850 | CE Sir, SE Sir and EE sir site visit. | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
14. | 17-03-2017 | 2+900 | 3.0 m span culvert masonary work in progress | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
15. | 02-03-2017 | 2+850 | Visit of CE sir,SE sir,and EE sir ,CE sir instructions for box culvert. | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
16. | 27-02-2017 | 1+700 | Defect cutting in progress | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
17. | 27-02-2017 | 0+810 | Sub grade making. | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
18. | 09-02-2017 | 2+175 | G2 1st layer material stacking work | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
19. | 09-02-2017 | 1+260 | Hill side cutting | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
20. | 01-02-2017 | 1+250 | Hp bend devlopement cutting work | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
|
|