Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/55 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 628 Package Name: UDRP/AF/BR/55 Sanction Cost: 663.03  lakhs
District: Tehri Block: Bhilangana Constituency: Ghanshali Circle:
DEA: DEA Tehri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4054   Bridge Over Asena Gadera at KM-5 of Gadoliya-Pilkhi-Ghansali MR (52.000 M.) (completed)
Procurement:
Package No.: 628        Package Name: UDRP/AF/BR/55        Tender Date: 22-01-2020        Current Status: Agreement signed        Achieved on Date: 12-10-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/55        Contractor Name: Triveni Construction Company       
Start Date: 28-10-2020        Intended Completion Date: 28-04-2022        Original End Date:  27-01-2022
Total Bond Cost: 63617925.11 (636.18 lakhs)        Variation Cost: 4876335.29 (48.76 lakhs)     Hence Total Bond Cost is   68494260.4 (684.94 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 8620239 for 271 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job49.771.00 Job1.00 Job8.6549.77
2.Foundation RHS1.00 Job8.581.00 Job1.00 Job1.498.58
3.Foundation LHS1.00 Job8.581.00 Job1.00 Job1.498.58
4.Abutment Superstructure RHS1.00 Job11.931.00 Job1.00 Job2.0711.93
5.Abutment Superstructure LHS1.00 Job11.931.00 Job1.00 Job2.0711.93
6.Steel Railing/crush barrier104.00 m12.25104.00 m104.00 m2.1312.25
7.Approach Ramp /path 190.00 m61.08190.00 m190.00 m10.6261.08
8.Protection Work1.00 Job29.181.00 Job1.00 Job5.0729.18
9.Errection Work1.00 Job77.891.00 Job1.00 Job13.5477.89
10.Fabrication Work1.00 job273.321.00 job1.00 job47.5273.32
11.Fixing Bearing/Slab Casting1.00 job27.521.00 job1.00 job4.7827.52
12.Wearing Coat22.07 Cum3.4222.07 Cum22.07 Cum0.593.42
Total Amount: 575.45 100   575.45
Remarks: No Remarks       Work Program Made On: 02-01-2021       Updation of work program on: 23-03-2022      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-March-202117.18  lakhs
2.31-May-202116.71  lakhs
3.30-June-2021271.75  lakhs
4.29-July-202135.91  lakhs
5.22-October-202122.48  lakhs
6.31-December-2021156.25  lakhs
7.31-March-202294.53  lakhs
8.20-May-202240.36  lakhs
9.15-June-202229.77  lakhs
Total 684.94  lakhs
% Payment 100 %
Advance Amount:  36.60  lakhs        Recovered Amount:  36.60  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 104     No. of Test Done : 104      No. of Test Passed : 104      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 51
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.04-03-2022Km 5 BR 55Steel checkingAlok Chandra Joshiunknownunknown See Pic
2.04-03-2022Asenagadera BR-55Reinforcement checking for Deck slabSuresh Prasad ` ` See Pic
3.27-02-2022Km 5 BR 55Concrete work in progress at dirt wall AW sideAlok Chandra Joshiunknownunknown See Pic
4.24-02-2022Km 5 BR 55Steel binding work in progressAlok Chandra Joshiunknownunknown See Pic
5.23-02-2022Asenagadera BR-55Reinforcement laying in progress for Deck slabSuresh Prasad ` ` See Pic
6.27-01-2022Km 5 BR 55Barekading workAlok Chandra Joshiunknownunknown See Pic
7.27-01-2022Km 5 BR 55Barekading workAlok Chandra Joshiunknownunknown See Pic
8.27-01-2022Km 5 BR 55Erection work completeAlok Chandra Joshiunknownunknown See Pic
9.22-01-2022Asenagadera BR-55Bridge Erection work completedSuresh Prasad ` ` See Pic
10.22-01-2022Asenagadera BR-55Erection work completedSuresh Prasad ` ` See Pic
11.22-01-2022Km 5 BR 55Shuttering work in progressAlok Chandra Joshiunknownunknown See Pic
12.22-01-2022Asenagadera BR-55 siteBearing fixing A1 Side (LHS) with pedestalSuresh Prasad ` ` See Pic
13.22-01-2022Asenagadera BR-55Bearing fixing A2 side (RHS) with pedestal casting M-40 CompletedSuresh Prasad ` ` See Pic
14.15-12-2021Erection work in progressErection work in progressAlok Chandra Joshiunknownunknown See Pic
15.15-12-2021Km 5 BR 55Erection work in progressAlok Chandra Joshiunknownunknown See Pic
16.15-12-2021Km 5 BR 55Bolting and Torquing work in progressAlok Chandra Joshiunknownunknown See Pic
17.12-12-2021Km 5 BR 55Erection work in progressAlok Chandra Joshiunknownunknown See Pic
18.18-11-2021Asena gadera 52 m span bridge ghansaliErection workSugandh singh saini ` ` See Pic
19.16-10-2021Asenagadera BR-55Erection work in progress A2 sideSuresh Prasad ` ` See Pic
20.16-10-2021Asenagadera BR-55Erection work in progress A1 side.SURESH PRASAD ` ` See Pic