UDRP/AF/BR/55
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
628 |
Package Name: |
UDRP/AF/BR/55 |
Sanction Cost: |
663.03 lakhs |
District: |
Tehri |
Block: |
Bhilangana |
Constituency: |
Ghanshali |
Circle: |
|
DEA: |
DEA Tehri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4054 Bridge Over Asena Gadera at KM-5 of Gadoliya-Pilkhi-Ghansali MR (52.000 M.) (completed) |
|
Procurement: |
Package No.: 628
Package Name: UDRP/AF/BR/55
Tender Date: 22-01-2020
Current Status: Agreement signed
Achieved on Date: 12-10-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/55
Contractor Name: Triveni Construction Company
|
Start Date: 28-10-2020
Intended Completion Date: 28-04-2022
Original End Date: 27-01-2022
|
Total Bond Cost: 63617925.11 (636.18 lakhs)
Variation Cost: 4876335.29 (48.76 lakhs) Hence Total Bond Cost is 68494260.4 (684.94 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 8620239 for 271 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 49.77 | 1.00 Job | 1.00 Job | 8.65 | 49.77 | 2. | Foundation RHS | 1.00 Job | 8.58 | 1.00 Job | 1.00 Job | 1.49 | 8.58 | 3. | Foundation LHS | 1.00 Job | 8.58 | 1.00 Job | 1.00 Job | 1.49 | 8.58 | 4. | Abutment Superstructure RHS | 1.00 Job | 11.93 | 1.00 Job | 1.00 Job | 2.07 | 11.93 | 5. | Abutment Superstructure LHS | 1.00 Job | 11.93 | 1.00 Job | 1.00 Job | 2.07 | 11.93 | 6. | Steel Railing/crush barrier | 104.00 m | 12.25 | 104.00 m | 104.00 m | 2.13 | 12.25 | 7. | Approach Ramp /path | 190.00 m | 61.08 | 190.00 m | 190.00 m | 10.62 | 61.08 | 8. | Protection Work | 1.00 Job | 29.18 | 1.00 Job | 1.00 Job | 5.07 | 29.18 | 9. | Errection Work | 1.00 Job | 77.89 | 1.00 Job | 1.00 Job | 13.54 | 77.89 | 10. | Fabrication Work | 1.00 job | 273.32 | 1.00 job | 1.00 job | 47.5 | 273.32 | 11. | Fixing Bearing/Slab Casting | 1.00 job | 27.52 | 1.00 job | 1.00 job | 4.78 | 27.52 | 12. | Wearing Coat | 22.07 Cum | 3.42 | 22.07 Cum | 22.07 Cum | 0.59 | 3.42 |
Total Amount: |
575.45 |
|
100 |
575.45 |
|
Remarks:
No Remarks
Work Program Made On:
02-01-2021
Updation of work program on:
23-03-2022
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-March-2021 | 17.18 lakhs |
2. | 31-May-2021 | 16.71 lakhs |
3. | 30-June-2021 | 271.75 lakhs |
4. | 29-July-2021 | 35.91 lakhs |
5. | 22-October-2021 | 22.48 lakhs |
6. | 31-December-2021 | 156.25 lakhs |
7. | 31-March-2022 | 94.53 lakhs |
8. | 20-May-2022 | 40.36 lakhs |
9. | 15-June-2022 | 29.77 lakhs |
Total |
684.94 lakhs |
% Payment |
100 % |
|
Advance Amount: 36.60 lakhs
Recovered Amount: 36.60 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 51 |
No Notice issued. |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 04-03-2022 | Km 5 BR 55 | Steel checking | Alok Chandra Joshi | unknown | unknown | See Pic |
2. | 04-03-2022 | Asenagadera BR-55 | Reinforcement checking for Deck slab | Suresh Prasad | ` | ` | See Pic |
3. | 27-02-2022 | Km 5 BR 55 | Concrete work in progress at dirt wall AW side | Alok Chandra Joshi | unknown | unknown | See Pic |
4. | 24-02-2022 | Km 5 BR 55 | Steel binding work in progress | Alok Chandra Joshi | unknown | unknown | See Pic |
5. | 23-02-2022 | Asenagadera BR-55 | Reinforcement laying in progress for Deck slab | Suresh Prasad | ` | ` | See Pic |
6. | 27-01-2022 | Km 5 BR 55 | Barekading work | Alok Chandra Joshi | unknown | unknown | See Pic |
7. | 27-01-2022 | Km 5 BR 55 | Barekading work | Alok Chandra Joshi | unknown | unknown | See Pic |
8. | 27-01-2022 | Km 5 BR 55 | Erection work complete | Alok Chandra Joshi | unknown | unknown | See Pic |
9. | 22-01-2022 | Asenagadera BR-55 | Bridge Erection work completed | Suresh Prasad | ` | ` | See Pic |
10. | 22-01-2022 | Asenagadera BR-55 | Erection work completed | Suresh Prasad | ` | ` | See Pic |
11. | 22-01-2022 | Km 5 BR 55 | Shuttering work in progress | Alok Chandra Joshi | unknown | unknown | See Pic |
12. | 22-01-2022 | Asenagadera BR-55 site | Bearing fixing A1 Side (LHS) with pedestal | Suresh Prasad | ` | ` | See Pic |
13. | 22-01-2022 | Asenagadera BR-55 | Bearing fixing A2 side (RHS) with pedestal casting M-40 Completed | Suresh Prasad | ` | ` | See Pic |
14. | 15-12-2021 | Erection work in progress | Erection work in progress | Alok Chandra Joshi | unknown | unknown | See Pic |
15. | 15-12-2021 | Km 5 BR 55 | Erection work in progress | Alok Chandra Joshi | unknown | unknown | See Pic |
16. | 15-12-2021 | Km 5 BR 55 | Bolting and Torquing work in progress | Alok Chandra Joshi | unknown | unknown | See Pic |
17. | 12-12-2021 | Km 5 BR 55 | Erection work in progress | Alok Chandra Joshi | unknown | unknown | See Pic |
18. | 18-11-2021 | Asena gadera 52 m span bridge ghansali | Erection work | Sugandh singh saini | ` | ` | See Pic |
19. | 16-10-2021 | Asenagadera BR-55 | Erection work in progress A2 side | Suresh Prasad | ` | ` | See Pic |
20. | 16-10-2021 | Asenagadera BR-55 | Erection work in progress A1 side. | SURESH PRASAD | ` | ` | See Pic |
|
|