Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/46 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 626 Package Name: UDRP/AF/BR/46 Sanction Cost: 968.92  lakhs
District: Pithoragarh Block: Gangolihat Constituency: Gangolihat Circle:
DEA: DEA Munsyari DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4062   Bridge at Gangolihat Madanpur Naini Motor Road KM-2 (70.000 M.) (completed)
Procurement:
Package No.: 626        Package Name: UDRP/AF/BR/46        Tender Date: 30-01-2020        Current Status: Agreement signed        Achieved on Date: 14-07-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/46        Contractor Name: M/s Laxmi Datt Binwal       
Start Date: 21-08-2020        Intended Completion Date: 22-05-2022        Original End Date:  02-02-2022
Total Bond Cost: 103819069.95 (1038.19 lakhs)        Variation Cost: -110312.47 (-1.1 lakhs)     Hence Total Bond Cost is   103708757.48 (1037.09 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 22477030 for 433 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job49.771.00 Job1.00 Job4.7949.77
2.Foundation RHS1.00 Job61.531.00 Job1.00 Job5.9361.53
3.Foundation LHS1.00 Job61.531.00 Job1.00 Job5.9361.53
4.Abutment Superstructure RHS1.00 Job58.121.00 Job1.00 Job5.658.12
5.Abutment Superstructure LHS1.00 Job58.121.00 Job1.00 Job5.658.12
6.Fixing of chequered Plate/RCC Deck462.80 sqm18.10462.80 sqm462.80 sqm1.7418.10
7.Steel Railing/crush barrier143.90 m9.46143.90 m143.90 m0.919.46
8.Approach Ramp /path 123.00 m67.89123.00 m123.00 m6.5467.89
9.Protection Work1.00 Job25.211.00 Job1.00 Job2.4325.21
10.Errection Work1.00 Job219.011.00 Job1.00 Job21.1219.01
11.Fabrication Work1.00 job409.451.00 job1.00 job39.44409.45
Total Amount: 1038.19 100   1038.19
Remarks: No Remarks       Work Program Made On: 28-09-2020       Updation of work program on: 23-05-2022      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-January-202140.82  lakhs
2.27-February-202139.21  lakhs
3.31-March-202142.48  lakhs
4.31-May-202160.47  lakhs
5.13-July-202124.54  lakhs
6.28-August-202126.36  lakhs
7.30-September-2021416.91  lakhs
8.09-November-20215.21  lakhs
9.30-November-20214.52  lakhs
10.31-December-202133.19  lakhs
11.16-February-2022212.52  lakhs
12.31-March-202245.60  lakhs
13.13-May-202252.28  lakhs
14.31-May-202232.96  lakhs
Total 1037.07  lakhs
% Payment 100 %
Advance Amount:  195.37  lakhs        Recovered Amount:  195.37  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 297     No. of Test Done : 349      No. of Test Passed : 349      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 261
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.04-06-2022BridgeBridge completedVs srivastava ` ` See Pic
2.21-05-2022At siteWearing coat completed.Neeraj Tewari ` ` See Pic
3.21-05-2022At siteReinforcement of deck slab.Neeraj Tewari ` ` See Pic
4.04-05-2022Seraghat BerinagA2 side PC work has been completedParambeer Singh Rawat ` ` See Pic
5.04-05-2022Seraghat BerinagA2 side PC work has been completedParambeer Singh Rawat ` ` See Pic
6.23-04-2022Seraghat BerinagBearing coat steel binding wipParambeer Singh Rawat ` ` See Pic
7.21-03-2022SeraghatA2 side plum concrete wipParambeer Singh Rawat ` ` See Pic
8.04-03-2022Seraghat BerinagShutering work and paint work in progressParambeer Singh Rawat ` ` See Pic
9.04-03-2022Seraghat BerinagShutering work and paint work in progressParambeer Singh Rawat ` ` See Pic
10.04-03-2022Seraghat BerinagShutering work and paint work in progressParambeer Singh Rawat ` ` See Pic
11.03-03-2022Seraghat BerinagBearing plate welding work in progressParambeer Singh Rawat ` ` See Pic
12.03-03-2022Seraghat BerinagShutering work in progressParambeer Singh Rawat ` ` See Pic
13.03-03-2022Seraghat BerinagShutering work in progressParambeer Singh Rawat ` ` See Pic
14.03-03-2022Seraghat BerinagPaint work and nut bolt tighting work in progressParambeer Singh Rawat ` ` See Pic
15.02-03-2022Seraghat BerinagAerial viewParambeer Singh Rawat ` ` See Pic
16.02-03-2022Seraghat BerinagSteel cuting work in progress for deck slabParambeer Singh Rawat ` ` See Pic
17.02-03-2022Seraghat BerinagBearing placing and fixing work in progressParambeer Singh Rawat ` ` See Pic
18.02-03-2022Seraghat BerinagBearing placing and fixing work in progressParambeer Singh Rawat ` ` See Pic
19.02-03-2022Seraghat BerinagBearing placing and fixing work in progressParambeer Singh Rawat ` ` See Pic
20.01-03-2022Seraghat BerinagPaint work and nut bolt tighting work in progressParambeer Singh Rawat ` ` See Pic