UDRP/AF/BR/46
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
626 |
Package Name: |
UDRP/AF/BR/46 |
Sanction Cost: |
968.92 lakhs |
District: |
Pithoragarh |
Block: |
Gangolihat |
Constituency: |
Gangolihat |
Circle: |
|
DEA: |
DEA Munsyari |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4062 Bridge at Gangolihat Madanpur Naini Motor Road KM-2 (70.000 M.) (completed) |
|
Procurement: |
Package No.: 626
Package Name: UDRP/AF/BR/46
Tender Date: 30-01-2020
Current Status: Agreement signed
Achieved on Date: 14-07-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/46
Contractor Name: M/s Laxmi Datt Binwal
|
Start Date: 21-08-2020
Intended Completion Date: 22-05-2022
Original End Date: 02-02-2022
|
Total Bond Cost: 103819069.95 (1038.19 lakhs)
Variation Cost: -110312.47 (-1.1 lakhs) Hence Total Bond Cost is 103708757.48 (1037.09 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 22477030 for 433 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 49.77 | 1.00 Job | 1.00 Job | 4.79 | 49.77 | 2. | Foundation RHS | 1.00 Job | 61.53 | 1.00 Job | 1.00 Job | 5.93 | 61.53 | 3. | Foundation LHS | 1.00 Job | 61.53 | 1.00 Job | 1.00 Job | 5.93 | 61.53 | 4. | Abutment Superstructure RHS | 1.00 Job | 58.12 | 1.00 Job | 1.00 Job | 5.6 | 58.12 | 5. | Abutment Superstructure LHS | 1.00 Job | 58.12 | 1.00 Job | 1.00 Job | 5.6 | 58.12 | 6. | Fixing of chequered Plate/RCC Deck | 462.80 sqm | 18.10 | 462.80 sqm | 462.80 sqm | 1.74 | 18.10 | 7. | Steel Railing/crush barrier | 143.90 m | 9.46 | 143.90 m | 143.90 m | 0.91 | 9.46 | 8. | Approach Ramp /path | 123.00 m | 67.89 | 123.00 m | 123.00 m | 6.54 | 67.89 | 9. | Protection Work | 1.00 Job | 25.21 | 1.00 Job | 1.00 Job | 2.43 | 25.21 | 10. | Errection Work | 1.00 Job | 219.01 | 1.00 Job | 1.00 Job | 21.1 | 219.01 | 11. | Fabrication Work | 1.00 job | 409.45 | 1.00 job | 1.00 job | 39.44 | 409.45 |
Total Amount: |
1038.19 |
|
100 |
1038.19 |
|
Remarks:
No Remarks
Work Program Made On:
28-09-2020
Updation of work program on:
23-05-2022
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-January-2021 | 40.82 lakhs |
2. | 27-February-2021 | 39.21 lakhs |
3. | 31-March-2021 | 42.48 lakhs |
4. | 31-May-2021 | 60.47 lakhs |
5. | 13-July-2021 | 24.54 lakhs |
6. | 28-August-2021 | 26.36 lakhs |
7. | 30-September-2021 | 416.91 lakhs |
8. | 09-November-2021 | 5.21 lakhs |
9. | 30-November-2021 | 4.52 lakhs |
10. | 31-December-2021 | 33.19 lakhs |
11. | 16-February-2022 | 212.52 lakhs |
12. | 31-March-2022 | 45.60 lakhs |
13. | 13-May-2022 | 52.28 lakhs |
14. | 31-May-2022 | 32.96 lakhs |
Total |
1037.07 lakhs |
% Payment |
100 % |
|
Advance Amount: 195.37 lakhs
Recovered Amount: 195.37 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 261 |
No Notice issued. |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 04-06-2022 | Bridge | Bridge completed | Vs srivastava | ` | ` | See Pic |
2. | 21-05-2022 | At site | Wearing coat completed. | Neeraj Tewari | ` | ` | See Pic |
3. | 21-05-2022 | At site | Reinforcement of deck slab. | Neeraj Tewari | ` | ` | See Pic |
4. | 04-05-2022 | Seraghat Berinag | A2 side PC work has been completed | Parambeer Singh Rawat | ` | ` | See Pic |
5. | 04-05-2022 | Seraghat Berinag | A2 side PC work has been completed | Parambeer Singh Rawat | ` | ` | See Pic |
6. | 23-04-2022 | Seraghat Berinag | Bearing coat steel binding wip | Parambeer Singh Rawat | ` | ` | See Pic |
7. | 21-03-2022 | Seraghat | A2 side plum concrete wip | Parambeer Singh Rawat | ` | ` | See Pic |
8. | 04-03-2022 | Seraghat Berinag | Shutering work and paint work in progress | Parambeer Singh Rawat | ` | ` | See Pic |
9. | 04-03-2022 | Seraghat Berinag | Shutering work and paint work in progress | Parambeer Singh Rawat | ` | ` | See Pic |
10. | 04-03-2022 | Seraghat Berinag | Shutering work and paint work in progress | Parambeer Singh Rawat | ` | ` | See Pic |
11. | 03-03-2022 | Seraghat Berinag | Bearing plate welding work in progress | Parambeer Singh Rawat | ` | ` | See Pic |
12. | 03-03-2022 | Seraghat Berinag | Shutering work in progress | Parambeer Singh Rawat | ` | ` | See Pic |
13. | 03-03-2022 | Seraghat Berinag | Shutering work in progress | Parambeer Singh Rawat | ` | ` | See Pic |
14. | 03-03-2022 | Seraghat Berinag | Paint work and nut bolt tighting work in progress | Parambeer Singh Rawat | ` | ` | See Pic |
15. | 02-03-2022 | Seraghat Berinag | Aerial view | Parambeer Singh Rawat | ` | ` | See Pic |
16. | 02-03-2022 | Seraghat Berinag | Steel cuting work in progress for deck slab | Parambeer Singh Rawat | ` | ` | See Pic |
17. | 02-03-2022 | Seraghat Berinag | Bearing placing and fixing work in progress | Parambeer Singh Rawat | ` | ` | See Pic |
18. | 02-03-2022 | Seraghat Berinag | Bearing placing and fixing work in progress | Parambeer Singh Rawat | ` | ` | See Pic |
19. | 02-03-2022 | Seraghat Berinag | Bearing placing and fixing work in progress | Parambeer Singh Rawat | ` | ` | See Pic |
20. | 01-03-2022 | Seraghat Berinag | Paint work and nut bolt tighting work in progress | Parambeer Singh Rawat | ` | ` | See Pic |
|
|