Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/60 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 625 Package Name: UDRP/AF/BR/60 Sanction Cost: 420.31  lakhs
District: Chamoli Block: Ghat Constituency: Tharali Circle:
DEA: DEA Karanprayag DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4075   Bridge at Village Lakhi Chufuliya Guard (45.000 M.) (completed)
Procurement:
Package No.: 625        Package Name: UDRP/AF/BR/60        Tender Date: 26-09-2019        Current Status: Agreement signed        Achieved on Date: 22-01-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/60        Contractor Name: M/S.KGL Infrastructure       
Start Date: 01-02-2020        Intended Completion Date: 06-11-2021        Original End Date:  30-04-2021
Total Bond Cost: 42080243.41 (420.8 lakhs)        Variation Cost: -3225018.71 (-32.25 lakhs)     Hence Total Bond Cost is   38855224.7 (388.55 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 9089280 for 432 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Env. Man & Moni Plan1.00 Job4.221.00 Job1.00 Job1.034.22
2.Other Allied Works & Finishing Work 1.00 Job3.451.00 Job1.00 Job0.843.45
3.Foundation RHS2.00 Job36.982.00 Job2.00 Job8.9936.98
4.Foundation LHS2.00 Job36.982.00 Job2.00 Job8.9936.98
5.Abutment Superstructure RHS1.00 Job0.221.00 Job1.00 Job0.050.22
6.Abutment Superstructure LHS1.00 Job0.221.00 Job1.00 Job0.050.22
7.Fixing of chequered Plate/RCC Deck89.21 sqm2.8989.21 sqm89.21 sqm0.72.89
8.Steel Railing/crush barrier91.20 m2.4891.20 m91.20 m0.62.48
9.Approach Ramp /path 120.00 m34.90120.00 m120.00 m8.4834.90
10.Protection Work1.00 Job21.551.00 Job1.00 Job5.2421.55
11.Errection Work1.00 Job46.171.00 Job1.00 Job11.2246.17
12.Gabion work334.00 m34.80334.00 m334.00 m8.4634.80
13.Fabrication Work1.00 job62.081.00 job1.00 job15.0962.08
14.Abutment Substructure RHS1.00 Job60.331.00 Job1.00 Job14.6660.33
15.Abutment Substructure LHS1.00 Job60.331.00 Job1.00 Job14.6660.33
16.Fixing Bearing/Slab Casting1.00 job3.821.00 job1.00 job0.933.82
Total Amount: 411.42 100   411.42
Remarks: No Remarks       Work Program Made On: 06-07-2020       Updation of work program on: 11-11-2021      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.11-November-202023.20  lakhs
2.04-December-20202.78  lakhs
3.04-February-2021128.13  lakhs
4.27-February-202134.69  lakhs
5.26-March-202118.76  lakhs
6.31-May-202174.80  lakhs
7.23-June-202136.26  lakhs
8.31-July-202112.23  lakhs
9.21-October-202145.20  lakhs
10.31-March-20226.99  lakhs
Total 383.04  lakhs
% Payment 98.58 %
Advance Amount:  36.82  lakhs        Recovered Amount:  36.82  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 1729     No. of Test Done : 1756      No. of Test Passed : 1753      No. of Test Failed : 3   Test report of this package
Number of Pics Available on Web Repository: 100
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.26-04-2022Lakhi-Chufliya Bridge site BR/60World Bank Team visit at site for InspectionEr.Vipin Tomar ,AE ` ` See Pic
2.26-01-2022Lakhi chufliyaA2side approach RoadRohit Kumar dubey ` ` See Pic
3.26-01-2022A1 side Approach RoadLakhi chufliyaRohit Kumar dubey ` ` See Pic
4.26-01-2022BridgeLakhi chafliyaRohit Kumar dubey ` ` See Pic
5.26-01-2022Completed bridgeLakhi chufliyaRohit Kumar dubey ` ` See Pic
6.29-12-2021Lakhi-Chufliya Bridge site BR/60Joint Inspection visit with Civil Division PWD Karnprayag Chamoli.Er. Vipin Tomar ` ` See Pic
7.18-11-2021Br/45 Vijaynagar TailaSite visit with Environment Expert Anju Pnawar from PIU Head-Office DehradunEr. Vipin Tomar AE ` ` See Pic
8.08-11-2021Lakhi chufliyaParapet work in progress.Manendra singh ` ` See Pic
9.07-11-2021Lakhi chufliyaParapet work in progress.Manendra singh ` ` See Pic
10.07-11-2021Lakhi chufliyaParfait work in progressManendra ` ` See Pic
11.30-10-2021Lakhi chufliyaPainting work in progressManendra singh ` ` See Pic
12.26-10-2021Lakhi chufliyaPanting work in progress BR60 bridgeManendra singh ` ` See Pic
13.16-10-2021BR60Curing for approach roadRohit Kumar Dubey ` ` See Pic
14.16-10-2021BR60Approach road work in progressRohit Kumar Dubey ` ` See Pic
15.29-09-2021A2 side RHS sideDe-shuttering work in progressVipin Tomar AE ` ` See Pic
16.23-07-2021Lakhi chuflagaad bridge br 60A1 side pedestal concreting work in progressManendra ` ` See Pic
17.26-06-2021At siteErection work under progressVipin Tomar AE ` ` See Pic
18.26-06-2021A2 side (RHS Side)Erection work under progress.Vipin Tomar AE ` ` See Pic
19.26-06-2021BR60Erection work in progressRohit Kumar Dubey ` ` See Pic
20.25-06-2021A2 side RHS SIDEErection work under progressDhwajvir Singh AAE ` ` See Pic