Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/59 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 624 Package Name: UDRP/AF/BR/59 Sanction Cost: 403.85  lakhs
District: Uttarkashi Block: Mori Constituency: Purola Circle:
DEA: DEA Uttarkashi DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4072   Km 11 of Arakot Chinwa Balcha MR (42.000 M.) (completed)
Procurement:
Package No.: 624        Package Name: UDRP/AF/BR/59        Tender Date: 26-09-2019        Current Status: Agreement signed        Achieved on Date: 22-01-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/59        Contractor Name: Tons Builderes       
Start Date: 01-02-2020        Intended Completion Date: 04-11-2021        Original End Date:  30-04-2021
Total Bond Cost: 37571580.54 (375.72 lakhs)        Variation Cost: 9661622.05 (96.62 lakhs)     Hence Total Bond Cost is   47233202.59 (472.33 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 5880018 for 313 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job9.041.00 Job1.00 Job2.699.04
2.Foundation RHS1.00 Job10.321.00 Job1.00 Job3.0810.32
3.Foundation LHS1.00 Job10.321.00 Job1.00 Job3.0810.32
4.Abutment Superstructure RHS1.00 Job14.561.00 Job1.00 Job4.3414.56
5.Abutment Superstructure LHS1.00 Job14.561.00 Job1.00 Job4.3414.56
6.Fixing of chequered Plate/RCC Deck1.00 sqm3.601.00 sqm1.00 sqm1.073.60
7.Steel Railing/crush barrier1.00 m2.671.00 m1.00 m0.82.67
8.Approach Ramp /path 1.00 m20.471.00 m1.00 m6.120.47
9.Protection Work1.00 Job19.701.00 Job1.00 Job5.8719.70
10.Errection Work1.00 Job59.761.00 Job1.00 Job17.8259.76
11.Fabrication Work1.00 job167.731.00 job1.00 job50167.73
12.Fixing Bearing/Slab Casting6.00 job2.726.00 job6.00 job0.812.72
Total Amount: 335.45 100   335.45
Remarks: No Remarks       Work Program Made On: 06-03-2020       Updation of work program on: 30-05-2022      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.01-December-2020188.33  lakhs
2.07-January-202119.11  lakhs
3.15-February-202120.69  lakhs
4.30-March-202181.11  lakhs
5.10-June-202172.94  lakhs
6.30-September-202139.30  lakhs
7.06-November-202135.77  lakhs
8.24-February-202215.08  lakhs
Total 472.33  lakhs
% Payment 100 %
Advance Amount:  76.13  lakhs        Recovered Amount:  76.13  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 470     No. of Test Done : 495      No. of Test Passed : 491      No. of Test Failed : 4   Test report of this package
Number of Pics Available on Web Repository: 47
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.21-01-2022Construction of 42m span steel truss motor bridge at Aarakot chinwa motor road km 11 BR59Complete bridgeMukesh Tyagi ` ` See Pic
2.16-11-2021Arakot chinwa motor bridgeWork completed at Arakot-chinwa motor bridge.Abhishek tiwari ` ` See Pic
3.16-11-2021Arakot-chinwa motor bridgeWork completed at arakot-chinwa motor bridge.Abhishek tiwari ` ` See Pic
4.16-11-2021Arakot-chinwa motor bridgeArakot-chinwa motor bridge work completed.Abhishek tiwari ` ` See Pic
5.16-11-2021Arakot-chinwa motor bridgeArakot chinwa motor bridge completed.Abhishek tiwari ` ` See Pic
6.29-10-2021BR59 arakot chinwa motor bridgeBridge work has been completedManoj sain Qc ` ` See Pic
7.29-10-2021BR59 arakot chinwa motor bridgeBridge work complted , curing work is in progressManoj sain Qc ` ` See Pic
8.29-10-2021BR59 arakot chinwa motor bridgeBridge work completed , curing work is in progressManoj sain Qc ` ` See Pic
9.29-10-2021BR59 arakot chinwa motor bridgeBridge work has been completedManoj sain Qc ` ` See Pic
10.19-10-2021Arakot chinwa BR59Slump test for deck slab concreteManoj sain ` ` See Pic
11.01-10-2021Arakot motor bridgeReinforcement of deck slab is in progress at arakot chinwa motor bridge.Abhishek tiwari ` ` See Pic
12.01-10-2021Arakot chinwa motor bridgeFixation of expansion joint is in progress at arakot-chinwa motor bridge in district Uttarkashi.Abhishek tiwari ` ` See Pic
13.17-08-2021Arakot bridgeWork in progressAAE CL Bharti ` ` See Pic
14.16-08-2021BR59At location arakot chinwa slop checking of Abutement A1 side approach road .Manoj sain ` ` See Pic
15.08-07-2021A2 pedestalCuring of A2 pedestalAAE C.L.Bharti ` ` See Pic
16.07-07-2021Arakot Chinwa motor Bridge BR 59Pedestals casting after fixing and leveling of Bearing.Manoj sain ` ` See Pic
17.05-07-2021Construction of 42m span steel truss motor bridge at km. 11 of Aarkot chinwa motor road in distt uttarkashiChecking of levels for bearingsSandeep kumarunknownunknown See Pic
18.27-06-2021Arakot motor bridgePanting work in progressAAE C.L.Bharti ` ` See Pic
19.27-06-2021Arakot BridgeBearing reached at Site.AAE C.L.Bharti ` ` See Pic
20.17-03-2021Arakot bridgeMedical Health checkup campC.L.Bharti ` ` See Pic