UDRP/AF/BR/57
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
622 |
Package Name: |
UDRP/AF/BR/57 |
Sanction Cost: |
688.00 lakhs |
District: |
Dehradun |
Block: |
Kalsi |
Constituency: |
Chakrata |
Circle: |
|
DEA: |
DEA Tehri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4094 48 Mtr span bridge steel truss motor bridge over kali raw river in km -10. (48.000 M.) (completed) |
|
Procurement: |
Package No.: 622
Package Name: UDRP/AF/BR/57
Tender Date: 26-09-2019
Current Status: Agreement signed
Achieved on Date: 22-01-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/57
Contractor Name: M/S.ARKS Universal pvt.ltd
|
Start Date: 01-02-2020
Intended Completion Date: 24-12-2021
Original End Date: 30-04-2021
|
Total Bond Cost: 61746413.36 (617.46 lakhs)
Variation Cost: -1297008.54 (-12.97 lakhs) Hence Total Bond Cost is 60449404.82 (604.49 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 13275390 for 430 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 9.03 | 1.00 Job | 1.00 Job | 1.64 | 9.03 | 2. | Foundation RHS | 1.00 Job | 7.21 | 1.00 Job | 1.00 Job | 1.31 | 7.21 | 3. | Foundation LHS | 1.00 Job | 7.21 | 1.00 Job | 1.00 Job | 1.31 | 7.21 | 4. | Steel Railing/crush barrier | 99.00 m | 3.99 | 99.00 m | 99.00 m | 0.73 | 3.99 | 5. | Approach Ramp /path | 214.00 m | 71.85 | 214.00 m | 214.00 m | 13.06 | 71.85 | 6. | Protection Work | 1.00 Job | 68.44 | 1.00 Job | 1.00 Job | 12.44 | 68.44 | 7. | Errection Work | 1.00 Job | 85.91 | 1.00 Job | 1.00 Job | 15.62 | 85.91 | 8. | PCC in Foundation | 22.44 cum | 1.16 | 22.44 cum | 22.44 cum | 0.21 | 1.16 | 9. | Fabrication Work | 1.00 job | 243.60 | 1.00 job | 1.00 job | 44.28 | 243.60 | 10. | Abutment Substructure RHS | 1.00 Job | 11.11 | 1.00 Job | 1.00 Job | 2.02 | 11.11 | 11. | Abutment Substructure LHS | 1.00 Job | 11.11 | 1.00 Job | 1.00 Job | 2.02 | 11.11 | 12. | Fixing Bearing/Slab Casting | 1.00 job | 26.39 | 1.00 job | 1.00 job | 4.8 | 26.39 | 13. | Wearing Coat | 27.84 Cum | 3.14 | 27.84 Cum | 27.84 Cum | 0.57 | 3.14 |
Total Amount: |
550.15 |
|
100 |
550.15 |
|
Remarks:
No Remarks
Work Program Made On:
21-10-2020
Updation of work program on:
21-09-2021
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 18-December-2020 | 24.72 lakhs |
2. | 25-March-2021 | 281.92 lakhs |
3. | 25-June-2021 | 84.17 lakhs |
4. | 31-August-2021 | 20.18 lakhs |
5. | 27-September-2021 | 115.21 lakhs |
6. | 02-November-2021 | 20.33 lakhs |
7. | 17-January-2022 | 23.74 lakhs |
8. | 31-May-2022 | 34.21 lakhs |
Total |
604.48 lakhs |
% Payment |
100 % |
|
Advance Amount: 55.13 lakhs
Recovered Amount: 10.13 lakhs
Balance to be Recovered 45.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 109 |
No Notice issued. |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 01-05-2022 | Kaliraw bridge Dehradun | Joint inspection with AE and JE PWD Dehradun | Sudhir Kumar | ` | ` | See Pic |
2. | 06-04-2022 | Kaliraw bridge BR57 | Final Measurement Checking | Sudhir Kumar | ` | ` | See Pic |
3. | 31-01-2022 | Kaliraw KM-10 BR-57 Bridge | Kaliraw Bridge downstream to upstream | Suresh Prasad | ` | ` | See Pic |
4. | 31-01-2022 | Kaliraw BR-57 Sahastradhara | Kaliraw KM-10 BR-57 Bridge | Suresh Prasad | ` | ` | See Pic |
5. | 31-01-2022 | Kaliraw KM-10 BR-57 | Kaliraw KM-10 Bridge Dehradun to Sahastradhara | Suresh Prasad | ` | ` | See Pic |
6. | 31-01-2022 | Kaliraw BR-57 Bridge completed | Kaliraw bridge Upstream to downstream | Suresh Prasad | ` | ` | See Pic |
7. | 31-01-2022 | Km 10 | Kaliraw bridge | Ashish bhatt | ` | ` | See Pic |
8. | 16-12-2021 | Kaliraw KM-10 (BR-57) | Bridge and approach road are committed | Suresh Prasad | ` | ` | See Pic |
9. | 26-11-2021 | Kaliraw KM-10 BR-57 | Bridge work completed and approach road in progress | Suresh Prasad | ` | ` | See Pic |
10. | 26-11-2021 | Kaliraw KM-10 BR-57 | Approach road completed LHS side | Suresh Prasad | ` | ` | See Pic |
11. | 10-11-2021 | Kaliraw KM-10 BR-57 | Curing of Approach slab A1 Side | Suresh Prasad | ` | ` | See Pic |
12. | 08-11-2021 | Kaliraw bridge Dehradun | Approach Slab Completed | Sudhir Kumar | ` | ` | See Pic |
13. | 04-11-2021 | Kaliraw KM-10 BR-57 | Painting work in progress for crash Barrier and Steel Truss Bridge | Suresh Prasad | ` | ` | See Pic |
14. | 04-11-2021 | Kaliraw KM-10 BR-57 | Reinforcement laying and binding work in progress for Approach slab A2 side (RHS) | Suresh Prasad | ` | ` | See Pic |
15. | 04-11-2021 | Kaliraw KM-10 BR-57 | Dirt wall with Expansion A2 side casting M-30 | Suresh Prasad | ` | ` | See Pic |
16. | 19-10-2021 | Kaliraw bridge Dehradun | Laying of Wearing Coat M30 | Sudhir Kumar | ` | ` | See Pic |
17. | 16-10-2021 | Kaliraw KM-10 BR-57 | Wearing coat Casting M-30 | Suresh Prasad | ` | ` | See Pic |
18. | 05-10-2021 | Kaliraw KM-10 BR-57 A2 side | Dirt wall A2 Casting M-35 in progress | Suresh Prasad | ` | ` | See Pic |
19. | 29-09-2021 | Kaliraw bridge Dehradun | Concrete work in progress for raft of RCC Wall in A1 side Kaliraw Bridge Dehradun | Sudhir Kumar | ` | ` | See Pic |
20. | 29-09-2021 | Kaliraw bridge Dehradun | Measurement Checking of Steel in Raft for RCC wall at A2 side Kaliraw Bridge Dehradun | Sudhir Kumar | ` | ` | See Pic |
|
|