Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/57 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 622 Package Name: UDRP/AF/BR/57 Sanction Cost: 688.00  lakhs
District: Dehradun Block: Kalsi Constituency: Chakrata Circle:
DEA: DEA Tehri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4094   48 Mtr span bridge steel truss motor bridge over kali raw river in km -10. (48.000 M.) (completed)
Procurement:
Package No.: 622        Package Name: UDRP/AF/BR/57        Tender Date: 26-09-2019        Current Status: Agreement signed        Achieved on Date: 22-01-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/57        Contractor Name: M/S.ARKS Universal pvt.ltd       
Start Date: 01-02-2020        Intended Completion Date: 24-12-2021        Original End Date:  30-04-2021
Total Bond Cost: 61746413.36 (617.46 lakhs)        Variation Cost: -1297008.54 (-12.97 lakhs)     Hence Total Bond Cost is   60449404.82 (604.49 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 13275390 for 430 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job9.031.00 Job1.00 Job1.649.03
2.Foundation RHS1.00 Job7.211.00 Job1.00 Job1.317.21
3.Foundation LHS1.00 Job7.211.00 Job1.00 Job1.317.21
4.Steel Railing/crush barrier99.00 m3.9999.00 m99.00 m0.733.99
5.Approach Ramp /path 214.00 m71.85214.00 m214.00 m13.0671.85
6.Protection Work1.00 Job68.441.00 Job1.00 Job12.4468.44
7.Errection Work1.00 Job85.911.00 Job1.00 Job15.6285.91
8.PCC in Foundation22.44 cum1.1622.44 cum22.44 cum0.211.16
9.Fabrication Work1.00 job243.601.00 job1.00 job44.28243.60
10.Abutment Substructure RHS1.00 Job11.111.00 Job1.00 Job2.0211.11
11.Abutment Substructure LHS1.00 Job11.111.00 Job1.00 Job2.0211.11
12.Fixing Bearing/Slab Casting1.00 job26.391.00 job1.00 job4.826.39
13.Wearing Coat27.84 Cum3.1427.84 Cum27.84 Cum0.573.14
Total Amount: 550.15 100   550.15
Remarks: No Remarks       Work Program Made On: 21-10-2020       Updation of work program on: 21-09-2021      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.18-December-202024.72  lakhs
2.25-March-2021281.92  lakhs
3.25-June-202184.17  lakhs
4.31-August-202120.18  lakhs
5.27-September-2021115.21  lakhs
6.02-November-202120.33  lakhs
7.17-January-202223.74  lakhs
8.31-May-202234.21  lakhs
Total 604.48  lakhs
% Payment 100 %
Advance Amount:  55.13  lakhs        Recovered Amount:  10.13  lakhs        Balance to be Recovered  45.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 336     No. of Test Done : 336      No. of Test Passed : 336      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 109
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.01-05-2022Kaliraw bridge DehradunJoint inspection with AE and JE PWD DehradunSudhir Kumar ` ` See Pic
2.06-04-2022Kaliraw bridge BR57Final Measurement CheckingSudhir Kumar ` ` See Pic
3.31-01-2022Kaliraw KM-10 BR-57 BridgeKaliraw Bridge downstream to upstreamSuresh Prasad ` ` See Pic
4.31-01-2022Kaliraw BR-57 SahastradharaKaliraw KM-10 BR-57 BridgeSuresh Prasad ` ` See Pic
5.31-01-2022Kaliraw KM-10 BR-57Kaliraw KM-10 Bridge Dehradun to SahastradharaSuresh Prasad ` ` See Pic
6.31-01-2022Kaliraw BR-57 Bridge completedKaliraw bridge Upstream to downstreamSuresh Prasad ` ` See Pic
7.31-01-2022Km 10Kaliraw bridgeAshish bhatt ` ` See Pic
8.16-12-2021Kaliraw KM-10 (BR-57)Bridge and approach road are committedSuresh Prasad ` ` See Pic
9.26-11-2021Kaliraw KM-10 BR-57Bridge work completed and approach road in progressSuresh Prasad ` ` See Pic
10.26-11-2021Kaliraw KM-10 BR-57Approach road completed LHS sideSuresh Prasad ` ` See Pic
11.10-11-2021Kaliraw KM-10 BR-57Curing of Approach slab A1 SideSuresh Prasad ` ` See Pic
12.08-11-2021Kaliraw bridge DehradunApproach Slab CompletedSudhir Kumar ` ` See Pic
13.04-11-2021Kaliraw KM-10 BR-57Painting work in progress for crash Barrier and Steel Truss BridgeSuresh Prasad ` ` See Pic
14.04-11-2021Kaliraw KM-10 BR-57Reinforcement laying and binding work in progress for Approach slab A2 side (RHS)Suresh Prasad ` ` See Pic
15.04-11-2021Kaliraw KM-10 BR-57Dirt wall with Expansion A2 side casting M-30Suresh Prasad ` ` See Pic
16.19-10-2021Kaliraw bridge DehradunLaying of Wearing Coat M30Sudhir Kumar ` ` See Pic
17.16-10-2021Kaliraw KM-10 BR-57Wearing coat Casting M-30Suresh Prasad ` ` See Pic
18.05-10-2021Kaliraw KM-10 BR-57 A2 sideDirt wall A2 Casting M-35 in progressSuresh Prasad ` ` See Pic
19.29-09-2021Kaliraw bridge DehradunConcrete work in progress for raft of RCC Wall in A1 side Kaliraw Bridge DehradunSudhir Kumar ` ` See Pic
20.29-09-2021Kaliraw bridge DehradunMeasurement Checking of Steel in Raft for RCC wall at A2 side Kaliraw Bridge DehradunSudhir Kumar ` ` See Pic