Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/57 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 622 Package Name: UDRP/AF/BR/57 Sanction Cost: 688.00  lakhs
District: Dehradun Block: Kalsi Constituency: Chakrata Circle:
DEA: DEA Tehri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4094   48 Mtr span bridge steel truss motor bridge over kali raw river in km -10. (48.000 M.) (in prorgress)
Procurement:
Package No.: 622        Package Name: UDRP/AF/BR/57        Tender Date: 26-09-2019        Current Status: Agreement signed        Achieved on Date: 22-01-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/57        Contractor Name: M/S.ARKS Universal pvt.ltd       
Start Date: 01-02-2020        Intended Completion Date: 04-11-2021        Original End Date:  30-04-2021
Total Bond Cost: 61746413.36 (617.46 lakhs)        Variation Cost: -1137798.13 (-11.38 lakhs)     Hence Total Bond Cost is   60608615.23 (606.09 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 13275390 for 430 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job9.030.00 Job0.00 Job00.00
2.Foundation RHS1.00 Job7.211.00 Job1.00 Job1.317.21
3.Foundation LHS1.00 Job7.211.00 Job1.00 Job1.317.21
4.Steel Railing/crush barrier99.00 m3.9999.00 m48.00 m0.351.93
5.Approach Ramp /path 214.00 m71.850.00 m0.00 m00.00
6.Protection Work1.00 Job68.441.00 Job0.50 Job6.2234.22
7.Errection Work1.00 Job85.911.00 Job1.00 Job15.6285.91
8.PCC in Foundation22.44 cum1.1622.44 cum22.44 cum0.211.16
9.Fabrication Work1.00 job243.601.00 job1.00 job44.28243.60
10.Abutment Substructure RHS1.00 Job11.111.00 Job1.00 Job2.0211.11
11.Abutment Substructure LHS1.00 Job11.111.00 Job1.00 Job2.0211.11
12.Fixing Bearing/Slab Casting1.00 job26.391.00 job1.00 job4.826.39
13.Wearing Coat27.84 Cum3.1427.84 Cum27.84 Cum0.573.14
Total Amount: 550.15 78.7   432.99
Remarks: No Remarks       Work Program Made On: 21-10-2020       Updation of work program on: 21-09-2021      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.18-December-202024.72  lakhs
2.25-March-2021281.92  lakhs
3.25-June-202184.17  lakhs
4.31-August-202120.18  lakhs
5.27-September-2021115.21  lakhs
Total 526.2  lakhs
% Payment 86.82 %
Advance Amount:  55.13  lakhs        Recovered Amount:  10.13  lakhs        Balance to be Recovered  45.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Environment & Social Compliances(Package level):No Pending Issue
Environment & Social Compliances(Sub Project level):
48 Mtr span bridge steel truss motor bridge over kali raw river in km -10.(4094) water sprinkling
48 Mtr span bridge steel truss motor bridge over kali raw river in km -10.(4094) water sprinkling
Detailed report of this Package
Quality
No. of Test Required : 269     No. of Test Done : 269      No. of Test Passed : 269      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 101
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.26-11-2021Kaliraw KM-10 BR-57Bridge work completed and approach road in progressSuresh Prasad ` ` See Pic
2.26-11-2021Kaliraw KM-10 BR-57Approach road completed LHS sideSuresh Prasad ` ` See Pic
3.10-11-2021Kaliraw KM-10 BR-57Curing of Approach slab A1 SideSuresh Prasad ` ` See Pic
4.08-11-2021Kaliraw bridge DehradunApproach Slab CompletedSudhir Kumar ` ` See Pic
5.04-11-2021Kaliraw KM-10 BR-57Painting work in progress for crash Barrier and Steel Truss BridgeSuresh Prasad ` ` See Pic
6.04-11-2021Kaliraw KM-10 BR-57Reinforcement laying and binding work in progress for Approach slab A2 side (RHS)Suresh Prasad ` ` See Pic
7.04-11-2021Kaliraw KM-10 BR-57Dirt wall with Expansion A2 side casting M-30Suresh Prasad ` ` See Pic
8.19-10-2021Kaliraw bridge DehradunLaying of Wearing Coat M30Sudhir Kumar ` ` See Pic
9.16-10-2021Kaliraw KM-10 BR-57Wearing coat Casting M-30Suresh Prasad ` ` See Pic
10.05-10-2021Kaliraw KM-10 BR-57 A2 sideDirt wall A2 Casting M-35 in progressSuresh Prasad ` ` See Pic
11.29-09-2021Kaliraw bridge DehradunConcrete work in progress for raft of RCC Wall in A1 side Kaliraw Bridge DehradunSudhir Kumar ` ` See Pic
12.29-09-2021Kaliraw bridge DehradunMeasurement Checking of Steel in Raft for RCC wall at A2 side Kaliraw Bridge DehradunSudhir Kumar ` ` See Pic
13.25-09-2021Kaliraw KM-10 (BR-57)Crash Barrier casting M-40 D/S in progressSuresh Prasad ` ` See Pic
14.25-09-2021Kaliraw KM-10 BR-57Deck Slab Shuttering and Reinforcement with Expansion Joint work completedSuresh Prasad ` ` See Pic
15.25-09-2021Km 10Casting of crash barrier (d/s)Ashish bhatt ` ` See Pic
16.25-09-2021Kaliraw KM-10 (BR-57)Protection work for river bankSuresh Prasad ` ` See Pic
17.02-09-2021Kaliraw KM-10Torque checking HSFG 10.9 grade 20mm diameter BoltSuresh Prasad ` ` See Pic
18.02-09-2021Kaliraw KM-10Reinforcement laying and binding for deck slabSuresh Prasad ` ` See Pic
19.02-09-2021Kaliraw KM-10Deck Slab Shuttering work in progressSuresh Prasad ` ` See Pic
20.01-09-2021Kaliraw bridge DehradunSite inspection by CE SirSudhir Kumar ` ` See Pic