Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/47 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 620 Package Name: UDRP/AF/BR/47 Sanction Cost: 987.07  lakhs
District: Pithoragarh Block: 0049 Constituency: 42 Circle:
DEA: DEA Munsyari DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4139   70 Mtr span motor bridge at Km-166 of Munshiyari motor road at hardiya nala. (70.000 M.) (in prorgress)
Procurement:
Package No.: 620        Package Name: UDRP/AF/BR/47        Tender Date: 21-09-2019        Current Status: Agreement signed        Achieved on Date: 20-01-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/47        Contractor Name: M/S.G.S.Matiyani and sons       
Start Date: 27-01-2020        Intended Completion Date: 18-12-2021        Original End Date:  26-07-2021
Total Bond Cost: 86310066.23 (863.1 lakhs)        Variation Cost: 10856369.38 (108.56 lakhs)     Hence Total Bond Cost is   97166435.61 (971.66 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 25893000 for 600 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job152.941.00 Job0.30 Job5.3245.88
2.Foundation RHS1.00 Job0.481.00 Job1.00 Job0.060.48
3.Foundation LHS1.00 Job2.191.00 Job1.00 Job0.252.19
4.Fixing of chequered Plate/RCC Deck609.45 sqm24.89609.45 sqm0.00 sqm00.00
5.Steel Railing/crush barrier143.40 m9.15143.40 m0.00 m00.00
6.Approach Ramp /path 100.00 m53.15100.00 m65.00 m434.55
7.Protection Work1.00 Job24.401.00 Job0.85 Job2.420.74
8.Errection Work1.00 Job119.341.00 Job0.00 Job00.00
9.Fabrication Work1.00 job387.851.00 job1.00 job44.94387.85
10.Abutment Substructure RHS1.00 Job18.031.00 Job1.00 Job2.0918.03
11.Abutment Substructure LHS1.00 Job70.681.00 Job1.00 Job8.1970.68
Total Amount: 863.1 67.25   580.4
Remarks: No Remarks       Work Program Made On: 06-05-2020       Updation of work program on: 03-08-2021      
Work Program Status:Work Programme workable.
Financial Progress
SNo. Date Payment
1.29-October-202061.17  lakhs
2.08-December-202023.68  lakhs
3.30-January-202129.80  lakhs
4.31-March-202127.57  lakhs
5.06-May-202140.44  lakhs
6.27-July-202125.04  lakhs
7.28-August-202122.45  lakhs
8.21-September-2021353.40  lakhs
9.09-November-202160.77  lakhs
Total 644.32  lakhs
% Payment 66.31 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 522     No. of Test Done : 624      No. of Test Passed : 624      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 173
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.26-11-2021Haradiya NalaBack filling work in progressShoyab aliunknownunknown See Pic
2.26-11-2021Haradiya NalaBack filling work in progressShoyab aliunknownunknown See Pic
3.25-11-2021Haradiya NalaT/W masonary work in progressShoyab aliunknownunknown See Pic
4.25-11-2021Haradiya NalaT/W masonary work in progressShoyab aliunknownunknown See Pic
5.25-11-2021Haradiya NalaBack filling work in progressShoyab aliunknownunknown See Pic
6.25-11-2021Haradiya NalaBack filling work in progressShoyab aliunknownunknown See Pic
7.25-11-2021Haradiya NalaBack filling work in progressShoyab aliunknownunknown See Pic
8.25-11-2021Haradiya NalaBack filling work in progressShoyab aliunknownunknown See Pic
9.25-11-2021Haradiya NalaBack filling work in progressShoyab aliunknownunknown See Pic
10.25-11-2021Haradiya NalaBack filling work in progressShoyab aliunknownunknown See Pic
11.21-11-2021At siteMaterial shifting from yard to siteShoyab aliunknownunknown See Pic
12.21-11-2021At siteMaterial shifting from yard to siteShoyab aliunknownunknown See Pic
13.20-11-2021Haradiya NalaSlip clearance work in progressShoyab aliunknownunknown See Pic
14.20-11-2021Haradiya NalaSlip clearance work in progressShoyab aliunknownunknown See Pic
15.20-11-2021Haradiya NalaSlip clearance in progressShoyab aliunknownunknown See Pic
16.20-11-2021Haradiya NalaT/W masonary work in progressShoyab aliunknownunknown See Pic
17.18-11-2021Abutment RHSHP filling behind abutment.Neeraj Tewari ` ` See Pic
18.18-11-2021Abutment LHSRCC of Cap completedNeeraj Tewari ` ` See Pic
19.18-11-2021Abutment LHSRCC work of R/wallNeeraj Tewari ` ` See Pic
20.18-11-2021RHS Approach RoadStone Masonary work.Neeraj Tewari ` ` See Pic