UDRP/AF/44(BR)
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
619 |
Package Name: |
UDRP/AF/44(BR) |
Sanction Cost: |
352.44 lakhs |
District: |
Bageshwar |
Block: |
Bageshwar |
Constituency: |
Bageshwar |
Circle: |
|
DEA: |
DEA Bageshwar |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4137 42 mtr spam motor bridge at km 6 of bhyun guler MR ( M.) (in prorgress) |
|
Procurement: |
Package No.: 619
Package Name: UDRP/AF/44(BR)
Tender Date: 21-09-2019
Current Status: Agreement signed
Achieved on Date: 20-01-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/44(BR)
Contractor Name: M/S.Dalip Singh Adhikari
|
Start Date: 27-01-2020
Intended Completion Date: 11-10-2022
Original End Date: 26-04-2021
|
Total Bond Cost: 33208174.53 (332.08 lakhs)
Variation Cost: -462595.56 (-4.63 lakhs) Hence Total Bond Cost is 32745578.97 (327.46 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 12037900 for 725 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Env. Man & Moni Plan | 1.00 Job | 2.61 | 1.00 Job | 1.00 Job | 0.79 | 2.61 | 2. | Other Allied Works & Finishing Work | 1.00 Job | 3.38 | 1.00 Job | 1.00 Job | 1.03 | 3.38 | 3. | Foundation RHS | 1.00 Job | 18.26 | 1.00 Job | 1.00 Job | 5.54 | 18.26 | 4. | Foundation LHS | 1.00 Job | 18.26 | 1.00 Job | 1.00 Job | 5.54 | 18.26 | 5. | Abutment Superstructure RHS | 1.00 Job | 0.52 | 0.00 Job | 0.00 Job | 0 | 0.00 | 6. | Abutment Superstructure LHS | 1.00 Job | 0.52 | 0.00 Job | 0.00 Job | 0 | 0.00 | 7. | Fixing of chequered Plate/RCC Deck | 55.40 sqm | 18.65 | 55.40 sqm | 0.00 sqm | 0 | 0.00 | 8. | Steel Railing/crush barrier | 93.00 m | 4.90 | 93.00 m | 0.00 m | 0 | 0.00 | 9. | Approach Ramp /path | 50.00 m | 42.02 | 50.00 m | 50.00 m | 12.75 | 42.02 | 10. | Protection Work | 1.00 Job | 39.38 | 1.00 Job | 1.00 Job | 11.95 | 39.38 | 11. | Errection Work | 1.00 Job | 45.32 | 1.00 Job | 1.00 Job | 13.75 | 45.32 | 12. | Fabrication Work | 1.00 job | 77.16 | 1.00 job | 1.00 job | 23.41 | 77.16 | 13. | Abutment Substructure RHS | 1.00 Job | 29.32 | 1.00 Job | 1.00 Job | 8.89 | 29.32 | 14. | Abutment Substructure LHS | 1.00 Job | 29.32 | 1.00 Job | 1.00 Job | 8.89 | 29.32 |
Total Amount: |
329.62 |
|
92.54 |
305.03 |
|
Remarks:
No Remarks
Work Program Made On:
10-06-2020
Updation of work program on:
22-05-2022
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 23-December-2020 | 49.49 lakhs |
2. | 29-May-2021 | 60.99 lakhs |
3. | 31-May-2022 | 88.66 lakhs |
4. | 15-June-2022 | 24.24 lakhs |
5. | 10-January-2023 | 85.21 lakhs |
Total |
308.59 lakhs |
% Payment |
94.24 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | No Pending Issue | Environment & Social Compliances(Sub Project level): | 42 mtr spam motor bridge at km 6 of bhyun guler MR(4137) | water sprinkling |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 159 |
No Notice issued. |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 21-05-2022 | Bhyun Guler motor road BR-44 | Erection work is in progress | Sarvesh chandra nautiyal | ` | ` | See Pic |
2. | 21-05-2022 | Bhyun Guler motor road BR-44 | Erection work is in progress | Sarvesh chandra nautiyal | ` | ` | See Pic |
3. | 17-05-2022 | 4137 | Erection work is in progress | Sarvesh Chandra nautiyal | ` | ` | See Pic |
4. | 17-05-2022 | Bhyun Guler motor road BR-44 | Erection work is in progress | Sarvesh Chandra nautiyal | ` | ` | See Pic |
5. | 04-05-2022 | Bhyun Guler motor road BR-44 | Erection work is in progress | Sarvesh chandra nautiyal | ` | ` | See Pic |
6. | 17-01-2022 | Bhyun Guler (BR-44), KM-6, District-Bageshwar | Bhyun Guler (BR-44), KM-6, District-Bageshwar | Lalit Kumar (SS) | ` | ` | See Pic |
7. | 17-01-2022 | Bhyun Guler (BR-44), KM-6, District-Bageshwar | Bhyun Guler (BR-44), KM-6, District-Bageshwar | Lalit Kumar (SS) | ` | ` | See Pic |
8. | 23-11-2021 | Bhyun Guler (BR-44), KM-6, District-Bageshwar | Bhyun Guler (BR-44), KM-6, District-Bageshwar | Lalit Kumar (SS) | ` | ` | See Pic |
9. | 23-11-2021 | Bhyun Guler (BR-44), KM-6, District-Bageshwar | Bhyun Guler (BR-44), KM-6, District-Bageshwar | Lalit Kumar SS | ` | ` | See Pic |
10. | 23-11-2021 | Bhyun Guler (BR-44), KM-6, District-Bageshwar | Bhyun Guler (BR-44), KM-6, District-Bageshwar | Lalit Kumar SS | ` | ` | See Pic |
11. | 27-10-2021 | Bhyun Guler BR-44, KM-6, District-Bageshwar | Abutment A1 side Abutment cap casting work has been completed. | Lalit Kumar (SS) | ` | ` | See Pic |
12. | 27-10-2021 | Bhyun Guler BR-44, KM-6, District-Bageshwar | Abutment A1 side Abutment cap casting work has been completed. | Lalit Kumar (SS) | ` | ` | See Pic |
13. | 27-10-2021 | Bhyun guler motor road BR 44 | R.h.s abutment cap casting work is in progress | Sarvesh chandra nautiyal | ` | ` | See Pic |
14. | 27-10-2021 | Bhyun guler motor road BR 44 | R.h.s abutment Cap casting work is in progress | Sarvesh chandra nautiyal | ` | ` | See Pic |
15. | 21-09-2021 | Bhyun Guler BR-44, KM-6, District-Bageshwar | Abutment A2 side Cap casting work is in progress. | Lalit Kumar (SS) | ` | ` | See Pic |
16. | 21-09-2021 | Bhyun Guler motor road BR 44 | L.h.s abutment cap casting work is in progress | Sarvesh chandra nautiyal | ` | ` | See Pic |
17. | 21-09-2021 | Bhyun Guler motor road BR 44 | L.h.s abutment cap casting work in in progress | Sarvesh chandra nautiyal | ` | ` | See Pic |
18. | 27-08-2021 | Bhyun Guler BR-44, KM-6, District-Bageshwar | Abutment A1 side filter media work is in progress. | Lalit Kumar (SS) | ` | ` | See Pic |
19. | 27-08-2021 | Bhyun Guler BR-44, KM-6, District-Bageshwar | Abutment A2 side return wall LHS side 2nd lift of toe wall work is in progress. | Lalit Kumar (SS) | ` | ` | See Pic |
20. | 27-08-2021 | Bhyun Guler BR-44, KM-6, District-Bageshwar | Abutment A2 side return wall LHS side 2nd lift of toe wall work is in progress. | Lalit Kumar (SS) | ` | ` | See Pic |
|
|