Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/44(BR) Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 619 Package Name: UDRP/AF/44(BR) Sanction Cost: 352.44  lakhs
District: Bageshwar Block: Bageshwar Constituency: Bageshwar Circle:
DEA: DEA Bageshwar DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4137   42 mtr spam motor bridge at km 6 of bhyun guler MR ( M.) (in prorgress)
Procurement:
Package No.: 619        Package Name: UDRP/AF/44(BR)        Tender Date: 21-09-2019        Current Status: Agreement signed        Achieved on Date: 20-01-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/44(BR)        Contractor Name: M/S.Dalip Singh Adhikari       
Start Date: 27-01-2020        Intended Completion Date: 16-08-2021        Original End Date:  26-04-2021
Total Bond Cost: 33208174.53 (332.08 lakhs)        Variation Cost: -247848.87 (-2.48 lakhs)     Hence Total Bond Cost is   32960325.66 (329.6 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 9530696 for 574 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Env. Man & Moni Plan1.00 Job2.611.00 Job1.00 Job0.794.21
2.Other Allied Works & Finishing Work 1.00 Job3.381.00 Job0.65 Job0.672.20
3.Foundation RHS1.00 Job18.261.00 Job1.00 Job5.5414.70
4.Foundation LHS1.00 Job18.261.00 Job1.00 Job5.5414.70
5.Abutment Superstructure RHS1.00 Job0.520.00 Job0.00 Job00.00
6.Abutment Superstructure LHS1.00 Job0.520.00 Job0.00 Job00.00
7.Fixing of chequered Plate/RCC Deck55.40 sqm18.6555.40 sqm0.00 sqm00.00
8.Steel Railing/crush barrier93.00 m4.9093.00 m0.00 m00.00
9.Approach Ramp /path 50.00 m42.0250.00 m16.00 m4.0813.45
10.Protection Work1.00 Job39.381.00 Job0.82 Job9.832.29
11.Errection Work1.00 Job45.321.00 Job0.00 Job00.00
12.Fabrication Work1.00 job77.161.00 job0.00 job00.00
13.Abutment Substructure RHS1.00 Job29.321.00 Job1.00 Job8.8930.89
14.Abutment Substructure LHS1.00 Job29.321.00 Job1.00 Job8.8930.89
Total Amount: 329.62 44.2   143.33
Remarks: No Remarks       Work Program Made On: 10-06-2020       Updation of work program on: 02-09-2021      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.23-December-202049.49  lakhs
2.29-May-202160.99  lakhs
Total 110.48  lakhs
% Payment 33.52 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Environment & Social Compliances(Package level):No Pending Issue
Environment & Social Compliances(Sub Project level):
42 mtr spam motor bridge at km 6 of bhyun guler MR(4137) water sprinkling
Detailed report of this Package
Quality
No. of Test Required : 235     No. of Test Done : 236      No. of Test Passed : 235      No. of Test Failed : 1   Test report of this package
Number of Pics Available on Web Repository: 152
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-11-2021Bhyun Guler (BR-44), KM-6, District-BageshwarBhyun Guler (BR-44), KM-6, District-BageshwarLalit Kumar (SS) ` ` See Pic
2.23-11-2021Bhyun Guler (BR-44), KM-6, District-BageshwarBhyun Guler (BR-44), KM-6, District-BageshwarLalit Kumar SS ` ` See Pic
3.23-11-2021Bhyun Guler (BR-44), KM-6, District-BageshwarBhyun Guler (BR-44), KM-6, District-BageshwarLalit Kumar SS ` ` See Pic
4.27-10-2021Bhyun Guler BR-44, KM-6, District-BageshwarAbutment A1 side Abutment cap casting work has been completed.Lalit Kumar (SS) ` ` See Pic
5.27-10-2021Bhyun Guler BR-44, KM-6, District-BageshwarAbutment A1 side Abutment cap casting work has been completed.Lalit Kumar (SS) ` ` See Pic
6.27-10-2021Bhyun guler motor road BR 44R.h.s abutment cap casting work is in progressSarvesh chandra nautiyal ` ` See Pic
7.27-10-2021Bhyun guler motor road BR 44R.h.s abutment Cap casting work is in progressSarvesh chandra nautiyal ` ` See Pic
8.21-09-2021Bhyun Guler BR-44, KM-6, District-BageshwarAbutment A2 side Cap casting work is in progress.Lalit Kumar (SS) ` ` See Pic
9.21-09-2021Bhyun Guler motor road BR 44L.h.s abutment cap casting work is in progressSarvesh chandra nautiyal ` ` See Pic
10.21-09-2021Bhyun Guler motor road BR 44L.h.s abutment cap casting work in in progressSarvesh chandra nautiyal ` ` See Pic
11.27-08-2021Bhyun Guler BR-44, KM-6, District-BageshwarAbutment A1 side filter media work is in progress.Lalit Kumar (SS) ` ` See Pic
12.27-08-2021Bhyun Guler BR-44, KM-6, District-BageshwarAbutment A2 side return wall LHS side 2nd lift of toe wall work is in progress.Lalit Kumar (SS) ` ` See Pic
13.27-08-2021Bhyun Guler BR-44, KM-6, District-BageshwarAbutment A2 side return wall LHS side 2nd lift of toe wall work is in progress.Lalit Kumar (SS) ` ` See Pic
14.27-08-2021Bhyun Guler BR-44, KM-6, District-BageshwarAbutment A1 side filter media work is in progress.Lalit Kumar (SS) ` ` See Pic
15.25-08-2021Bhyun Guler BR-44, KM-6, District-BageshwarAbutment A2 side return wall LHS side 1st lift of toe wall work is in progress.Lalit Kumar (SS) ` ` See Pic
16.25-08-2021Bhyun Guler BR-44, KM-6, District-BageshwarAbutment A2 side return wall LHS side 1st lift of toe wall work is in progress.Lalit Kumar (SS) ` ` See Pic
17.16-08-2021Bhyun Guler (BR-44), KM-6, District-BageshwarAbutment A1 side RR wall work.Lalit Kumar (SS) ` ` See Pic
18.04-08-2021Bhyun Guler (BR-44), KM-6 District-BageshwarAbutment A1 side toe wall work is in progress.Lalit Kumar (SS) ` ` See Pic
19.04-08-2021Bhyun Guler (BR-44), KM-6 District-BageshwarAbutment A1 side toe wall work is in progress.Lalit Kumar (SS) ` ` See Pic
20.30-07-2021Bhyun Guler BR-44, KM-6, District-BageshwarLabour health and safety training at site.Lalit Kumar (SS) ` ` See Pic