Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/41 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 618 Package Name: UDRP/AF/BR/41 Sanction Cost: 228.19  lakhs
District: Uttarkashi Block: Dunda Constituency: Gangotri Circle:
DEA: DEA Uttarkashi DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4070   Bridge at KM-1 of Dhauntari Kamad MR (24.000 M.) (completed)
Procurement:
Package No.: 618        Package Name: UDRP/AF/BR/41        Tender Date: 02-09-2019        Current Status: Agreement signed        Achieved on Date: 11-06-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/41        Contractor Name: Anil Mehta       
Start Date: 01-07-2020        Intended Completion Date: 03-02-2022        Original End Date:  30-09-2021
Total Bond Cost: 19940526.2 (199.41 lakhs)        Variation Cost: 934564.65 (9.35 lakhs)     Hence Total Bond Cost is   20875090.85 (208.75 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 219340 for 22 days        LD Analysis for Milestone2: calculated LD is Rs 697900 for 70 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job6.331.00 Job1.00 Job3.566.33
2.Foundation RHS1.00 Job7.051.00 Job1.00 Job3.967.05
3.Foundation LHS1.00 Job7.051.00 Job1.00 Job3.967.05
4.Abutment Superstructure RHS1.00 Job10.051.00 Job1.00 Job5.6410.05
5.Abutment Superstructure LHS1.00 Job10.051.00 Job1.00 Job5.6410.05
6.Fixing of chequered Plate/RCC Deck1.00 sqm10.971.00 sqm1.00 sqm6.1610.97
7.Steel Railing/crush barrier96.00 m3.7196.00 m96.00 m2.083.71
8.Approach Ramp /path 1.00 m46.801.00 m1.00 m26.2946.80
9.Protection Work1.00 Job28.431.00 Job1.00 Job15.9728.43
10.Errection Work1.00 Job17.511.00 Job1.00 Job9.8317.51
11.Fabrication Work1.00 job28.261.00 job1.00 job15.8728.26
12.Fixing Bearing/Slab Casting4.00 job1.854.00 job4.00 job1.041.85
Total Amount: 178.06 100   178.06
Remarks: No Remarks       Work Program Made On: 04-02-2021       Updation of work program on: 03-08-2021      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.23-January-202147.31  lakhs
2.30-March-20219.16  lakhs
3.23-June-202134.04  lakhs
4.03-August-202122.68  lakhs
5.07-September-202114.45  lakhs
6.20-January-202223.55  lakhs
7.24-February-202211.48  lakhs
8.31-May-202245.72  lakhs
Total 208.39  lakhs
% Payment 99.82 %
Advance Amount:  12.03  lakhs        Recovered Amount:  12.03  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 532     No. of Test Done : 674      No. of Test Passed : 667      No. of Test Failed : 7   Test report of this package
Number of Pics Available on Web Repository: 169
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.14-05-2022Dhauntri KamadCompleteAjay Singh Rana ` ` See Pic
2.13-05-202224m span Motor bridge Dhauntri KamadPainting completeAjay Singh Rana ` ` See Pic
3.12-05-2022Dhauntri-KamadCompletedAjay Singh Rana ` ` See Pic
4.11-05-2022Bagigaon Gajna bridle bridgeComplete painting workAjay Singh Rana ` ` See Pic
5.06-05-2022Dhauntri kamad 24m span motor bridgePainting work completedAjay Singh Rana ` ` See Pic
6.22-01-2022Dhauntri kamad km1Curing For Dack slab At dhauntri kamad motor bridge BR 41Deepak ` ` See Pic
7.31-12-2021BR/41Deck slab curring work in progress.Niraj pathak ` ` See Pic
8.23-12-2021Br 41 dhauntri kamad bridge deck castingDeck slab casting in progressArun kumar RE ` ` See Pic
9.20-12-2021BR/41Deck slab concrete sampling done.concrete grade,M35.Niraj pathak ` ` See Pic
10.20-12-2021BR/41Deck slab concrete sampling work in progress. Concrete grade M35.Niraj pathak ` ` See Pic
11.20-12-2021BR/41Deck slab concrete.slump test on progress, concrete grade M35.Niraj pathak ` ` See Pic
12.20-12-2021BR/41Slump test on progress. Concrete grade M35.deck slabNiraj pathak ` ` See Pic
13.20-12-2021BR/41Course aggregate gradation test on progress.Niraj pathak ` ` See Pic
14.20-12-2021Dhautri kamad bridgeDeck slab work is on progress of M-35 gradeAE Pawan Kumarunknownunknown See Pic
15.20-12-2021Dhautri-kamad bridgeSlump test of deck slab M-35 GradeAE Pawan Kumarunknownunknown See Pic
16.09-12-2021Dhauntri kamada km1Dirtwall casting A1 side at dhauntri kamad motor bridge BR/41Deepak ` ` See Pic
17.09-12-2021Dhauntri kamad km1Cube casting for Dirtwall A1 side At dhauntri kamad motor bridge BR/41Deepak ` ` See Pic
18.01-12-2021Dhauntri kamad km1Dirt wall concrete A1 side at dhauntri kamad motor bridge BR/41Deepak ` ` See Pic
19.25-11-2021Dhauntri kamad motor bridgeDeck slab shuttering work on progressAjay Singh Rana ` ` See Pic
20.24-11-2021BR/41A1,A2, pedestal concrete sampling work in progress.concrete grade M40.Niraj pathak ` ` See Pic