Package Profile Report

UDRP/AF/BR/40 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 617 Package Name: UDRP/AF/BR/40 Sanction Cost: 265.16  lakhs
District: Bageshwar Block: Kapkot Constituency: Kapkote Circle:
DEA: DEA Bageshwar DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4056   Bridge on Sangad Vasti Motor Road KM-5 (24.000 M.) (completed)
Procurement:
Package No.: 617        Package Name: UDRP/AF/BR/40        Tender Date: 02-09-2019        Current Status: Agreement signed        Achieved on Date: 07-02-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/40        Contractor Name: M/S.KGL Infrastructure       
Start Date: 15-02-2020        Intended Completion Date: 18-11-2021        Original End Date:  14-05-2021
Total Bond Cost: 28163186.45 (281.63 lakhs)        Variation Cost: -68440.10 (-0.68 lakhs)     Hence Total Bond Cost is   28094746.35 (280.95 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 6167916 for 438 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Env. Man & Moni Plan1.00 Job4.931.00 Job1.00 Job1.754.93
2.Other Allied Works & Finishing Work 1.00 Job2.291.00 Job1.00 Job0.812.29
3.Foundation RHS1.00 Job9.821.00 Job1.00 Job3.499.82
4.Foundation LHS1.00 Job9.821.00 Job1.00 Job3.499.82
5.Abutment Superstructure RHS1.00 Job45.431.00 Job1.00 Job16.1345.43
6.Abutment Superstructure LHS1.00 Job45.431.00 Job1.00 Job16.1345.43
7.Fixing of chequered Plate/RCC Deck126.00 sqm16.09126.00 sqm126.00 sqm5.7116.09
8.Steel Railing/crush barrier48.00 m4.1448.00 m48.00 m1.474.14
9.Approach Ramp /path 100.00 m42.50100.00 m100.00 m15.0942.50
10.Protection Work1.00 Job31.431.00 Job1.00 Job11.1631.43
11.Errection Work1.00 Job32.661.00 Job1.00 Job11.632.66
12.Fabrication Work1.00 job37.111.00 job1.00 job13.1837.11
Total Amount: 281.65 100   281.65
Remarks: No Remarks       Work Program Made On: 07-07-2020       Updation of work program on: 19-10-2020      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.29-October-202057.82  lakhs
2.26-December-202036.03  lakhs
3.30-March-202123.86  lakhs
4.21-June-202189.94  lakhs
5.18-December-202113.63  lakhs
6.29-March-202259.66  lakhs
Total 280.94  lakhs
% Payment 100 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 229     No. of Test Done : 230      No. of Test Passed : 229      No. of Test Failed : 1   Test report of this package
Number of Pics Available on Web Repository: 227
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.20-01-2022SANGAD-VASTI KM-5 BR-40Site view of SANGAD-VASTI Motor-Road bridge KM-5Anurag SinghR.E. UDRP-AF SB DSC Bageshwar See Pic
2.20-01-2022SANGAD-VASTI BR-40 Motor-Road bridge KM-5Approach road of LHSAnurag SinghR.E. UDRP-AF SB DSC Bageshwar See Pic
3.20-01-2022SANGAD-VASTI BR-40 Motor-Road bridge KM-5RR WALL HILL Protection work of D/S (LHS)Anurag SinghR.E. UDRP-AF SB DSC Bageshwar See Pic
4.20-01-2022SANGAD-VASTI BR-40 Motor-Road bridge KM-5Veiw of Bridge structuresAnurag SinghR.E. UDRP-AF SB DSC Bageshwar See Pic
5.20-01-2022SANGAD-VASTI Motor-Road bridge KM-5 BR-40.Side view of bridge from U/SAnurag SinghR.E. UDRP-AF SB DSC Bageshwar See Pic
6.20-01-2022SANGAD-VASTI Motor-Road bridge KM-5, BR-40View of bridge with protection work from LHSAnurag SinghR.E. UDRP-AF SB DSC Bageshwar See Pic
7.20-01-2022SANGAD-VASTI Motor-Road bridge KM-5 BR-40Approach road at RHS with RR wall protection workAnurag SinghR.E. UDRP-AF SB DSC Bageshwar See Pic
8.20-01-2022SANGAD-VASTI Motor-Road bridge KM-5 BR-40View of bottom super Structure with abutment at LHSAnurag SinghR.E. UDRP-AF SB DSC Bageshwar See Pic
9.20-01-2022SANGAD-VASTI Motor-Road bridge KM-5, BR-40View of bridge from D/SAnurag SinghR.E. UDRP-AF SB DSC Bageshwar See Pic
10.20-01-2022SANGAD-VASTI Motor-Road bridge KM-5 BR-40Bottom view of super structure with RHS abutmentAnurag SinghR.E. UDRP-AF SB DSC Bageshwar See Pic
11.20-01-2022SANGAD-VASTI Motor-Road bridge KM-5 BR-40Bridge view of RHSAnurag SinghR.E. UDRP-AF SB DSC Bageshwar See Pic
12.20-01-2022SANGAD-VASTI Motor-Road bridge KM-5 BR-40View of bridge from RHSAnurag SinghR.E. UDRP-AF SB DSC Bageshwar See Pic
13.20-01-2022SANGAD-VASTI Motor-Road bridge KM-5 BR-40Top view of bridgeAnurag SinghR.E. UDRP-AF SB DSC Bageshwar See Pic
14.17-01-202224 mtr span steel girder bridge Sangad vasti km5After painting work Bridge photographMukesh Kumar ` ` See Pic
15.17-01-202224 mtr span steel girder bridge at Sangad basti MR km 5Bridge completion pictureJagdish narayan meena ` ` See Pic
16.17-01-202224 mtr span steel girder bridge at Sangad basti MR km 5Bridge completion pictureJagdish narayan meena ` ` See Pic
17.17-01-202224 mtr span steel girder bridge at Sangad basti MR km 5Bridge completion pictureJagdish narayan meena ` ` See Pic
18.17-01-202224 mtr span steel girder bridge at Sangad basti MR km 5LHS side bridge completion pictureJagdish narayan meena ` ` See Pic
19.17-01-202224 mtr span steel girder bridge at Sangad basti MR km 5LHS side bridge completion pictureJagdish narayan meena ` ` See Pic
20.17-01-202224 mtr span steel girder bridge at Sangad basti MR km 5Picture after completionJagdish narayan meena ` ` See Pic